RESOLUTION NO. 4,H "
A RESOLUTION ACCEPTING THE COMPLETEL) WORK
OF CALLIES rT,FCTRIC, INC. AT A TOTAL COST
OF $20,835.00 FOR FIRE STATION NO. 1 -
EMERGENCY GENERATOR.; AND AUTHORIZT_NG A
FINAL PAYMENT OF $2,160.00
WHEREAS, there exists a contract dated February 15,
1984 between the City of Miami_ and Callies Electric, Inc.; and
WHEREAS, the work has been satisfactorily completed,
and Callies Electric, Inc. has furnished the required documents
certifying that all hills for labor and materials have been paid
in full in connection with the aforesaid contract; and
WHEREAS, the City Manager and the Department of Public
Works recommend that the completed work be accepted and final
payment made to the contractor;
NOW, THEREFORE, BE IT RESOLVED BY THE COMMISSION OF
THE CITY OF MIAMI, FLORIDA:
Section 1. The completed work performed by Callies
Electric, Inc. for FIRE STATION NO. 1 - EMERGENCY GENERATOR
at a total cost of $20,835.00 is hereby approved.
Section 2. The proper officials of the City of Miami
are hereby authorized to pay $2,160.00 to Callies Electric, Inc.
as full and final payment for all work performed and all
materials furnished in connection with FIRE STATION NO. 1 -
EMERGENCY GENERATOR.
PASSED AND ADOPTED this 30th day of July 1984.
ATTEST:
Citif Clerk
PREPARED AND APPROVED BY:
eputy City Attorney
_ Maurice A. Ferr
M A Y O R
APPROVED AS TO FORM AND CORRECTNESS:
40 4004�4-- a4ao�
y Attor.ney
CITY C0I'knI.4ISSIUN
1k1EI `1'i','1!G OF
JUL 20 19841
kEIr1F;kh�
CITY OF MIAMI. FLORIDA
INTER -OFFICE MEMORANDUM
TO. Howard V . Gary DATE:
City Manager
�- SUBJECT:
boriald W. C.atY17r REFERENCES:
Director of Public Works
June 12, 1984 f ILE:
FIRE STATION NO. I -
EMERGENCY GENERATOR
Resolution for Final Payment
ENCLOSURES: (For Commission Meeting of
July -1-2-, 1984 )
-500
The Department of Public Works recommends
the adoption of the resolution accepting
the completed work and authorizing a final
payment of $2,160.00 to Callies Electric,
Inc. for FIRE STATION NO. 1 - EMERGENCY
GENERATOR
Callies Electric, Inc. has completed the project consisting
of a new 45 M1 standby generator, as a replacement for the
existing generator, at Fire Station No. 1, located at 144 N.E.
5 Street. The original contract amount was for $21,750.00,
and the completed amount is $20,835.00. It was completed on
time. The source of funds is Renovation of Fire Stations, 1,2,
5 and 8 account.
It is now in order for the Commission to accept the completed
work and authorize final payment, after all conditions are
met.
LE�L�: az
Resolution attached
cc: Manuel Alvarez
_ µz
_.� _� NL I
FINAL CONSTRUCTION FACT SHEET
FOR THE CITY MANAGER
JOB NAME
Fire Station No. 1 - Emergency Generator - B-2869
CONTRACTOR
Callies Electric, Inc.
JOB SCOPE
Furnish and install a new 45 KW standby electrical
generator at F.S. #1 located at 144 N. E. 5 Street.
REASON
FOR WORK
Replace old undersized generator
SOURCE
OF FUNDS
Renovation of Fire Stations, 1, 2, 5 and 8
PROJECT
Bids Received: 10/31/83
HISTORY
Contract Awarded: 2/9/84 .
Preconstruction Meeting: 1/23/84
CONTRACT
TIME
STARTED
4/16/84
_ CONTRACT
TIME
10 Working days
SCHEDULED
�.. COMPLETION
DATE
4/27/84 _
ACTUAL
COMPLETION
DATE
4/25/84
BID AMOUNT
$ 21,750.00
CONTRACT
FINAL COST
$ 20,835.00
CURRENT
ITEM FOR
Resolution to accept completed work and authorize
CONSIDERATION final payment to the contractor.