RESOLUTION NO. 79 - 8 4 $
A RESOLUTION ACCEPTING THE COMPLETED WORK
PERFORMED BY T AND N CONSTRUCTION COMPANY,
INC. AT A TOTAL COST OF $55,585.98 FOR
CULMER SANITARY SEWER MODIFICATIONS
PHASE III; AND AUTHORIZING A FINAL
PAYMENT OF $3,308.60
WHEREAS, there exists a contract dated April
1979 between
Company
the City of Miami and T and N Construction
26,
Inc.; and
WHEREAS, the work has been satisfactorily completed
and T and N Construction Company, Inc has furnished the
required documents certifying that all bills for labor and
materials have been paid in full in connection` with the
aforesaid contract; and
WHEREAS, the City Manager and the Department of
Public Works recommend that the completed work be accepted
and final payment made to the contractor;
NOW, THEREFORE, BE IT RESOLVEDCaI Mich
Y OF MIAMI, FLORIDA: ITEM NO.
OF THE CIT
Section 1 The completed work performed by T and N
Construction Company, Inc. for CULMER SANITARY SEWER MODIFICATIONS
PHASE III at a total cost of $55,585.98 is hereby approved.
Section 2. The proper officials of the City of
Miami are hereby authorized to pay $3,308.60 as full and
final payment for all work performed and all materials
furnished in connection with CULMER SANITARY SEWER
MODIFICATIONS - PHASE III.
PASSED AND ADOPTED this 5th day ofDecember; , 1979.
Maurice A. Ferre
ATTT: MAYOR
C:1751 (2112'' ('
R LONGIE,CITY CLE4iC
A
PREPARED AND APPROVED BY:
Jg"
ROBERT F. CLARK GEOR
ASSISTANT CITY ATTORNEY CITY
AP D AS T
-41
ORD AND CORRECTNESS
F. KNO
TTORNEY
CITY COMMISSION
MEETING OF
OFC 5 1979
7 9 - 84E
RESOLUTION NO.................,,�.,,
MANS:
t
Joseph R. Grassie
City Manager
Donald W. Cather.
Di ector
November 19, 1979
B-5459
CULMER SANITARY SEWER
MODIFICATIONS PHASE III -
Resolution for Final Payment
(For Commission Meeting
of December 13, 1979)
orks
The Department of Public Works recommends
the adoption of the resolution accepting
the completed work and authorizing a
final payment of $3,308.60 to T and N
Construction Company, Inc. for CULMER
SANITARY SEWER MODIFICATIONS - PHASE III..
T and N Construction Company, Inc. has completed the
modifications to the existing sanitary sewer system on
N. W. 2 Avenue between N. W. 11 Terrace and N. W. 14
Street, and on N. W. 14 Terrace between N. W. 2 and 3
Avenues. The original contract amount was for $63,447.60,
but the completed amount is $55,585.98, and it was
completed on time.
It is now in order for the Commission to accept the
completed work: and authorize final payment, after all
conditions are met.
jerH:hc
solution attached
G
FOL Liv/S
1-0
`79-846
FINAL CONSTRUCTION FACT SHEET
FOR THE CITY MANAGER
JOB NAME Culmer Sanitary Sewer Modifications Phase III B-5459
CONTRACTOR T & N Construction Co.
JOB SCOPE Modifications to existing sanitary sewage system on
N. W. 2 Avenue .between N. W. 11 Terrace and N. W. 14
Street and on N. W. 14 Terrace between N. W. 2-3 Avenues
REASON
FOR WORK
SOURCE OF.
FUNDS
In conjunction with paving project..
Fourth Year Federal Community Development Block Grant
Fund
PROJECT Bids Received: 4/10/79
HISTORY Contract Awarded: 4/19/79
Preconstruction Meeting: 5/21/79
CONTRACT
TIME
STARTED 6/11/79
CONTRACT
TIME
SCHEDULED
COMPLETION
DATE
30 Working days
7/23/79
ACTUAL
COIMPLETION
DATE 7/10/79
BID AMOUNT $ 63, 447.60
CONTRACT
FINAL COST
CURRENT
ITEM FOR
CONSIDERATION
$ 55,585.98
Resolution to accept completed work and authorize
final payment to the contractor.
79-846