HomeMy WebLinkAboutR-83-0649J-33 S -'_ 0 0
RESOLUTION No. S-3" E 4SI
A'RESOLUTION ACCEPTING THE COMPLETED
WORK OF KENNEY DRAPERY ASSOCIATES, INC.
AT A TOTAL COST OF $184,450. FOR CITY
OF MIAMI/UNIVERSITY OF MIAMI JAMES L.
KNIGHT INTERNATIONAL CENTER - ADDITIVE
ITEMS "B" AND "C" FINISHES AND MILLWORK
PROJECT; AND AUTHORIZING FINAL PAYMENT
OF $5,669.
WHEREAS, there exists a contract dated May 27, 1982 between the
City of Miami and Kenney Drapery Associates, Inc.; and
WHEREAS, the work has been satisfactorily completed, and Kenney
Drapery Associates, Inc. has furnished the required documents certifying
that all bills for labor and materials have been paid in full in
connection with the aforesaid contract; and
WHEREAS, the City Manager and the Department of Public Works
recommend that the completed work be accepted and final payment made to
the contractor;
NOW, THEREFORE, BE IT RESOLVED BY THE COMMISSION OF THE CITY OF
MIAMI, FLORIDA:
Section 1. The completed work performed by Kenney Drapery Associates,
Inc. for City of Miami/University of Miami James L. Knight International
Center - Additive Items "B" and "C" Finishes and Millwork Project at a
total cost of $184,450. is hereby approved.
Section 2. The proper officials of the City of Miami are hereby
authorized to pay $5,669. to Kenney Drapery Associates, Inc. as full
and final payment for all work performed and all materials furnished in
connection with City of Miami/University of Miami James L. Knight
International Center - Additive Items "B" and "C" Finishes and Millwork
Project.
PASSED AND ADOPTED this 18th day of July , 1983.
ATTEST:
101
(� City Clerk
Maurice A. Ferre MMISSIO;
MAYOR
MEETING OF
JUL 18 19883
RrSCuuliu,
REMARKS. --`-
PREPARED AND APPROVED BY: APPROVED AS TO FORM AND CORRECTNESS:
07 & - '/"000,
lleputy Lit} Attorney City Attorney
59
CITY OF MIAMI, FLORIOA
INTER -OFFICE MEMORANDUM
TO Howard V. Gary
City Manager
°ROM Donald W. Cather, Director
Public Works Dezat.l
OATE June 24, 1983 FILE: B-3148-V-2
SUBJECT Convention Center - Additive Items
"B" and "C" Finishes and Millwork
Project, Resolution for Final Payment
REFERENCES:
(ForCommission Meeting
ENCLOSURES, of July 18, 1983 )
The Department of Public Works
recomnwds the adoption of the
resolution accepting the completed
work and—authorizingand—authorizing a final
payment o _ 5,669 to Kenney Drapery
Associates, Inc. for City of Miami/
University of Miami James L. Knight
International Center - Additive
Items "B" and "C" Finishes and
Millwork project.
Kenney Drapery Associates, Inc. has completed the project consisting
of furnishing and installing drapery, brass beads, track and fabric
panels for the Convention Center interiors. The project was completed
for the original amount of $184,450 and it was completed on time.
Funding was provided from the Convention Center and Parking Garage
Revenue Bonds - Construction Account.
It is now in order for the Commission to accept the completed work
and authorize final payment after all conditions are met.
AIP/mim11-17-
1.l
6671)
Resolution attached
(S
83--6491