HomeMy WebLinkAboutR-79-0457" SU1P P RT!VE
DOCUn iEN i ,~S
1a .
FOLLOW"
RESOLUTION NO.
7.9-457
A RESOLUTION ACCEPTING THE COMPLETED
WORK OF SCOPE CONSTRUCTION, INC. AND
INSURANCE COMPANY OF NORTH AMERICA'
FOR AFRICAN SQUARE PARK AT A TOTAL
COST OF;$427,651.b0; AUTHORIZING AN
INCREASE INTHE CONTRACT IN THE NET
AMOUNT OF $4,140..20; ASSESSING
$8,700.00 AS LIQUIDATED DAMAGES FOR
87 DAYS OVERRUN OF CONTRACT TIME;
AND AUTHORIZING A FINAL .PAYMENT OF
$38,791.20'TO SCOPE CONSTRUCTION, INC.
AND INSURANCE COMPANY OF NORTH AMERICA
FOR AFRICAN SQUARE PARK
WHEREAS,
1977 between
and
and
there exists a contract dated March
the City of Miami and Scope Construction
WHEREAS.
he work
has
been satisfactorily
completed,
Construction, Inc. and Insurance Company of:North
America have furnished the required documents certifying
that all bilis for labor and materials have been paid in';.
Scope
full in connection with the aforesaid contrac
WHEREAS, there was an overrun of the contrac
; and
amount for extra work authorized by the City Manager,; which
resulted in an increase in the contract;; and
WHEREAS, liquidated damages for 87 days overrun o
contract time should be deducted from the final payment due
the contractor and the insurance company; and
WHEREAS, the City Manager and the
Public Works recommend
and final payment made
company;
that
Department of
the completed work be accepted
contractor and the insurance
"DOCUMENT INDEX
BE IT RESOLVED' BY+ THE 'COMM' SION
theto,
NOW, THEREFORE,
OF THE CITY OF MIAMI, FLORIDA:.
Section 1. The completed work performed by Scope.
Construction, Inc. and Insurance Company of North America is
hereby accepted at a total cost of $427 651.00.
Section
.' The amount.
of the contract
increased in the amount of $4,140.20.
is;hereby
cn-i COMMISSION
MEETING OF
"JUN2 5 197Y
ilESOUMON 79 ' 4 5
Matt
Section
f $8,700.00 for 8
3. The liquidated damages in the amount
7 overrun of contract time shall be
days
deducted `from .the balance due the contractor and; the insurance
company.
Section
4. The proper officials of The City
Miami are hereby authorized to pay
Scope Construction,
nc.
and InsuranceCompany of North'America, after all adjustments
are made, a balance of $38791.20 as full and final payment,
for all work performed and allmaterials furnished' in.
connection with AFRICAN SQUARE PARK.
PASSED AND ADOPTED this 25th day. of June.
1979.'.
Maurice ,A. Terre
ATTEST:
Rali G.'Ongie, City . Clerk
PREPARED. AND`;. APPROVED BY:
Assis.tantCity Attorney
APPROVED AS TO FORM AND CORRECTNESS'
City
ttorney.
MAURICE'A FERRE.
MAYOR,.
"SUPPORTIVE
DOCUMENTS
FOLLOW,,
- 2 -
79-457
5l
Joseph R. Grassie,
City Manager
DonaldW. Cather
Director
Dena tment ofPubl
WRrks
June 8,
1979
B-2642-A
AFRICAN SQUARE PARK -
Resolution to Increase; Contract
and Assess Liquidated;Damages
(For Commission Meeting
June_'25, 1979.)
Scope Construction,; Inc. and Insurance Company of North
America have completed the project consisting of the con-
struction of a park at the southwest corner. of N. W. 62
Street (MartinLuther King Boulevard) and N. W..14.Avenue.
The construction includes a comfort station, administration
building, an amphitheater,,playground equipment, and a
basketball court. This was a lump sum contract in the
amount of $427,651.00, but there was. an overrUfl of the
contract amount for extra work authorized by the City
Manager in the amount of $4,140.20, less liquidated damages.
for87 days overrun of contract in the amount of $8,700.00.'.
It is now in order for the Commission to accept the com-
pleted work and authorize final payment, after all con-
ditions are met.
THE DEPARTMENT OF PUBLIC WORKS RECOMMENDS THE ADOPTION OF
A RESOLUTION ACCEPTING THE COMPLETED WORK PERFORMED BY
SCOPE CONSTRUCTION, INC. AND INSURANCE COMPANY OF NORTH
AMERICA AT A TOTAL COST OF;$427651.00; INCREASING THE
CONTRACT IN THE AMOUNT OF $4,140.20;:ASSESSING $8,700.00
AS LIQUIDATED DAMAGES FOR OVERRUN OF CONTRACT TIME;. AND
AUTHORIZING A FINAL PAYMENT OF $38,791.20 TO SCOPE
CONSTRUCTION, INC.; AND INSURANCE COMPANY OF NORTH AMERICA
FOR AFRICAN SQUARE PARK.
JAH :hc`
SUPPORTIVE
rn{```
-' 45'7
L
1
CONTRACTOR
JOB SCOPE
REASON,
FOR WORK
SOURCE OF'
FUNDS.
PROJECT:
HISTORY
CONTRACT
TIME
STARTED
CONTRACT
TIME: —
SCHEDULED
COMPLETION
DATE
ACTUAL:
COMPLETION.
DATE
BID AMOUNT
CONTRACT,
FINAL COST
CURRENT,:
ITEM FOR
CONSIDERATION
FINAL CONSTRUCTION FACT SHEET
FOR THE CITY MANAGER
African Square. Park B-2642-A
Scope Construction, Inc..
Development of a park at the S..W, corner of N. W.
62nd Street (Martin L. King Blvd.) and 14th.Avenue
complete :'with a comfort station, administration
building and amphitheatre.
• Part :'of. -parks.. -program as approved by the voters on
March 14, 1972
ADDITIONAL._
INFORMATION_
Bids Received: 2/9/77
Contract Awarded:2/24/77.
Preconstruction Meeting 3/22/77
4/18/77
120 Working ; days
21 days allowed for rain and 63 days
for delay in delivery of materials.
2/28/78
6/16/78
87: calendar', days: overrun.- of contract,•
tine
•The Consultant:recommends,`• assessment :of
$8,700liquidated damages.
,140 •20 Overrun of Contract °Amount to
791..20 be paid:::from liquidated damages
Resolution:. to accept the completed work,. increase the
amount of :contract by $4,140-.20,assess. liquida.ted
damages of $8,700.00,•.and authorize final 'payment to
the contractor, and the bonding company.
Work was completed on the. project on 6/16/78. The
contractor was unable to pay all of his subcontractors
and material suppliers and, his. bonding company. had -:to
take over. The bonding.` company, Insurance Company of
North America, has now reached an agreeinent with the
Law Department that indernnifles the City against all
claims and, allows 'Us to snake final payment on the'
project.