A RESOLUTION ACCEPTING THq COMPLETED WORK
OF MET CONSTRUCTION, INC. AT A TOTAL COST
OF $97,649.00 FOR CITY OF
MIAMI/UNIVERSITY OF MIAMI JAMES L KNIGHT
INTERNATIONAL CENTER - ENTRANCE CANOPY;
ASSESSING $9,500-00 AS LIQUIDATED DAMAGES
FOR 19 DAYS OVERRUN OF CONTRACT TIME; AND
AUTHORIZING A FINAL PAYMENT OF $264.90.
WHEREAS, there exists a contract dated January 209 1983
between the City of Miami and MET Construction, Inc.; and
WHEREAS, the work, consisting of furnishing and
installing a structural steel frame and canopy assembly, for
the entrance to the Inter -national Center located at 400 S.E.
2nd Avenue, has been satisfactorily completed, and MET
Construction, Inc. has furnished the required documents
certifyina that all bills for labor, and roaterials have been
paid in full in connect inn with thf- afvres,- o -- - 4 i 0 c r act ; and
WHEREAS, I iquidated dartiages, for, cater run (-.,f contract
time of 19 days should be deducted from the final Qaymert
due the contractor; and
WHEREAS, the City Manager and the Department of Public
Works recommend that the completed work be accepted and
final payment made to the contractor;
NOW, THEREFORE, BE IT RESOLVED BY THE COMMISSION OF THE
CITY OF MIAMI, FLORIDA:
Section 1. The completed work performed by MET
Construction, Inc. for CITY OF MIAMI/UNIVERSITY OF MIAMI
JAMES L. KNIGHT INTERNATIONAL CENTER - ENTRANCE CANOPY at a
total cost of $97,649.00 is hereby approved.
Section 2. That liquidated damages in the amount of
$9,500.00 for 19 days overrun of contract time shall be
deducted from the balance due the contractor.
'A 11
Section 3. The proper officials of the City of Miami
are hereby authorized to Day to MET Construction, Inc.,
after all adjustments are made, a balance of $264.90 as full
and final payment for all work performed and all m4terials
furnished in connection with CITY OF MIAMI/UNIVERSITY OF
MIAMI JAMES L. KNIGHT INTERNATIONAL CENTER - ENTRANCE
CANOPY.
PASSED AND ADOPTED this day of_SgqtqMbet_q
19e4.
ATTEST:
-A N- G- E, -CITY CL.S
PREPARED AND APPROVED BY:
C38ERT F. CLARK
DEPUTY CITY ATTORNEY
APP
AND CORI
Maurice A. Ferre
M A Y 0 R
CiTY OF MIAMI. FL0I11I0A
52
lNTt/l-OFFIGr MEMORANDUM
rO 'toward V. Gary DAYS: August 23 19e4
City Manager g + F,,,�Q-3149-Y
sus�ccr CITY OF MIAMI /UNIVERSITY OF
MIAMI JAMES L. KNIGHT
INTERNATIONAL CENTER -
o«: Donald W. Cather ENTRANCE CANOPY - Resolution
Director of Pubi it Works R`FCRCNccs Assessing Liquidated Damagles
,r & Authorizing Final'Payment
EIVCIOSUREs: (For Commission Meeting of
i
1
The Department of Public Works recommends
the adoption of a resolution accepting
the completed work performed by MET
Construction, Inc., at a total cost of
$97, 649 00 ; a ssess i na a9, -J00. 00 as
liquidated damages for overrun of
contract time; and authorizing a final
payment of $264.90. for CITY OC
MIAMI/UNIVERSITY OF MIAMI JAMES L. KNIGH7
INTERNATIONAL CENTER - ENTRANCE CANOPY.
MET Construction, Inc. has completed the project cons i st i na of
furnishing and installing a structural steel. frame and canonv
assembly, for the entrance to the International Center located at 406
S. E. 2nd Avenue.
The contractor experienced considerable oroblems concerning the
welding of the structural stool frame and many welds had to be
redone. In addition, his canopy subcontractor was not able to
complete the canopy in a timely manner. Both of these items have
caused an overrun to the contract time of 19 calendar days at $500
per calendar day. This was a unit price contract in the amount of
$177,649.00 less $9,500.00 as liquidated damages for 19 days overrun
of contract.
It is now in order for the Commission to accept the completed work
and authorize final payment, after all conditions are met.
Iaz
��v lution attached
cc: Manuel Alvarez
41b5� 6 P
�c�l�
444
FINAL CONSTRUCTION FACT SHEET
FOR THE CITY MANAGER
JOB AME City of Miami/University of Miami James L. Knight
International Center - Entrance Canopy - B-3148-Y
CONTRACTOR MET Construction, Inc.
JOB SCOPE Furnish and install a structural steel frame and canopy
assembly and lighting for the entrance to the International
Center located at 400 S. E. 2 Avenue.
REASON Provide protection from the elements to patrons of the
FOR WORK Center.
SOURCE City of Miami, James L. Knight International Center
OF FUNDS and Parking Garage
PROJECT Bids Received: 1/11/83
HISTORY Contract Awarded: 1/13/83
Preconstruction Meeting: 2/24/83
CONTRACT
TIME
STARTED 2/24/83
CONTRACT
TIME 90 Calendar days plus 2 days delay from rain
SCHEDULED
COMPLETION
DATE 5/26/83
y ACTUAL
COKPLETION
DATE 6/14/83 (An overrun of the contract time by 19 Calendar
days at $500.00/day • $9,500.00)
sID AMOUNT $ 102,474.00
CONTRACT
!'IM COST $ 97,649.00 (Less $9,500 liquidated damages)
CURRENT
ITZK aOR Resolution to accept completed work, assess $9,500
CONSIDERATION liquidated damages, authorize final payment to the
contractor.