HomeMy WebLinkAboutR-83-0639J-UO3-570
RESOLUTION NO.
A RESOLUTION ACCEPTING THE COMPLETED WORK
OF ROENCA CORPORATION, AT A TOTAL COST OF
$1, 377 , 662.56 FOR KIRKLAND SANITARY SEWER
IMPROVEMENT IN KIRKLAND SANITARY SEWER
IMPROVEMENT DISTRICT SR-5478-C (CENTERLINE.
SEWER); AND AUTHORIZING A FINAL PAYMENT OF
$135,093.93
WHEREAS, there exists a contract dated January 19,
1982 between the City of Miami and Roenca Corporation; and
GIHEREAS, the work has been satisfactorily completed,
and Roenca Corporation has furnished the required documents
certifying that all bills for labor and materials have been
paid in full in connection with the aforesaid contract; and
WHEREAS, the City Manager and the Department of
Public Works recommend that the completed work be accepted
and final payment made to the contractor;
NOW, THEREFORE, BE IT RESOLVED BY THE COMMISSION OF
THE CITY OF MIAMI, FLORIDA:
Section 1. The completed work performed by Roenca
Corporation for KIRKLAND SANITARY SEWER IMPROVEMENT in
KIRKLAND SANITARY SEWER IMPROVEMENT DISTRICT SR-5478-C
(centerline sewer) at a total cost of $1,377,662.56 is hereby
approved.
Section 2. The proper officials of the City of Miami
are hereby authorized to pay $135,093.93 to Roenca Corporation
as full and final payment for all work performed and all
materials furnished in connection with KIRKLAND SANITARY SEWER
IMPROVEMENT in KIRKLAND SANITARY SEWER IMPROVEMENT DISTRICT
SR-5478-C (centerline sewer).
1983.
PASSED AND ADOPTED this 18th day of July ,
Maurice A. Ferre
M A Y 0 R
CITY COMMISSION
MEETING OF
JUL 188 1983
RESCLUTiON i,,8,3-(;3v
P.EMARKS
0
ATTEST:
(CI—ty-
Clerk
PREPARED AND APPROVED BY:
Deputy City Attorney
APPROVED AS TO FORM AND CORRECTNESS:
fcae /r-
y Attorney
- 2 -
83--639
FINAL CONSTRUCTION FACT SHEET
FOR THE CITY MANAGER
JOB NAME Kirkland Sanitary Sewer Improvement SR-5478-C
(centerline)
CONTRACTOR Roenca Corporation
JOB SCOPE Construct sanitary sewage system using 8"-20"
sewer pipe, 6" laterals, together with all
necessary appurtenances in the area bounded
by West Flager Street, S. W. 8 Street, S. W.
32 Avenue, and S. W. 37 Avenue.
REASON
FOR WORK Provide sanitary sewers in previously unsewered
area.
SOURCE
OF FUNDS Sanitary Sewer G. 0. Bond Fund
PROJECT Bids Received: 12/10/81
HISTORY Contract Awarded: 1/14/82
Preconstruction Meeting: 2/10/82
CONTRACT
TIME
STARTED 3/1/82
CONTRACT 160 Working days plus 17 days delay from rain
TIME and 20 days delay in having
tie-in manhole constructed
SCHEDULED
COMPLETION
DATE 12/9/82
ACTUAL
COMPLETION
DATE 12/9/82
BID AMOUNT $ 1,431,590.00
CONTRACT
FINAL COST $ 1,377,662.56
CURRENT
ITEM FOR Resolution to
CONSIDERATION final payment
r
CITY OF MIAMI. FLORIDA
8
INTER-OFFFCE• 'MEMORANOUM
' t
;7"1 TO
Howard V . Gary DATE: June 30, 1983 FILE: B- 54 78
City Manager
susdECT. KIRKLAND SANITARY SEWER
IMPROVEMENT SR-5478-C
Resolution for Final Payment
FROM Donald W. Cather Director of Publ' Wo s REFERENCES: (For Commission Meeting of
ENCLOSURES: July 18, 1983)
The Department of Public Works recommends
the adoption of the resolution accepting the
completed work and authorizing a final pay-
ment of $135,093.93 to Roenca Corporation
for KIRKLAND SANITARY SEWER IMPROVEMENT in
KIRKLAND SANITARY SEWER IMPROVEMENT DISTRICT
SR-5478-C (centerline sewer).
Roenca Corporation has completed the project consisting of
constructing a new sanitary sewage system using 8"-20" sewer
main, 6" house laterals, together with all necessary
appurtenances in the area bounded by West Flagler Street,
S.W. 8 Street, S. W. 32 Avenue, and S.W. 37 Avenue. The
original contract amount was for $1,431,590.00, and the
completed amount is $1,377,662.56, and it was completed on
time.
At the Commission meeting of June 15, 1983 Resolution
No. 83-551 passed, directing the City Clerk to publish a
Notice of Public Hearing on KIRKLAND SANITARY SEWER
IMPROVEMENT - in KIRKLAND SANITARY SEWER IMPROVEMENT
DISTRICT SR-5478-C (centerline sewer).
It is now in order for the Commission to accept the completed
work and authorize final payment, after all conditions are
met.
Lsaz
esolution attached
'7 U
83- 63S