RESOLUTION No. 8 0- 3 5 8
A RESOLUTION ACCEPTING THE C014PLETED WORK
OF MIRI CONSTRUCTION, INC. AT A TOTAL
COST OF $137,973.57 FOR CULMER COMMUNITY
DEVELOPMENT PAVING PROJECT - PHASE, III -
BID "A" (HIGHWAYS); AND AUTHORIZING A
FINAL PAYMENT OF $15,720.09
WHEREAS, there exists a contract dated May 2,
1979 between the City of Miami and Miri Construction,
Inc.; and
WHEREAS, the work has been satisfactorily
completed, and Miri Construction, Inc. has furnished the
required documents certifying that all bills for labor
and materials have been paid in full in connection with
the aforesaid contract; and
WHEREAS, the City Manager and the Department of
Public Works recommend that the completed work be accepted
and final payment made to the contractor;
NOW, THEREFORE, BE IT RESOLVED BY THE COMMISSION
OF THE CITY OF MIAMI, FLORIDA:
Section 1. The completed work performed by Miri
Construction, Inc. for CULMER COMMUNITY DEVELOPMENT PAVING
PROJECT - PHASE III - BID "A" (HIGHWAYS.1 .4.t,. a..t�)te1 0 t
of $137,973.57 is hereby approved.
I1T�E-M. N.G. -- - --
Section 2. The proper officials of the City of
Miami are hereby authorized to pay $15,720.09 to Miri
Construction, Inc. as full and final payment for all work
performed and all materials furnished in connection with
CULMER COMMUNITY DEVELOPMENT PAVING PROJECT - PHASE III -
BID "A" (HIGHWAYS).
PASSED AND ADOPTED this 8 day of MAY , 1980.
A ST : _n, J 0
city Cleric
PREPAH ') A:?:) i1I'IAPPR
MAURICE A. FERRE
M A Y O R
S TO FORM[ AND"ViORRECTNESS :
ty AttNne,y
80-358
Joseph R. Grassie
City Manager
Donald W. Cather
J}i-rector of, Pub,14c orks
April 24, 1980 B-4.440-A
CULMER COMMUNITY DEVELOPMENT
PAVING PROJECT - PHASE III -
BID "A" (HIGH, -LAYS) -
Resolution for Final Payment
•. i. F ...
(For Commission Meeting
IN -L0 of May 8, 1980)
The Department of Public Works recommends
the adoption of the resolution accepting
the completed work and authorizing a final
payment of $15,720.09 to Miri Construction,
Inc. for CULMMER COMMUNITY DEVELOP 1ENT
PAVING PROJECT - PHASE III - BID "A"
(Highways).
Miri Construction, Inc. has completed the project con-
sisting of constructing approximately 0.4 miles of
streets within 30'-50' rights -of -way, including asphaltic
concrete pavement, curbs and gutters, sidewalk, storm
sewer molifications, and landscapin:_,. Th> project is
bounded by N. 'r1. 2-3 Avenues bet-ar ?en N'. W. 11 'Terrace
and N. W. 14 Terrace. The oriFina.l contract amount was
for $147,5'37.50, anri the completed amount is $137,973.57.
It was completed on time.
It is now in order for the Commission to accept the
completed wort: and authorize final payment, after all
conditions are met.
-i:hc
L4 esolution attached
Its qPP0RT1V'p
14T r/
FOL . ` `-
80-358
FA
FINAL CONSTRUCTION FACT SHEET
FOR THE CITY MPNAGER
JOB NAME Culmer Community Development Paving Project
Phase III (Bid "A" - Highways) - B-4440
CONTRACTOR Miri Construction, Inc.
JOB SCOPE Construct 0.4 mile of streets within 30' to 50'
rights of way includin- asphaltic concrete pave-
ment, curbs and cutters, sidewalk, storm sewer
modifications, and landscaping; in an area bounded
by N. W. 2-3 Avenues between N. W. 11 Terrace and
N. W. 14 Terrace.
REASON
FOR WORK. Rebuild deteriorated streets.
SOURCE
OF FUNDS Fourth Year Federal Community Development
Block Grant Fund
PROJECT Bids Received: 4/10/79
HISTORY Contract Awarded: 4/19/79
Preconstruction Meeting: 5/21/79
CONTRACT
TI"^E
STARTED 8/13/79
C0ITRACT
TII,?E 50 Working days plus 9 days delay due to rain.
SCHEDULED
COMPLETI0I1
DATE 11/5/79
ACTUAL
CO11'1PLETIOII
DATE 11/5/79
BID AMOUNT $ 1479597.50
CONTRACT
FILIAL -COST $ 137,973.57
CURRENT
ITEIN FOR
CONSIDERATION
Resolution to accept completed work and authorize
final payment to the contractor.