HomeMy WebLinkAboutR-82-0405RESOLUTION NO.82 - 4 05�
A RESOLUTION ACCEPTING THE COMPLETED WORK
OF SUNSET ENTERPRISES, INC. AT A TOTAL
COST OF $26,445.00 FOR VIRRICK GYM - BOAT
RAMP MODIFICATIONS; AND AUTHORIZING A FINAL
PAYMENT OF $2,775.00
WHEREAS, there exists a contract dated November 17,
1981 between the City of Miami and Sunset Enterprises, Inc.;
and
WHEREAS, the work has been satisfactorily completed,
a
A and Sunset Enterprises, Inc. has furnished the required
documents certifying that all bills for labor and materials
KI
have been paid in full in connection with the aforesaid
contract; and
WHEREAS, the City Manager and the Department of
Public Works recommend that the completed work be accepted
-
and final payment made to the contractor;
NOW, THEREFORE, BE IT RESOLVED BY THE COMMISSION
OF THE CITY OF MIAMI, FLORIDA:
Section 1. The completed work performed by
�t
Sunset Enterprises, Inc. for VIRRICK GYM - BOAT RAMP MODIFI-
CATIONS at a total cost of $26,445.00 is hereby approved.
Section 2. The proper officials of the City of
Miami are hereby authorized to pay $2,775.00 to Sunset
Enterprises, Inc. as full and final payment for all work
?r" performed and all materials furnished in connection with
VIRRICK GYM - BOAT RAMP MODIFICATIONS.
5
PASSED AND ADOPTED this 11th day of May
1982.
ATTEST:
PREPARED AND APPROVED BY:
Deputy City Attorney
APPROVED AS TO FORM AND CORRECTNESS:
City torney
fill
Maurice A..Ferre
MAYOR_
- 2 -
■
82-405
CITY OF MIAMI, FLORIDA
11
3
INTER -OFFICE MEMORANDUM
C
To Howard V. Gary DATE April 28, 1982 r,;E B-2836
City Manager
VIRRICK GYM - BOAT RAMP
MODIFICATIONS - Resolution
for Final Payment
F R0M Donald W. Cather R E F E R E h•=ES
Director of Public Works (For Commission Meeting
of May 11, 1982)
The Department of Public Works recommends
the adoption of the resolution accepting
the completed work and authorizing a final
payment of $2,775.00 to Sunset Enterprises,
Inc. for VIRRICK GYM - BOAT RAMP MODIFI-
CATIONS.
Sunset Enterprises, Inc. has completed the project consisting
of rebuilding an existing boat ramp in order to better
utilize the facility located at 2600 S. Bayshore Drive. The
original contract amount was for $28,650.00, and the completed
:mount is $26,445.00. It was completed on time.
It is now in order for the Commission to accept the completed
work and authorize final payment, after all conditions'are met.
LEL:az
Reso on attached
CS ' 1 1 - "Z ddV Z81
��ti�1►i-cJ',iJl���'i rll
\ t
c
82-405
f
FINAL CONSTRUCTION FACT SHEET
FOR THE CITY MANAGER
JOB NAME Virrick Gym - Boat Ramp Modifications B-2836
CONTRACTOR Sunset Enterprises, Inc.
JOB SCOPE Rebuild existing boat ramp at 26DO S. Bayshore Drive.
REASON
FOR WORK To allow better utilization of facility.
0611jaoo
OF FUNDS Capital Improvement Fund
PROJECT Bids Received: 9/21/81
HISTORY Contract Awarded: 11/12/81
Preconstruction Meeting: 12/16/81
CONTRACT
TIME 3/l/82 (Contractor started work 2/2/82, prior to
STARTED receiving executed contract)
CONTRACT
TIME 30 Working Days
SCHEDULED
COMPLETION
DATE 4/9/82
ACTUAL
COMPLETION
DATE 3/2/82
BID AMOUNT $ 28,650.00
CONTRACT
FINAL COST $ 26,445.00
CURRENT
ITEM FOR Resolution to accept completed work and authorize
CONSIDERATION final payment to the contractor.
82-405
'0Y/a?/ 71:1-,