HomeMy WebLinkAboutR-83-0232J-33-178
2
RESOLUTION NO.
A RESOLUTION ACCEPTING THE COMPLETED WORK
OF DOCK AND MARINE CONSTRUCTION, INC. AT
A TOTAL COST OF $29,552.00 FOR MIAMARINA
AND WATSON ISLAND - PILE REPLACEMENT (BID A);
AND AUTHORIZING A FINAL PAYMENT OF $2,955.20
WHEREAS, there exists a contract dated September 15,
1982 between the City of Miami and Dock and Marine Con-
struction, Inc.; and
WHEREAS, the work has been satisfactorily completed,
and Dock and Marine Construction, Inc. has furnished the
required documents certifying that all bills for labor
and materials have been paid in full in connection with
the aforesaid contract; and
WHEREAS, the City Manager and the Department of
Public Works recommend that the completed work be accepted
and final payment made to the contractor;
NOW, THEREFORE, BE IT RESOLVED BY THE COMMISSION
OF THE CITY OF MIAMI, FLORIDA:
Section 1. The completed work performed by Dock and
Marine Construction, Inc. for MIAMARINA AND WATSON ISLAND -
PILE REPLACEMENT - BID A at a total cost of $29,552.00 is
hereby approved.
Section 2. The proper officials of the City of
Miami are hereby authorized to pay $2,955.20 to Dock and
Marine Construction, Inc. as full and final payment for
all work performed and all materials furnished in connection
with MIAMARINA AND WATSON ISLAND - PILE REPLACEMENT - BID A.
PASSED AND ADOPTED this 18 day of MARCH 1983.
MAURICE A. FERRE
ATTEST: M A Y O R
Cit Clerk
PREPARED AND APPROVED BY: APPROVED AS TO FORM AND CORRECTNESS•
Deputy City Attorney
City Attorney
l�l/IL.
a
El
r
8
51J4,
63 INTER -OFFICE MEMORANDUM
TO Howard V. Gary
City Manager
FROM Donald W. Ca�her "
Director o1fi�Pu tW6 s
CITY OF MIAMI. FLORIDA
DATE- March 2, 1983 FILE B-2849A
SUBJECT MIAMARINA AND WATSON ISLAND -
PILE REPLACEMENT (Bid "A" -
Miamarina) Resolution for
REFERENCEinal Payment
ENCLOSURES. (For Commission Meeting of
March 18,1983)
The Department of Public Works recommends
the adoption of the resolution accepting
the completed work and authorizing a final
payment of $2,955.20 to Dock & Marine
Construction, Inc. for MIA14ARINA AND 14ATSON
ISLAND - PILE REPLACEMENT (Bid "A" -
Miamarina)
Dock & Marine Construction, Inc. has completed the project
consisting of removing and replacing 24 pier piles and 6
mooring piles at Miamarina. The original contract amount
was for $29,740.00, and the completed amount is $29,552.00.
It was completed on time.
It -is now in order for the Commission to accept the completed
work and authorize final payment, after all conditions are
met. The source of funds is "Miamarina and Watson Island
Marinas - Major Maintenance" account.
-- az
solution attached
t � =I NJ Z- ON E8@
301330 S,830VNVW 4110
S-3-%�3A,
40
•
FINAL CONSTRUCTION FACT SHEET
FOR THE CITY MANAGER
JOB NAME Miamarina and Watson Island - Pile Replacement
(Bid "A" - Miamarina) - B-2849
CONTRACTOR Dock and Marine Construction, Inc.
JOB SCOPE Remove and replace 24 pier piles and 6 mooring piles
at Miamarina
REASON
FOR WORK Replacement of deteriorated piles
SOURCE
OF FUNDS Miamarina and Watson Island Marinas - Major Maintenance
PROJECT Bids Received: 8/24/82
HISTORY Contract Awarded: 9/9/82
Preconstruction Meeting: 10/28/82
CONTRACT
TIME
STARTED 12/13/82
CONTRACT
TIME 30 Working days
SCHEDULED
COMPLETION
DATE 1/25/83
ACTUAL
COMPLETION
DATE 1/7/83
BID AMOUNT $ 29,740.00
CONTRACT
FINAL COST $ 29,552.00
CURRENT
ITEM FOR Resolution to accept completed work and authorize
CONSIDERATION final payment to the contractor.