HomeMy WebLinkAboutR-85-0426J-85-362 0
HESOLUTIUN NO. 85-426
A RESOLUTION ACCEPTING THE COMPLETED WORK
OF JOE HEIHERTSON EWUIPMENT CU., AT A
TOTAL COST OF $1589U52.'16 FOR CITY WIDE
SANITARY SEWER IMPROVEMENT DISTRICT -
UVERTUWN PHASE I - SR-5501 C&S
(CENTERLINE & SIDELINE SEWERS); AND
AUTHORIZING A FINAL PAYMENT OF $1'17891.96
WHEREAS, there exists a contract dated April 1J, 1984
between the City of Miami and Joe Reinertson Equipment Co.;
and
WHEREAS, the work, has been satisfactorily completed,
and Joe Reinertson Equipment Co. has furnished the required
documents certifying that all bills for labor and materials
have been paid in full in connection with the aforesaid
contract; and
WHEREAS, the City Manager and the Department of Public
Works recommend that the completed work be accepted and
final payment made to the contractor; and
WHEREAS, after a duly advertised public hearing held on
April 11, 1965, to hear objections by persons interested in
or affected by City Commission acceptance of the completed
construction of CITY WIDE SANITARY SEWER IMPROVEMENT -
UVEHTOWN - PHASE I - (BID D) in CITY WIDE SANITARY SEWER
IMPROVEMENT DISTRICT - OVERTOWN - PHASE I - SR-5501 C&S
(centerline & sideline sewers), no objections were
sustained;
NOW, THEREFORE, 8E: IT RESOLVED BY THE COMMISSION OF THE
CITY OF MIAMI, FLURIDA:
Section 1. The completed work performed by Joe
Reinertson Equipment Co. for CITY WIDE SANITARY SEWER
IMPROVEMENT - OVERTUWN - PHASE I - (BID D) in CITY WIDE
SANITARY SEWER IMPROVEMENT DISTRICT - UVERTOWN - PHASE I-
SH-55U1 (centerline & sideline sewers) is hereby approved.
CITY C0141 !,If; �"'N
MEET11's''..
APR 111 19855
T101% 11U. 85--4
Section 2. The proper officials of the City of Miami
are hereby authorized to pay $1'fydyl.gb to Joe Reinertson
Equipment Co. as full and final payment for all work
performed and ail materials furnished in connection with
CITY WIDE SANITARY SEWER IMPROVEMENT UVERTUWw - PHASE I -
(BID D) in CITY WIDE SANITARY SEWER IMPROVEMENT D1aT1iICT -
UVERTOWN - PHASE I - SH-5501 (centerline & sideline sewers).
PASSED AND ADOPTED this filth day of April9
1985.
ATTEST:
-c� � Q
RALPH U UNIUIE,CLTY C RK
PREPARED AND APPROVED BY:
X�
ROBERT F. CLARK
DEPUTY CITY ATTORNEY
MA Y AO _R errg�------
APPROVE U FORM AND CORRECTNESS:
LUCIA A. DUU'HERTY
CITY ATTORNEY
85-426►
- 2 -
4
_ CITY OF MIAMI. PLORIDA
59
INfi�RyOFFItE MEMi�RANOUM
To Randolph B. Rosencrantz DATE March 20, 1985 ME. B=5501
City Manager
SUNJECT CITY WIDE SANITARY SEWER
IMPROVEMENT - OVERTUWN -
PHASE I - ( BID "0" )
FROM REFERENCES Resolution for Final
Payment (SR-5501-C&S)
Donald W. Cather
Director of Public Works ENCLOSURES (For Commission Meeting
The Department of Public Works recommends
adoption of a resolution accepting the
completed work and authorizing a final payment
of $1'1,891.96 to Reinertson Equipment Co., Inc.
for CITY WIDE SANITARY SEWER IMPRUVEMENT -
OVERTOWN - PHASE I - (SIV "D") ah-550-C&S
(centerline and sideline sewers).
Joe Heine;rtson Equipment Co., Inc. has completed the project
consisting of replacing existing deteriorated sanitary sewers
in N.W. 3 Ave. between N.W. 14 - 19 Sts., N.W. 4 Ave. between
N.W. 5 - 9 Sts., N.W. 9 St. between N.N. 4 - 5 Aves., and
N.W. 20 Terrace between N.W. 2 - J Aves. The original
contract amount was for $163,703.20, and the corupleced amount
is 4156,052.76. It was completed on time. The source of
funds is "City Wide Sanitary Sewer Extensions Improvements"
account.
At the Commission meeting of December 13, 1984 Resolution No.
64-143U passed, directing the City Clerk to publish a Notice
of Public Hearing on CITY WIDE SANITARY SEWER IMPRUVEME14T -
OVERTUWN - PHASE 1 - (BID "D") in CITY-WIDE SANITARY SEWER
IMPROVEMENT DISTRICT - OVERTOWN - PHASE I - SR-5501 C&S
(centerline and sideline sewers) at the completion of the
project.
It is now in order for the City Commission io accept the
completed work and authorize final payment, after all
conditions are met.
r:mw
Resolution attached
cc: Alberto Ruder
85-426,
P16
FINAL CONSTRUCTION FACT SHEET
FOR THE CITY MANAGER
JOB NAME City Wide Sanitary Sewer Improvement Overtown
Phase I - B-5501C
CONTRACTOR Joe Reinertson Equipment Co.
JOB SCOPE Replace 0.85 mile of sanitary sewers in deteriorated
condition.
REASON
FOR WORK In conjunction with highway rebuilding.
SOURCE
OF FUNDS City Wide Sanitary Sewer Extensions Improvements
PROJECT Bids Received: 3/8/84
HISTORY Contract Awarded: 1/19/84
Preconstruction Meeting: 5/10/84
CONTRACT
TIME
STARTED 8/3/84
CONTRACT 40 Working days plus 5 days delay from rain,
TIME 10 days of extra work, and
32 days delay in getting M.D. Water
and Sewer to pump down surcharged -
sewer mains so they could be televised.
SCHEDULED
COMPLETION
DATE 12/11/84
ACTUAL
COMPLETION
DATE 12/11/84
BID AMOUNT $ 163,703.00
CONTRACT
FINAL COST $ 158,052.76
CURRENT
ITEM FOR Resolution to accept completed work and authorize
CONSIDERATION final payment to the contractor.
85-426
N
t
Ralph G. Ongie March 2U, 1y65 B-57J1
City Clerk
CITY W.LDE �;ANI'TARY SEviEh
IMPhJVEMENT - OVERTJ4N -
PHASE 1 - (BID "D")
Request to Publish Woti.:e
for Public Hearing
D�-Ca , e#'
Director of Public Works (Copy of Res. 84-14.50
Please arrange to publish a Notice of Public Hearing
for objections to the acceptance by the City
Commisssion of the completed construction of C17Y WIDE
SANITARY SEWER IMPRUVEMENT - UVEKTJWN - PiiASE 1 - (BID
"U")-SR-5501 for the Commission meeting of April 11,
105.
attached for your information is Resolution No. 84-1430
which authorizes the City Clerk. ro publish this Notice
of Public Hearing.
44:low
cc: Alberto Ruder,
85-426