RESOLUTION NO. 6_�3--,JS3'
A RESOLUTION AUTHORIZING THE CITY MANAGER
TO EXTEND THE EXISTING PROFESSIONAL
SERVICES AGREEMENT, S►_ BiECT TO THE CITY
ATTORNEY'S APPROVAL AS 'TO FORM AND
CORRECTNESS, WITH E. P. IACONIS,
CERTIFIED PUBLIC ACCOU'VTANr, FOR SPECIAL
COST REVIEW AND AUnITS AS NECESSARY AND
AS DETERMINED BY THE CITY MANAGER FOR THE
CITY OF MIAMI/UNIVERSITY OF MIAMI, JAMES
L. KNIGHT INTERNATIONAL CENTER PROJECT;
FURTHER AUTHORIZING THE EXPENDITURE OF
ADDITIONAL FUNDS NOT TO EXCEED $45,000
FOR THE AFORESAID SERVICES FROM THE
CONSTRUCTION ACCOUNT ESTABLISHED FROM THE
SALE OF CONVENTION CENTER AND PARKING
GARAGE REVENUE ►3ONDS, UNLESS FURTHER
EXPRESSLY AUTHORIZED 3Y THE CITY
COMMISSION.
WHEREAS, the City of Miami/University of Miami James L.
Knight International Center_ project involves the expenditure
of almost $100 million dollars in public fun,3s; anti
WHEREAS, the source of these Funds has been from the
Federal Government, Revenue Bonds and other City capital
funds; and
WHEREAS, proper control of the expenditure of these
funds is essential; and
WHEREAS, by Resolution No. 81-852, the City Commission
authorized the City Manager to enter into a Professional
Services Agreement with E.P. Iaconis, Certified Public
Accountant, for cost review and audits as necessary and as
determined by the Assistant to the City Manager in charge of
the said Project; and
WHEREAS, on October 30, 1961, a Professional Services
Agreement was executed for a term of one year commenciri(j
October 7, 1981 and terminating October 7, 1982; and
WHEREAS, by Resolution No. 82-933 the City Commission
authorized the City Manager to extend for six (6) months the
term of the existing Professional Services Agreement; and
CITY I-OMMISSIOU
L U 4
J u N 9 1983
3-4
FFMd RK"
6
WHEREAS, the finds previously authorized for these
services have been fully expender; and
WHEREAS, the construction of the Convention Center_ is
substantially complete; and
WHEREAS, there is a need to audit the general
construction contract in order to make final payment to the
Contractor;
NOW, T►iEREPORE, BE IT RESOLVED BY THE COMMISSION OF THE
CITY OF MIAMI, FLORIDA:
Section 1. The City Manager is hereby authorized to ,=
extend the existing Professional Services Agreement, subject
to the City Attorney's approval as to form and correctness,
with E. P. Iaconis, Certified Public Accountant, for special
cost review and audits as necessary and as determined by the
City Manager for the City of Miami/University of Miami James
L. Knight International Center Project.
Section 2. The expenditure of additional funds for the
aforesaid services is hereby approved in an amount not to
exceed $45,000 from the Construction Account established from
the sale of Convention Center and Parking Garage Revenue
Bonds, unless further expressly authorized by the City
Commission.
PASSED AND ADOPTED this 9th day of June , 1983.
Ma price A. Ferri'
MAURICE A. FERRE
M A Y 0 R
T:
�_ALPH G. ONGIE, CITY CLER
IK
PREPARED AND APPROVED BY:
6
ROBERT F. CLA K
DEPUTY CITY ATTORNEY
APPROVED AS TO FORM AND CORRECTNESS:
)IR R. GARCIA-PEDROSA
ITY ATTORNEY
-2-
83-483
0
45
CITY OF MIAMI. FLORIDA
•- lWER-OFFICE MEMORANDUM
7
To Howard Gary _ CATE May 20, 1983 C'LE
City Manager
Resolution to Extend Auditor's
I
Contract to Audit Convention
•^I;t,?t,• 1_ Center Construction Contract
R C•d Allan I. Poms REFERENCES
Project Director
Conference Center ENCLOSURES
Since Commission action to extend E.P. Iaconis' (CPA) contract
to audit the Convention Center Construction Contract has been
delayed, he has agreed to proceed with the audit work under
the City Manager's authority. On this basis and as agreed at
the meeting with Frank J. Rooney, Inc. on 4/12/83,
E.P. Iaconis is proceeding with the audit.
It is recommended that the proposed Resolution to extend the
Auditor's contract be put on the next City Commission Meeting
Agenda. If possible, it should be considered to include it on
the Agenda for the Planning & Zoning Meeting scheduled for
May 31, 1983.
cc: Vince Grimm
John Copelan
Miriam Maer
I.P. Iaconis
83-483,
4*
1
April 28, 1983LS
Honorable Mayor and A P
Members of the City
Commission - Proposed Resolution to Extend
the Auditor's Contract for
the Convention Center Project
Howard V. Gary � "=5
City Manager
It is recommended that the proposed resolution
be adopted by the City Commission in its meeting
of April 28, 1983, whereby the City Manager is
authorized to extend the existing Professional
Services Agreement with E.P. Iaconis, Certified
Public Accountant, for special cost review and
audits as necessary and as determined by the
City Manager for the City of Miami/University of
Miami James L. Knight International Center Project;
further authorizing the expenditure of additional
funds not to exceed $45,000 for the aforesaid
services from the Construction Account established
from the sale of Convention Center and Parking
Garage Revenue Bonds unless further expressly
authorized by the City Commission.
The construction of the Convention Center Project is substantially
complete and there is a need to audit the City's contract with
Frank J. Rooney Inc. on the general construction in order to make
final payment. The contract is a "Cost of the Work plus a fee
with Guaranteed Maximum Cost" and the contract must be audited
in order to establish a final cost as provided by the contract
and to ensure that all expenditures were appropriate. As a result
of a preliminary audit, we found several matters of concern
requiring a comprehensive audit to verify the expenditures by
the Contractor.
In addition, there is a need for cost review concerning operation
and maintenance expenditures to be allocated to the City and its
lessees on an equitable basis.
It is essential that these auditing services proceed immediately.
The rate of compensation to E.P. Iaconis, Certified Public Accountant,
will remain the same as contained in the current agreement dated
September 3, 1982.