HomeMy WebLinkAboutR-82-0704RESOLUTION NO. Ei2--; Q
A RESOLUTION ACCEPTING THE COMPLETED WORK
OF R.J.L. TRADING COMPANY AT A TOTAL
COST OF $107,663.80 FOR WYNDWOOD COMMUNITY
DEVELOPMENT PAVING PROJECT - PHASE V -
BID "B" (DRAINAGE); AND AUTHORIZING A
FINAL PAYMENT OF $10,766.38.
WHEREAS, there exists a contract dated July 27,
1981 between the City of Miami and R.J.L. Trading Company;
and
WHEREAS, the work has been satisfactorily completed,
and R.J.L. Trading Company has furnished the required documents
certifying that all bills for labor and materials have been
paid in full in connection with the aforesaid contract; and
WHEREAS, the City Manager and the Department of
Public Works recommend that the completed work be accepted
and final payment made to the contractor;
NOW, THEREFORE, BE IT RESOLVED BY THE COMMISSION
OF THE CITY OF MIAMI, FLORIDA:
Section 1. The completed work performed by R.J.L.
Tradin-; Company for WYNDWOOD COMMUNITY DEVELOPMENT PAVING
PROJECT - PHASE V - BID "B" (DRAINAGE) at a total cost of
$107,663.80 is hereby approved.
Section 2. The proper officials of the City of
Miami are hereby authorized to pay $10,766.38 to R.J.L.
Trading Company as full and final payment for all work
performed and all materials furnished in connection with
WYNDWOOD COMMUNITY DEVELOPMENT PAVING PROJECT - PHASE V -
BID "B" (DRAINAGE).
CITY COMMISSION}- �
MEETING OF
J U L 2 2 1982
to
w
ouffiOt1 Hd.N �.`.� ....:.f
REOMW............................
PASSED AND ADOPTED this 22nd day of July
1982.
Maurice A. Ferre
M A Y 0 R
ATTEST:
A.. C T ItiG CITY CLERK
PREPARED AND APPROVED BY:
Deputy City Attorney
APPROVED AS TO FORM AND CORRECTNESS:
City torney
- 2 - FZ `7G a :
f,
FINAL CONSTRUCTION FACT SHEET
FOR THE CITY MANAGER
JOB NAME Wyynndwood Community Development Paving Project - Phase V
(Bid "B" - Drainage) - B-4467
CONTRACTOR R.J.L. Trading Company
JOB SCOPE Construct 1201' of Covered ditch drainage system in an
area bounded by N.W. 32-36 Streets between N. Miami
Avenue and N. W. 2 Avenue.
REASON Eliminate drainage problems in conjunction with street
FOR WORK rebuilding.
SOURCE
OF FUNDS Federal Community Development Block Grant Fund
PROJECT Bids Received: 7/7/81
HISTORY Contract Awarded: 7/23/81
Preconstruction Meeting: 8/24/81
CONTRACT
TIME
STARTED 11/27/81
CONTRACT
TIME 60 Working days
SCHEDULED
COMPLETION
DATE 2/23/82
ACTUAL
COMPLETION
DATE 2/8/82
BID AMOUNT $ 120,487.40
CONTRACT
FINAL COST
CURRENT
ITEM FOR
CONSIDERATION
$ 107,663.80
Resolution to accept completed work and authorize final
payment to the contractor.
VZ- 7 V w
TO Howard V. Gary
City Manager
`P°'' Donald W. Cather
Director of Publ
CITY OFF MIAMI. FLOPICA
INTER -OFFICE M=t•4ORAN0UM
::•� June 23, 1982 -+_F B-4467B
»WYNDWOOD COMMUNITY DEVELOPMENT
PAVING PROJECT - PHASE V -
BID "B" (DRAINAGE) - Resolution
for Final Payment
(For Commission Meeting
of July 22, 1982)
The Department of Public Works recommends
the adoption of the resolution accepting
the completed work and authorizing a final
payment of $10,766.38 to R.J.L. Trading
Company for WYNDWOOD COMMUNITY DEVELOPMENT
PAVING PROJECT - PHASE V - BID "B"
(DRAINAGE)
R.J.L. Trading Company has completed the project consisting
of constructing 1201 feet of covered ditch drainage system
in conjunction with street rebuilding. The project is
located between N.W. 32 - 30' Streets between N. Miami Avenue
and N.W. 2 Avenue. The original contract amount was for
$120,487.40, and the completed amount is $107,663.80. It
was completed on time.
It is now in order for the Commission to accept the completed
work and authorize final payment, after all conditions are
met.