RESOLUTION NO.
A RESOLUTION ACCEPTING THE COMPLETED WORK
PERFORMED BY D.M.P. CORPORATION AT A TOTAL
COST OF $442,028.03 FOR NORTHERN DRAINAGE
PROJECT E-52; AND AUTHORIZING A FINAL
PAYMENT OF $11,128.71.
WHEREAS, there exists a contract dated July 9, 1982
between the City of Miami and D.M.P. Corporation; and
WHEREAS, the original contract was increased on
October 14, 1982 by Resolution No. 82-963 in the amount
of $40,000.00; and
WHEREAS, the work has been satisfactorily completed,
and D.M.P. Corporation has furnished the required documents
certifying that all bills for labor and materials have been
paid in full in connection with the aforesaid contract; and
IMEREAS, the City Manager and the Department of
Public Works recommend that the completed work be accepted
and final payment made to the contractor;
NOW, THEREFORE, BE IT RESOLVED BY THE COMMISSION
OF THE CITY OF MIAMI, FLORIDA:
Section 1. The completed work performed by D.M.P.
Corporation at a total cost of $442,028.03 is hereby
approved.
Section 2. The proper officials of the City of
Miami are herewith authorized to pay $11,128.71 to D.M.P.
Corporation as full and final payment for all work performed
and all materials furnished in connection with NORTHERN
DRAINAGE PROJECT E-52.
PASSED AND ADOPTED this 13 day of January , 1983.
MAURICE A. FERRE
__ATTEST: M A Y O R
Qff ity Clerk
PREPARED AND APPROVED BY: APPROVED AS TO FORM AND CORRECTNESS:
Deputy City Attorney City Attorney
8 3-51
CITY OF MIAMI. FLORIDA
42 INTER -OFFICE MEMORANDUM
TO Howard V. Gary DATE December 29, 1982 FILE B-5484
City Manager
SUBJECT NORTHERN DRAINAGE E-52 -
Resolution for Final Payment
FROM
Donald W. Cather REFERENCES (For Commission Meeting
of January 13 , 1983 )
Director of._P blic orks
ENZLOSURES
The Department of Public Works recommends
the adoption of the resolution accepting
the completed work and authorizing a
final payment of $11,128.71 to D.M.P.
Corporation for NORTHERN DRAINAGE PROJECT
E-52.
D.M.P. Corporation has completed the project consisting
of constructing 45 drainage structures in the area bounded
by the north.and west City limits, Biscayne Bay, North 36
Street, with 12 locations outside this area. The original
contract amount was $402,237.02, and was increased by
Resolution No. 82-963 in the amount of $40,000.00 on
October 14, 1982. The completed amount is $442,028.03,
and it was completed on time.
It is now in order for the Commission to accept the com-
pleted work and authorize final payment, after all
conditions are met.
:hc
tj solution attached
o
N c�
co �
N
O
w
w m
0
83-51
FINAL CONSTRUCTION FACT SHEET
FOR THE CITY MANAGER
JOB NAME Northern Drainage Project E-52 - B-5484
CONTRACTOR D.M.P. Corporation
JOB SCOPE Construct 45 drainage structures in the area
bounded by the north and west City limits,
Biscayne Bay, and N. 36 Street, with 12 locations
outside this area.
REASON
FOR WORK Eliminate storm drainage problems at locations of
greatest need.
SOURCE
OF FUNDS Storm Sewer G. 0. Bond Fund
PROJECT Bids Received: 5/13/82
HISTORY Contract Awarded: 6/17/82
Preconstruction Meeting: 7/16/82
CONTRACT
TIME
STARTED 7/13/82
CONTRACT
TIME 150 Working days
SCHEDULED
COMPLETION
DATE 2/16/83
ACTUAL
COMPLETION
DATE 12/27/82
BID AMOUNT $ 442,237.02 (Includes $40,000 increase in contract
amount authorized by Reso. 82-963, 10/14/82:
CONTRACT
FINAL COST $ 442,028.03
CURRENT
ITEM FOR Resolution to accept completed work and authorize
CONSIDERATION final payment to the contractor.
A 9?1a 1/1 P ; Z -