HomeMy WebLinkAboutR-83-0309J-83-254 a
RESOLUTION NO. 83 IL:1
A RESOLUTION ACCEPTING THE COMPLETED WORK OF
ROMA CONSTRUCTION, INC. AT A TOTAL COST OF
$343,490 FOR CITY OF MIAMI/UNIVERSITY OF MIAMI
JAMES L. KNIGHT INTERNATIONAL CENTER -
FINISHES AND MILLWORK PROJECT; AND AUTHORIZING
A FINAL PAYMENT OF $8,587.25.
WHEREAS, there exists a contract dated May 21, 1982 between
the City of Miami and Roma Construction, Inc.; and
WHEREAS, the work has been satisfactorily completed, and
Roma Construction Inc. has furnished the required documents
certifying that all bills for labor and materials have been paid
in full in connection with the aforesaid contract; and
WHEREAS, the City Manager and the Department of Public Works
recommend that the completed work be accepted and final payment
made to the contractor;
NOW, THEREFORE, BE IT RESOLVED BY THE COMMISSION OF THE
CITY OF MIAMI, FLORIDA:
Section 1. The completed work performed by Roma Construction
Inc. for City of Miami/University of Miami James L. Knight
International Center - Finishes and Millwork Project at a total
cost of $343,490 is hereby approved.
Section 2. The proper officials of the City of Miami are
hereby authorized to pay $8,587.25 to Roma Construction, Inc.
as full and final payment for all work performed and all materials
furnished in connection with City of Miami/University of Miami
James L. Knight International Center - Finishes and Millwork Project.
PASSED AND ADOPTED this 6th day of April , 1983.
Maurice A. Ferre
M A Y O R
ATTEST:
City Clerk
PREPARED AND APPROVED BY: APPROVED AS TO FORM AND CORRECTNESS:
Deputy City Attorney City Attorney
r/ Ci`Y :'OIL^:?;°I`:'s'OI1
1983
83--•30
0 a
Hv�
To Howard V. Gary
City Manager
CITY OF MIAMI. FLORIDA
INTER -OFFICE MEMORANDUM
FRO4 Donald W. Cath
Di eecttor mac- Works
-� ,
CIL -E March 18, 1983 FILE B-3148-V-1
Convention Center Finishes
and Millwork Project
Resolution for Final Payment
REV ERE%CE` For Commission Meeting of
April 14, 1983
E%CLCS,RES
The Department of Public Works recommends
the adoption of the resolution accepting
the completed work and authorizing a final
payment of $8,587.25 to Roma Construction,
Inc. for City of Miami/University of Miami
James L. Knight International Center -
Finishes and Millwork Project.
Roma Construction, Inc. has completed the project consisting
of furnishing and installing cabinetwork, millwork, tambour
wood paneling, accordian door grilles, and decorative mirrors
for the Convention Center interiors. The project was completed
for the original amount of $343,490 and it was completed on time.
Funding was provided from the Convention Center and Parking
Garage Revenue Bonds - Construction Account.
It is now in order for the Commission to accept the completed
work and authorize final payment after all conditions are met.
cc: Law Department
83-3309