HomeMy WebLinkAboutR-82-0802RESOLUTION NO. 8 2 _ $ 0 3.
A RESOLUTION ACCEPTI14G THE COMPLETED WORK
OF JOB REINERTSON EQUIPMENT COMPANY AT A
TOTAL COST OF $81,898.36 FOR WYNDWOOD
COMMUNITY DEVELOPMENT PAVING PROJECT -
PHASE VI (BID "B" - DRAINAGE); AND
AUTHORIZING A FINAL PAYMENT OF $8,952.46
WHEREAS, there exists a contract dated December 15,
1981 between the City of Miami and Joe Reinertson Equipment
Company; and
WHEREAS, the work has been satisfactorily com-
pleted, and Joe Reinertson Equipment Company has furnished
the required documents certifying that all bills for labor
and materials have been paid in full in connection with
the aforesaid contract; and
WHEREAS, the City Manager and the Department of
Public Works recommend that the completed work be accepted
and final payment made to the contractor;
NOW, THEREFORE, BE IT RESOLVED BY THE COMMISSION
OF THE CITY OF MIAMI, FLORIDA:
Section 1. The completed work performed by
Joe Reinertson Equipment Company for WYNDWOOD COMMUNITY
DEVELOPMENT PAVING PROJECT - PHASE VI (BID "B" - DRAINAGE)
at a total cost of $81,898.36 is hereby approved.
Section 2. The proper officials of the City of
Miami are hereby authorized to pay $8,952.46 to Joe
Reinertson Equipment Company as full and final payment
for all wort: performed and all materials furnished in
connection with WYNDWOOD COMMUNITY DEVELOPMENT PAVING
PROJECT - PHASE VI (BID "B" - DRAINAGE).
CITY COMMISSION
MEETING OF
S E P 9 1982
mm ux 8 2_;.,8 0
PASSED A14D ADOPTED this 9TH day of SEPTEMBER
1982.
ATTEST:
-77 Q
City ler /
PREPARED AND APPROVED BY:
Deputy City Attorney
APPROVED AS TO FORK AND CORRECTNESS:
C.YW Attorney
- 2 -
MAURICE A. FERRE
M A Y O R
82-803,
C
95
Howard V. Gary
City t1anager
Donald W. Cather
Director of Public Works
August 23, 1982 B-4472
WYNDWOOD COMMUNITY DEVELOPMENT
PAVING PROJECT - PHASE VI_
(BID "B" - DRAINAGE) -
Resolution for Final Payment
(For Commission Meeting
of September 9, 1982)
The Department of Public Works recommends
the adoption of the resolution accepting
the completed work and authorizing a final
payment of $8,952.46 to Joe Reinertson
Equipment Company for WYNDWOOD COMMUNITY
DEVELOPMENT PAVING PROJECT - PHASE VI
(BID "B" - DRAINAGE).
Joe Reinertson Equipment Company has completed the project
consisting of constructing a covered ditch drainage system
in the area bounded by N. 14. 29-32 Streets between N. Miami
Avenue and N. W. 2 Avenue. The original contract amount was
for $98,401.25, and the completed amount is $81,898.36. It
was completed on time.
It is now -in order for the Commission to accept the completed
work and authorize final payment, after all conditions are
met.
/0=lution
L:hc
� attached
$2-80)...
JOB NAME
CONTRACTOR
JOB SCOPE
REASON
SOURCE
OF FUNDS
PROJECT
HISTORY
FINAL CONSTRUCTION FACT SHEET
Wyndwood Community Development Paving Project Phase VI
(Bid "B" - Drainage) - B-4472
Joe Reinertson Equipment Co.
Construct covered ditch drainage system in area bounded
by N. W. 29-32 Streets between N. Miami Avenue and N.
W. 2 Avenue
In conjunction with highway rebuilding.
Highway G. 0. Bond Fund
Bids Received: 11/12/81
Contract Awarded: 12/10/81
Preconstruction Meeting: 12/23/81
CONTRACT
TIME
STARTED
2/4/82
CONTRACT
TIME
60 Working days
SCHEDULED
COMPLETION
DATE
4/29/82
ACTUAL
COMPLETION
DATE
2/25/82
BID AMOUNT
$ 98,401.25
CONTRACT
FINAL COST
$ 81,898.36
CURRENT
ITEM FOR
Resolution to accept completed work and authorize
CONSIDERATION
final payment to the contractor.