A RESOLUTION ACCEPTING THE COMPLETED WORK
OF P.N.M. CORPORATION AT A TOTAL COST OF
$165,733.50 FOR BUENA VISTA COMMUNITY
DEVELOPMENT PAVING PROJECT - PHASE V (BID B -
DRAINAGE); AND AUTHORIZING A FINAL PAYMENT
OF $16,577.40
WHEREAS, there exists a contract dated December 22,
1980 between the City of Miami and P.N.M. Corporation; and
WHEREAS, the work has been satisfactorily completed,
and P.N.M. Corporation has furnished the required documents
certifying that all bills for labor and materials have been
paid in full in connection with the aforesaid contract; and
WHEREAS, the City Manager and the Department of
Public Works recommend that the completed work be accepted
and final payment made to the contractor;
NOW, THEREFORE, BE IT RESOLVED BY THE COMMISSION
OF THE CITY OF MIAMI, FLORIDA*
Section 1. The completed G;orl; performed by j'•TI•T1•
Cor,�oratioii for BUENA VISTA COIiI.1UNITY DEVELOPMENT PAVING
PROJECT - PHASE V (BID B - DRAINAGE) at a total cost of
$165,733.50 is hereby approved.
Section 2. The proper officials of the City of
Miami are hereby authorized to pay $16,577.40 to P.N.M.
Corporation as full and final payment for all work performed
and all materials furnished in connection with BUENA VISTA
COMMUNITY DEVELOPMENT PAVING PROJECT - PHASE V (BID B -
DRAINAGE).
PASSED AND ADOPTED this 11 day of FEBRUARY , 1982.
EST :
City Clerk
PREPARED AND APPROVED BY: APP
'64.T` C:(G
Deputy City Attorney
MAURICE A. FERRE
M A Y O R
AS TO FORM AND CORRECTNESS:
ity Atto
,fi+ MING OF
F E B 1 1 1982
2-14'
�otutaM '
r CITY CF MIAMI. FLORIDA
85' Ir4•r,ry•oF:-1_-r 7�I1:irJ:�AiVDIJ"�1 •
Hovrard V. Gary
SAT January 19, 1982 F!LE B-4 461
City Manager
su3JEc7 BUENA VISTA COI.7MUNITY
DEVELOPMENT PAVING PROJECT -
PHASE V (BID B - DRAINAGE) -
=��Donald W. Cather REV c RK;ii:E3Resolution for Final Payment
D'rector of Public ,.orks
f NCI_U:U RES (For Commission IZeet lrib
of February 11, 1982)
The Department of Public Works recommends
the adoption of the resolution acceptinto;
the completed work and authorizing a final
payment of $16,577.40 to P.N.M. Corporation
for BUENA VISTA COMMUNITY DEVELOPMENT
PAVING PROJECT - PHASE V (BID B - DRAINAGE).
P.N.M. Corporation has completed the project consisting
of constructing 1,879 feet of 36" french drain system in
11. 1.1. 5 Avenue between N. W. 46-54 Streets. This drainage
work is in conjunction with the street rebuilding of
iv. W. 5 Avenue. The original contract amount was for
$175,612.85, and the completed amount is $165,733.50. It
was completed on time.
It is noa in order for the Commission to accept the com-
pleted work and authorize final payment, after all cond_-
tions are met.
6e,
he
lution attached
m
82-143
FINAL CONSTRUCTION FACT SHEET
FOR THE CITY MANAGER
JOB NAIIE
Buena Vista Community Development Paving Project
Phase V (Bid "B" - Drainage) B-4461
CONTRACTOR
P.N.M. Corporation
JOB SCOPE
Construct 1879' of 36" French Drain System in
N. W. 5 Avenue between N. W. 46-54 Streets.
REASON
Eliminate drainage problems in conjunction with
FOR WORK
street rebuilding
SOURCE
OF FUNDS
Storm Sewer G. 0. Bond Fund
PROJECT
Bids Received: 12/2/80
HISTORY
Contract Awarded: 12/17/80
Preconstruction Meeting: 2/3/81
CONTRACT
T I ME
STARTED 3/30/81
CONTRACT
TIME 60 Vilorl:ing days
SCHEDULED
COMPLETION
DATE 6/22/81
ACTUAL
COMPLETION
DATE 6/16/81
BID Al�!OUNT $ 175,612.85
CONTRACT
FINAL COST $ 165,733.50
CURRENT
ITE?" FOR Resolution to accept completed work and authorize
COE'SIDERATION final payment to the contractor.
82-143