RESOLUT1014 NO.
A RESOLUTION ACCEPTING THE COMPLETED WORK
OF REDLAND CONSTRUCTION CO., INC. AT A
TOTAL COST OF $360,456-37 FOR WYNDWOOD
COMMUNITY DEVELOPMENT PAVING PROJECT -
PHASE V - BID "A" (HIGHWAYS); AND AUTHOR-
IZTiV(", A FINAL PAYMENT OF $36,045.64
INTHEREAS, there exists a contract dated July 28, 1981
between the Citv of Miami and Redland Construction Co., Inc.;
and
WHEREAS, the word; has been satisfactorily completed,
and Redland Construction Co., Inc. has furnished the required
documents certifying that all bills for labor and materials
have been paid in full in connection with the aforesaid contract;
and
WHEREAS, the City Manager and the Department of
Public Works recommend that the completed work be accepted and
final Davment made to the contractor;
NOW, THEREFORE, BE IT RESOLVED BY THE CO',T11TSSION OF
THE CITY OF FLORIDA-
Section 1. The completed work performed by Redland
Construction Co. , Inc. for 1JYNM,1OOD C0111MNITY DEVELOPMENT PAVING
PROJECT - PHASE V - BID "A" (HIGHWAYS) at a total cost of
$360,456.37 is herebv approved.
Section 2. The proper officials of the City of Miami
are herebv authorized to pay $36,045.64 to Redland Construction
Co , Inc, as full and final payment for all work performed and
all materials furnished in connection with WYNDWOOD COPQIUNITY
DEVELOPMENT PAVING PROJECT - PRASE. V - BID "A" (HIGHWAYS)
PASSED AND ADOPTED this 14th day of October, 1982.
_ Maurice A. Ferre
M A Y 0 R
CITY COMMWOH
MEETING OF
OPT 1 4 19B2
RPlBLIrrroN NO. .....
ATTEST:
-•-mil .. (" �' � � , , , ;
CY CLERK
PREPARED AND APPROVED BY:
DEPUTY CITY ATTOR,dEY
APPROVED AS TO FORA AND CORRECTNESS:
zk
CI; , ATT/OR E
Yr
`1, 7—t a
-y� "6
CITY OF MIAMI, FLORIDA
INTER -OFFICE MEMORANDUM
TO Howard V. Gary
City Manager
Donald W. Cather
FROM
Director of Public Works
DATE September 20, 1982 ME B-4467A
SuBJEci WYNDWOOD COMMUNITY DEVELOPMENT
PAVING PROJECT - PHASE V -
(BID .A__ HIGHWAYS)
Resolution for Final Payment
REFERENCES
(For Commission Meeting
ENCLOSURES of October 14, 1982)
The Department of Public Works recommends
the adoption of the resolution accepting
the completed work and authorizing a final
payment of $36,045.64 to Redland Construction
Co., Inc. for WYNDWOOD COM11UN ITY DEVELOPMENT
PAVING PROJECT - PHASE V - BID "A" (HIGHWAY)
Redland Construction Co., Inc. has completed the project consisting
of constructing one mile of street including asphaltic pavement,
concrete sidewalk, concrete curb and gutter, and landscaping in an
area bounded by N.W. 32 - 36 Streets between N. Miami Avenue and
N.W. 2 Avenue. The original contract amount was for $373,061.50,
and the completed amount is $360,456.37. It was completed on time.
It is now in order for the Commission to accept the completed
work and authorize final payment, after all conditions are met.
:az
olution attached
�:"S G CJ
Y
0
FINAL CONSTRUCTION FACT SHEET
FOR THE CITY MANAGER
JOB NAME Wyndwood Community Development Paving Project Phase V
(Bid "A" - Highways) - B-4467
CONTRACTOR Redland Construction Co., Inc.
JOB SCOPE Construct one mile of street including asphaltic pavement,
concrete sidewalk, concrete curbs and/or gutters and land-
scaping in an area bounded by N. W. 32-36 Streets between
North Miami Avenue and N. W. 2 Avenue.
REASON Existing streets out of grade, side parkways deteriorated
FOR WORK from extensive on -street parking.
SOURCE
OF FUNDS Federal Community Development Block Grant Fund
PROJECT Bids Received: 7/7/81
HISTORY Contract Awarded: 7/23/81
Preconstruction Meeting: 8/24/81
CONTRACT
TIME
STARTED 12/29/81
CONTRACT 80 Working days plus 5 day delay from rain
TIME and 19 days delay from Florida Power &
Light Co. and Peoples Gas System
relocation work
SCHEDULED
COMPLETION
DATE 5/25/82
ACTUAL
COMPLETION
DATE 5/25/82
BID AMOUNT $ 373,061.50
CONTRACT
FINAL COST $ 360,456.37
CURRENT
ITEM FOR Resolution to accept completed work and authorize
CONSIDERATION final payment to the contractor.
G