HomeMy WebLinkAboutR-82-0263RESOLUTION 140. 8 2- 2 6 3
A RESOLUTION ACCEPTING THE COMPLETED
WORK OF SUNSET ENTERPRISES, INC. AT A
TOTAL COST OF $39,478 FOR BELLE MEADE
ISLAND BRIDGE P40DIFICATIONS - 1981;
AND AUTHORIZING A FINAL PAYMENT OF
$4,495.
WHEREAS, there exists a contract dated August 10,
1981 between the City of Miami and Sunset Enterprises, Inc.;
and
WHEREAS, the work has been satisfactorily completed,
and Sunset Enterprises, Inc. has furnished the required
documents certifying that all bills for labor and materials
have been paid in full in connection with the aforesaid
contract; and
WHEREAS, the City Manager and the Department of
Public Works recommend that the completed work be accepted
and final payment made to the contractor;
14014, THEREFORE, BE IT RESOLVED BY THE C0I4MISSION
OF THE CITY OF MIAMI, FLORIDA:
Section 1. The completed work performed by Sunset
Enterprises, Inc. for BELLE MEADE ISLAND BRIDGE MODIFICATIONS -
1981 at a total cost of $39,478 is hereby approved.
Section 2. The proper officials of the City of
Miami are hereby authorized to pay $4,495 to Sunset Enterprises,
Inc. as full and final payment for all work performed and all
materials furnished in connection with BELLE MEADE ISLAND
BRIDGE MODIFICATIONS - 1981.
PASSED AND ADOPTED this 16 day of MARCH , 1982.
ATTEST:
eREP
ClerkARED AND APPROVED BY: APPRO
A-OL .�. &M
Deputy City Attorney
MAURICE A. FERRE
M A Y 0 R
AS TO
'FORM AND CORRECTNESS:
y AttzSP►—
CITY )COMMISSION
MEETING OF
MAR t 6 1982
82-26
ItMOT101t NO.....
r
i
._,r•r '.lta,Mt, rLcz10.,
52
Howard V. Gary February 19, 1982 -•L4 B-2830
City ^rIanacer
BELLE '-IEADE ISLAND BRIDGE
NODIFICA.1=71S - 1981 -
Resolution for Final Payment
Donald W. Cathe (For Commission Meeting
ector� Works of Narch 11, 1982)
The Department of Public Works recommends
the adoption of the resolution accepting
the completed work and authorizinc a final
payment of $4,495 to Sunset Enterprises,
Inc. for BELLE MEADS I5LAND BRIDGE
MODIFICATIONS - 1931.
Sunset Enterprises, Inc. has completed the project consisting
of making repairs to 16 existing pile; and replacing selected
wood decking on an existing; wood trestle bridge to the Island,
located at N. E. 9 Avenue and N. E. 76 Street. The original
_ contract amount was for $40,752, a unit price contract with
one lump sum item, includin, a $5,000 cash allowance for
special items. The completed a::nount is $39,473. It was
completed on time.
It is now in order for the Corutiission to acce t the completed
work and authorize final payment, after all conditions are
met.
L:hc
ir4C
solution attached
82-263
FI'll AL CONSTRUCTION FACT SHEET
FOR THE CITY 'LlAI AGF.R
JOB NAME Belle Meade Island Bridge Modifications - 1981 B-2830
CONTRACTOR Sunset Enterprises, Inc.
JOB SCOPE Make pile repairs and replace selected rood decking on
an existing wood trestle brad-e to Belle Meade Island
located at 11. E. 76 Street and N. E. 9 Avenue.
REASON
FOR WORK Reolace deteriorated wood
SOURCE
OF FUNDS High,ra-; General Obligation 3onds
PROJECT Bids Received: 7/13/81
HISTORY Contract Awarded: 7/23/81
Preconstruction I"eeting: 9/24/81
CONTRACT
T I ME
STARTED 10/13/81
CONTRACT
TIIiG 45 Working days plus 14 da,s delay due to tides.
SCHEDULED
CO'1PLETT0j
DATE 1/8/82
ACTUAL,
COMPLETION
DATE
BID AMOUI1T
CONTRACT
FINAL COST
CURRENT
ITEIM FOR
CONSIDERATION
1/8/82
$ 40,752.00
$ 39,478.00
Resolution to accept completed work and authorize
final payment to the contractor
82-263