HomeMy WebLinkAboutR-82-0215RESOLUTION 140. 8 2- 2 1 5
A RESOLUTION CONFIRMING ASSESSMENT ROLL
FOR CONSTRUCTION OF SIDIPS014 SANITARY SEWER
IMPROVEMENT IN SIMPSON SANITARY SEWER
IMPROVEMENT DISTRICT SR-5391-5 (sideline
sewer); AND REMOVING ALL PENDING LIENS FOR
THIS IMPROVEMENT 140T HEREBY CERTIFIED.
WHEREAS, the Commission of The City of Miami,
Florida met on the llth day of March, 1982, pursuant to
due legal notice of said meeting under Section 56 of the
City Charter, as amended, to receive all written objec-
tions to the confirmation of the preliminary assessment
roll for the cost of SIMPS014 SANITARY SEWER IMPROVEMENT
in SIMPSON SANITARY SEWER IMPROVEMENT DISTRICT SR-5391-5
(sideline sewer) on the following streets:
S. E. 15 Road to S. E. 32 Road from
Brickell Avenue on the south to S. W.
First Avenue and South Dixie Highway
on the north
WHEREAS, no objections thereto by any person
interested in, or affected by, said assessments were sus-
tained by the Commission, and said assessment roll appeared,
in all respects, regular and in accordance with the require-
ments and provisions of the City Charter, as amended;
NOW, THEREFORE, BE IT RESOLVED BY THE COMMISSION
OF THE CITY OF MIAMI, FLORIDA:
Section 1. That the prima facie assessments, as
apportioned and indicated on the preliminary assessment
roll for SIMPSON SANITARY SEWER IMPROVEMENT in SIMPSON
SANITARY SEWER IMPROVEMENT DISTRICT SR-5391-5 (sideline
sewer) be, and they are hereby, in all things, confirmed
and sustained against any and all lots or parcels of
ground described therein.
CITY COMMISSION
MEETING OF
MAR 1 1 1982
82-21
MUMN NO...« ................,
MARKS :............................
Section 2. That the sums and amounts assessed
against each of the lots or parcels of ground in said
preliminary assessment roll are less than the amount that
each of the said lots or parcels of ;round is especially
benefited by said improvement and that such amounts are
in proportion to the special benefits that the property
received.
Section 3. That the total assessment cost of
said SIMPSON SANITARY SEWER IMPROVEMENT in SIMPSON
SANITARY SEWER IMPROVEMENT DISTRICT SR-5391-S (sideline
sewer) in the amount of $337,540.57 be, and the same is
hereby, approved and confirmed.
Section 4. That any pending lien in SIMPSON
SANITARY SEWER IMPROVEMENT in SIMPSON SANITARY SEWER
IMPROVEMENT DISTRICT SR-5391-S (sideline sewer) for
sanitary sewer improvements not appearing in the preliminary
assessment roll and not certified hereby, be, and the same
is hereby, cancelled and removed.
PASSED AND ADOPTED this 11 day of MARCH
1982.
MAURICE A. FERRE
M A Y O R
ATTEST:
Q
Cit Cler
REPARED AND APPROVED BY: APPROVED AS TO FORM AND CORRECT14ESS:
Deputy City Attorney City Xt.-torney""
i
- 2 - 82-215
M1
-� Howard V. Gary February 19, 1982 F B-5391
Cite Manager
SIMPS;011 SANITARY SEWER
Ii•iPROV�,.._.''T SR-5391-C&S -
Resolutions Confirming
Assessment Rolls
rROh+ Donald W. Cather
Dire or of Pu 'c orlcs (For Commission Meeting
of March 11, 1982)
The Department of Public Works recommends
the adoption of the attached resolutions
confirming the preliminary assessment rolls
for SI 1PSON SAN71LTARY S�.��'iER Ii•1PROVE:.-'dT in
SIIIPSON SANITARY SLiiER Ii-1PR. OVE1.1E'1T DISTRICT
SR-5391-C&S (centerline and sideline sewers).
Construction of SIMPSON SANITARY SE ,"IER IMPROVEii-..NT in
SI14PSON SANITARY SEWIIE'R IMPROVEi1BNT DISTRICT SR-5391-C&S
(centerline and sideline seeaers) has been completed,
and the preliminary assessment rolls for this improvement
are ready to be presented to the Commission for confirma-
tion. The construction of this sanitary serer improvement
;ras on the follo;vin streets:
S. E. 15 Road to S. Road fro::; riciceil
Avenue on the south to S. W. i"Irst Avenue
and South Dixie on the nr�rth
The total assessment cost of the centerline seerers amount
to 4113,703.79, and the total assessment cost of the side-
line sewers amount to $337,540.57.
A public hearin`; is sch .�dule�l for i•iarch 11, 1982 to hear
objections to confirmation of the assessment rolls. If
no objections are sustained, it Trill be in order for the
Commission to adopt the resolutions confirming; the assess-
ment rolls.
A section has been includ•�d cancelling, and removing_, pending
liens placed against properties not benetite•-1 by the im-
provement.
tic
6
Resolution-- attached
82-215
PUBLIC HEARING - ASSESSMENT ROLL
MEETING DATE: March ll, 1982
AGENDA ITE\,l NO.
MAP MADE: (Yes) (No)
Simpson Sanitary Sewer Imp. SR 5391 C&S
! JOB
i
S.E. 15 Road to S.W. 32 Road from Brickell Avenue on the south
LOCATION
+ o S. Dixie Highway & S.W. 1 Avenue on the north.
COST OF IMPROVEMENT:
Front foot (C/L)
Front foot (S/L)
Lateral C/L (Average)
Lateral S/L
Typical 50
Typical 50
ESTIMATED ACTUAL ASSESSED
$ 18.99 $ 20.91 $ 8.90
$ 45.27 $ 34.48 $ 19.53
$ 530.00 $ 319.26 $ 319.26
$ 15.00 $ 11.87 $ 11.87
$ 1,480 $ 1,365 $ 764
$ L,308 $ 1,760 $ 1,012
Number of parcels in District: 483
CONTRACTOR: Roenca Corporation
Amount $ 783,000 Final Cost $ 718,035
Started Work 5 Apr 76 Completed Work 16 Dec 76
lot (C/L)
lot (S/L)
PREVIOUS COMMISSION ACTION:
Ordered on 4 Sep 75 Confirmed on 9 Oct 75
Accepted work - Final Payment on 14 Jul 77
Confirmation of these assessment rolls has been delayed b
' REMARKS: Y v
Resolution 76-928 which held up collection of assessments until
July 1980, or pendirg condemnation of certain properties within the
districtby Metro for Rapid Transit, whichever came first.
Cost of incidental expenses is not included in estimated figures.
Prepared by E. M. Pelaez
Porm - PW M356 5172
g2-215