HomeMy WebLinkAboutR-82-0800RESOLUTION NO. 8 2- 8 O O
A RESOLUTION ACCEPTING THE COMPLETED WORK
OF FRE CONSTRUCTIO14 CO., INC. AT A TOTAL
COST OF $63,874.08 FOR ALLAPATTAH
COMMUNITY DEVELOPMENT PAVING PROJECT -
PHASE IV (BID "B" - SANITARY SEWERS) ; A14D
AUTHORIZING A FINAL PAYMENT OF $8,724.17
WHEREAS, there exists a contract dated October 16,
1981 between the City of Miami and FRE Construction Co'.,
Inc.; and
WHEREAS, the work has been satisfactorily com-
pleted, and FRE Construction Co., Inc. has furnished the
required documents certifying that all bills for labor
and materials have been paid in full in connection with
the aforesaid contract; and
WHEREAS, the City Manager and the Department of
Public works recommend that the completed work be accepted
and final payment made to the contractor;
NOW, THEREFORE, BE IT RESOLVED BY THE COMMISSION
OF THE CITY OF MIAMI, rLORIDA:
Section 1. The completed work performed by FRE
Construction Co., Inc. for ALLAPATTAH COMMUNITY DEVELOPMENT
PAVING PROJECT - PHASE IV (BID "B" - SANITARY SEWERS) at
a total cost of $63,874.08 is hereby approved.
Section 2. The proper officials of the City of
Miami are hereby authorized to pay $8,724.17 to FRE
Construction Co., Inc. as full and final payment for all
work performed and all materials furnished in connection
with ALLAPATTAH COMMUNITY DEVELOPMENT PAVING PROJECT -
PHASE IV (BID "B" - SANITARY SEWERS) .
CITY COMMISSION
MEETING OF
S E P 91982
t1AN 1 I...L .-A
�AAI� ......................ease..
w
f
PASSED AND ADOPTED this 9TH day of SEPTEMBER
1982.
MAURICE A. FERRE
M A Y O R
ATTEST:
ty
C
rk
PREPARED AND APPROVED BY:
Deputy City Attorney
APPROVED AS TO FOR14 AND CORRECTNESS:
-0/.46�
?t'y:lttorney
- 2 -
82 - 8 00
99
To Howard V. Gary
City Manager
FROM Donald W. Cather
Director of Public
CITY OF MIAMI, FLORIDA
INTER -OFFICE MEMORANDUM
DATE August 23, 1982 FILE B-4468
SUBJECT ALLAPATTAH COMMUNITY
DEVELOPMENT PAVING PROJECT -
PHASE IV (BID "B" - SANITARY
SEWERS) - Resolution for
REFERENCES Final Payment
ENCLOSURES (For Commission Meeting
of September 9, 1982)
The Department of Public Works recommends
the adoption of the resolution accepting
the completed work and authorizing a
final payment of $8,724.17 to FRE
Construction Co., Inc. for ALLAPATTAH
COMMUNITY DEVELOPMENT PAVING PROJECT -
PHASE IV (BID "B" - SANITARY SEWERS).
FRE Construction Co., Inc. has completed the project consist-
ing of replacing an existing sanitary sewage system in con-
junction with a highway rebuilding on N. 11. 30 Street between
N. W. 23-24 Avenues and N. W. 23 Avenue between N. W. 29-32
Streets. The original contract amount was for $75,643.00,
and the completed amount is $63,874.08. It was completed on
time.
It is now in order for the Commission to accept the completed
work and authorize final payment, after all conditions are
met.
ca
:hc
esolution attached
N
F
82-800
FINAL CONSTRUCTION FACT SHEET
FOR THE CITY MANAGER
JOB NAME Allapattah C.D. Paving Project Phase IV (Bid "B" -
Sanitary Sewer) - B-4468
CONTPACTOR FRE Construction Co., Inc.
JOB SCOPE Replace sanitary sewage system using 8", 12" and 15"
clay pipe together with all necessary appurtenances
located in N. W. 30 Street between N. W. 23-24 Avenues
and in N. W. 23 Avenue between N. W. 29-32 Streets.
REASON
FOR WORK In conjunction with highway rebuilding.
SOURCE
OF FUNDS Federal Community Development Block Grant Fund
PROJECT Bids Received: 9/17/81
HISTORY Contract Awarded: 10/7/81
Preconstruction Meeting: 11/12/81
CONTRACT
TIME 12/28/81
STARTED
CONTRACT
TIME 30 Working days
SCHEDULED
COMPLETION 2/8/82
DATE
ACTUAL
COMPLETION 1/25/82
DATE
BID AMOUNT $ 75,643.00
CONTRACT
FINAL COST
ITEM FOR
CONSIDERATION
$ 63,874.08
Resolution to accept completed work and authorize
final payment to the Contractor.
82-800