HomeMy WebLinkAboutO-09280AN ORDINANCE AMENDING SECTION 53-151
OF THE CODE OF THE CITY OF MIAMI, FLORIDA
(1980) AS AMENDED, WHICH PERTAINS TO
PROCEDURES AND USE CHARGES AT THE MUNI-
CIPAL AUDITORIUM AND COCONUT GROVE
EXHIBITION CENTER BY INCREASING CERTAIN
SPECIFIED FEES DETERMINED BY THE TYPE
OF EVENT BEING HELD; CONTAINING A REPEALER
PROVISION AND A SEVERABILITY CLAUSE.
WHEREAS, a review of the Coconut Grove Exhibition Center
rate structures and schedules reflects that an increase in rates
is necessary to reduce the huge operating deficit which has
resulted from large fixed -operation costs and spiraling inflation;
NOW, THEREFORE, BE IT ORDAINED BY THE COMMISSION OF THE CITY
OF MIAMI, FLORIDA:
Section 1. Section 53-151 of the Code of the City of Miami,
Florida (1980) as amended, is hereby further amended in the
l/
following particulars:
"Sec. 53-151. City Auditoriums -use rates and reservation
'3 requirements, setup costs, move -in and move -out
charges.
(1) MUNICIPAL AUDITORIUM USE RATE SCHEDULE:
(a) Trade shows, exhibitions, consumer shows:
�t
(2) COCONUT GROVE EXHIBITION CENTER RENTAL SCHEDULE:
R
w (a) Trade shows, exhibitions, consumer shows:
(i) Main Hall and West ExhibitrArea:
-------------------------------------------------------------------
l/ Words stricken through shall be deleted. Underscored words
constitute the amendment proposed. Remaining provisions
are now in effect and remain unchanged. Asterisks indicate
omitted and unchanged material..
a. 'Three-day scheduled
shoo or less —
Per square foot used
$ 0.30
Minimum guarantee
per show .........
A WQ-09 7 , 000.00
b. Four -day through six -
day scheduled show —
Per square foot used
0.35
Minimum guarantee
per show .........
.6,609•09 8, 000.00
c. Shows exceeding six
(6) days in scheduled
length —an addition-
al charge of ene-
two thousand
dollars ($2 , 000. 00)
-&ed• - dellers• - W ,-699. -
-00) per scheduled day
will be added to the
above minimum charge
per show.
(ii)
Mezzanine:
Per square foot used ....
$ _&M 0.25
Minimum guarantee per
day if no other Center
area is used ..........
-%00.00 1,200,00
If used in conjunction
with the Main Hall, per
day ..................
300;00 6 0 0 0 0
(iii)
Courtyard:
Per square foot used .....
$ -O:Ufi 0.20
Minimum guarantee per
day, flat .............
-&00:00 800.00
Maximum payment per
day if used in conjunc-
tion with the Main
Hall .................
WOM 500 -00
(iv)
Main Hall:
a. Three-day scheduled
show or less —
Per square foot used
$ 0.30
Minimum guarantee
per show .........
?;500.06 6,000.00
b. Four -day through six.
day scheduled show —
Per square foot used
0.35
Minimum guarantee
per show .........
47OOAA9- 6,500.00
c. Shows exceeding six
(6) days in scheduled
length —an addition.
al charge of one
thousand &14ae s{$l,-
five hundred
4)09.99) per scheduled
do I I ars ,'500 .00 )
day will be added to
the above minimum
charge per show.
(v)
West Exhibit Area:
a. Three-day scheduled
show or less —
Per square foot used
$ 0.30
Minimum guarantee
per show .........
_21d99G.00 4,000.00
-2-
V. $2ao
4
ifid.flSny`
"5'�L� it • A
b. Four -day through
six -day scheduled
show —
her square foot used 0.30
Minimum guarantee
per show ......... 21699.9Q 4,500.00
c. Shows exceeding six
(6) days in scheduled
length —an addition-
al charge of-shcharr- one thousand two hundred
died-d-(4k►f9-W0G.@R)- 'dollars
($1 , 20.0 )
per scheduled day
will be added to the
above minimum
charge per show.
