RESOLUTION NO. S3-135
A RESOLUTION ACCEPTING THE COMPLETED
WORK OF MIRI CONSTRUCTION, INC. AT
A TOTAL COST OF $344,814.40 FOR BUENA
VISTA COMMUNITY DEVELOPMENT PAVING
PROJECT - PHASE VI; AND AUTHORIZING
A FINAL PAYMENT OF $36,669.25
WHEREAS, there exists a contract dated October 27,
1981 between the City of Miami and Miri Construction,
Inc.; and
WHEREAS, the work has been satisfactorily completed, ,
and Miri Construction, Inc. has furnished the required
documents certifying that all bills for labor and
materials have been paid in full in connection with
the aforesaid contract; and
WHEREAS, the City Manager and the Department
of Public Works recommend that the completed work
be accepted and final payment made to the contractor;
NOW, THEREFORE, BE IT RESOLVED BY THE COMMISSION
OF THE CITY OF MIAMI, FLORIDA:
Section 1. The completed work performed by
Miri Construction, Inc. for BUENA VISTA COMMUNITY
DEVELOPMENT PAVING PROJECT - PHASE VI at a total
cost of $344,814.40 is hereby approved.
Section 2. The proper officials of the City
of Miami are hereby authorized to pay $36,669.25
as full and final payment for all work performed
and all materials furnished in connection with BUENA
VISTA COMMUNITY DEVELOPMENT PAVING PROJECT - PHASE VI.
PASSED AND ADOPTED this 10thday of February , 1983.
Maurice A. Ferre
ATTEST: M A Y O R
City lerk
PREPARED AND APPROVED BY: APPROVED AS TO FORM AND CORRECTNESS:
OF
Deputy City Attorney City Attorney
F F 1 0 1983
8 3-135
CITY OF MIAMI. FLORIDA ,
75 INTER -OFFICE MEMORANDUVITY MANAGER'S OFFICE
DATE January J2126Ou 19 �• S9FILE B-4469
To Howard V. Gary Y
City Manager
FROM Donald W. Cather
Director of Publi r, Works
ME
SUBJECT BUENA VISTA COMMUNITY
DEVELOPMENT PAVING PROJECT -
PHASE VI - Resolution for
Final Payment
REFERENCES:
ENCLOSURES (For Commission Meeting
of February 10, 1983)
The Department of Public Works recommends
the adoption of the resolution accepting
the completed work; and authorizing a
final payment of $36,669.25 to Miri
Construction, Inc. for BUENA VISTA
COMMUNITY DEVELOPMENT PAVING PROJECT -
PHASE VI.
Miri Construction, Inc. has completed the project consisting
of constructing 0.7 mile of street, including asphaltic
pavement, concrete curb and gutters, concrete sidewalk, a
covered ditch drainage system, and landscaping. The project
is located in the area bounded by N. W. 46-50 Streets
between N. W. 5-6 Avenues. The original contract amount
was for $354,157.76, and the completed amount is $344,814.40.
It was completed on time.
It is now in order for the Commission to accept the completed
work and authorize final payment, after all conditions are
met.
.hc
solution attached
83--13LA
6"
P1
r -.
FINAL CONSTRUCTION FACT SHEET
FOR THE CITY MANAGER
JOB NAME Buena Vista Community Development Paving
Project Phase VI - B-4469
CONTRACTOR Miri Construction, Inc.
JOB SCOPE Construct 0.7 mile of street including asphaltic
pavement, concrete curbs and gutters, concrete
sidewalk, a covered ditch drainage system, and
landscaping in an area bounded by N. W. 46-50 Streets
between N. W. 5-6 Avenues.
REASON Existing streets out of grade, side parkways
FOR WORK deteriorated from heavy on -street parking, and
drainage problems.
SOURCE
OF FUNDS Federal Community Development Block Grant Fund
PROJECT Bids Received: 9/15/81
HISTORY Contract Awarded: 10/7/81
Preconstruction Meeting: 11/5/81
CONTRACT
TIME
STARTED 3/l/82
CONTRACT
TIME 100 Working days plus 12 days delay from rain.
SCHEDULED
COMPLETION
DATE 8/5/82
ACTUAL
COMPLETION
DATE 8/5/82
BID AMOUNT $ 354,157.76
CONTRACT
FINAL COST $ 344,814.40
CURRENT
ITEM FOR Resolution to accept completed work and authorize
CONSIDERATION final payment to the contractor.
83-JL35