NO Promenade Area (the
parking lot area be-
tween the south side
of the exhibition cen-
ter and Biscayne
Bay), per day, flat... $2A4.94
500.00
(b) Public admission events:
(i) Main Hall and West Exhibit
IArea,
single performance—$3,000.00,
6,500.00
or 10 percent of ticket sales, whichev-
er is greater.
(ii) Main Hall, single performance—$2,-
5,000.00
-500-00-or 10 percent of ticket sales,
whichever is greater.
_
(iii) West Exhibit Area, single per -
forma nce---1-,506:06 3,000.00 or 10
percent of
ticket sales, whichever is' great er.
(iv) Mezzanine, single performance—
1,500.00
${A8-09 or 10 percent of ticket sales,
whichever is greater.
-
(v) Courtyard, single performance—
1,000.00
-
$&09.fl9,-or 10 pe?cent of ticket sales,
whichever is greater.
kc) Noncommercial, nonprofit:
(i) Main Hall, per day, flat . $2,400.00
4,000.00
(ii) West Exhibit Area, per
day, flat ............... t,200:00-
2,500.00
(iii) Mezzanine, per day, flat. -79&.G&
F , 2uuTuo
(iv) Courtyard, per day, flat 460:60-
ITU UFO
(B) Move -in or Move -out Charges. For
shows, exhibits and conventions of:
(1) One to 3 days in duration, two (2) days'
move -in and two (2) days' move -out at no
additional charge.
(2) Four or more days in duration, four (4)
days' move -in and three (3) days' move -
out at no additional charge.
Any additional time required is at the rate of
X;
one-half CAz) day's rental fee per day.
14
(C) Setup Costs for Labor:
'4f
(1) Chairs, each ............... $ Ad9
0.50
(2) Upholstered chairs (if avail-
able), each ................. 6.725
1.00
(3) Tables, each ............... 0.60
2.50
(4) Portable stage, per section .. ]0.00
15 A 0
- " -
'
80
E
(D) Miscellaneous Char es
1) There is a charge o 0 per hour
use of the air conditioner durin
move -in and/or move -out time.
TTie—charge for use of the golf cart
is 5.00 per day if requested.
E ectrical Lighting Trees ...... $ 75.00/day
Dimmer Pack 40.00/day"
Section 2. All ordinances or parts of ordinances in
conflict herewith, insofar as they are in conflict, are hereby
repealed.
Section 3. If any section, part of section, paragraph,
clause, phrase, or word of this ordinance is declared invalid, the
remaining provisions of this ordinance shall not be affected.
PASSED ON FIRST READING BY TITLE ONLY this 15th day
of
May , 1981.
PASSED AND ADOPTED ON SECOND READING BY TITLE ONLY this
day of June , 1981.
Z7
RALPH G. ONGIE, CITY CLERK
PREPARED AND APPROVED BY:
P'Z"( J
RO ERT F. CLERK
ASSISTANT CITY ATTORNEY
-4-
MAURICE A. FERRE
M A Y O R
40 Id
T A B L E IV
PROPOSED AND
EX IS TING RATES
FOR COCONUT GROVE
E X H I B I T I O N C E N
T E R
Public Admission Events
Main and west Exhibit Area
Main Hall
West Exhibit Area
Mezzanine
Courtyard
Existing -
Single performance $3,000
Single performance $2500
Single performance
Single performance
Single performance
or 10% of ticket sales,
or 10% of ticket sales,
$1,500 or 10% of ticket
$600 or 10% of ticket
$500 or 10% of tic -
whichever is greater
whichever is greater
sales, whichever is
sales, whichever is
ket sales, whichever
greater
greater
is greater
Proposed -
Single performance $6,500
Single performance
Single performance
Single performance
Single performance
or 10% of ticket sales,
$5,000 or 10% of
$3,000 or 10% of ticket
$1,500 or 10% of
$1,000 or 10% of
whichever is greater
ticket sales, whichever
sales, whichever is
ticket sales, whichever
ticket sales, which -
is greater
greater
is greater
ever is greater
Noncommercial, Nonprofit
Events
Existing -
$2,400 per day flat
$1,200 per day flat
$700 per day flat
$400 per day flat
Proposed -
$4,000 per day flat
$2,500 per day flat
$1,200 per day flat
$1,000 per day flat
0