i A RESULUTIUN ACCEPTING THE COMPLETED WURK
j OF JUE HEINERTSUN EQUIPMENT CU., INC. AT
A TUTAL CUST OF $129,211.20 FOR CITY WIDE
SANITARY SEWER IMPROVEMENT - SUUTH WEST
I STREET (BID "D") SR-5499; AND
AUTHURILINU A FINAL PAYMENT OF $1j,j22.25
i
WHEREAS, there exists a contract dated October 16, 1984
between the City of Miami and Joe Reinertson Equipment Co.,
Inc.; and
WHEREAS, the work has been satisfactorily completed,
and Joe Reinertson Equipment Co., Inc. has furnished the
required documents certifying that all bills for labor and
a
c,
p.
materials have been aid in full in connection with the
aforesaid contract; and
WHEREAS, the City Manager and the Department of Public
Works recommend that the completed work be accepted and
final payment made to the contractor; and
WHEREAS, after a duly advertised public hearing held on
E
k„
April 11 , 1985, to hear objections by persons interested in
or affected by City Commission acceptance of the completed
.,.b;;.
�S
construction of CITY WIDE SANITARY SEWER IMPRUVEMENT - SOUTH
WEST 16 STREET - (BID "D") in CITY WIDE SANITARY SEWER
IMPROVEMENT - SOUTH WEST 16 STREET - (BID "D") DISTRICT
SR-5499, no objections were sustained;
NOW, THEREFORE, BE IT RESOLVED BY THi: COMMISSION OF THE
CITY OF MIAMI, FLORIDA:
Section 1. The completed work performed b Joe
P P Y
Reinertson Equipment Co., Inc. for CITY WIDE SANITARY SEWER
IMPROVEMENT - SUUTH WEST 16 STREET - (BID 1I1)11) in CITY WIDE
SANITARY SEWER IMPROVEMENT - SUUTH WEST 16 STREET - (BID
"D") DISTRICT SR-5499 is hereby approved.
CITY COMMISSION
MEETING OF
APR 111 J985
RESOLUNW% wo. v_.5-4
REMARKS.__
a
Section 2. The proper officials of the City of Miami
are hereby authorized to pay $13,322.25 to Joe Reinertson
t
Equipment Co., Inc. as full and final payment for all work
i performed and all materials furnished in connection with
i CITY WIDE SANITARY SEWER IMPROVEMENT - SUUTH WEST 1b
STREET - (BID "D") in CITY WIDE SANITARY SEWER
IMPROVEMENT - SOUTH WEST lb STREET - (lslll I'll") DISTRICT
SR-5499.
PASSED AND ADOPTED this llth day of Ate_,
1985•
Maurice A F rre
M A Y U R
k
ATTEST:
Icy
',.4._.. KAL4FH G. ONGIE, CITY CL�sK
PREPARED AND APPROVED BY:
� �. Moe
RUBERT F. CLARK
DEPUTY CITY ATTORNEY
APPROVE /S FORM AND CORRECTNESS:
XUCA A. DOU ERTY
CITY ATTORNEY
- 2 -
85-425
0
CITE OF MIAMI, FLORIDA58 '
IN1r10R-0FFICE MEMORANOUM
To Randolph B. Rosencrantz DATE. March 5, 1985 ME B-5499
City Manager
FROM
Donald W. Ca•thgr
director7+of �6I(ic Works
CITY WIDE SANITARY SEWER
SUBJECT IMPROVEMENT - SOUTH WEST
16 STREET - (BID "D11)
Resolution for Final
REFERENCES Payment
ENCLOSURES. (For Commission Meeting
of April 11. 1985)
The Department of Public Works recommends
adoption of a resolution accepting the complete
work and authorizing a final payment of
$13,322.25 to Reinertson Equipment Co., Inc.
for CITY WIDE SANITARY SEWER IMPROVEMENT -
SOUTH WEST 16 STREET - (BID "D11) SR-5499.
ram:
Joe Reinertson Equipment Co., Inc. has completed the project
consisting of replacing an existing 8f1 - 10t1 sewer pipe with
extra strength vitrified clay or ductile iron pipe together
with all necessary appurtenances located in S.W. 16 Street
r. $
between S.W. 22 - 27 Avenues. The original contract amount
was for $129,275.00, and the completed amount is $129,211.20.
It was completed on time. The source of funds is "City Wide
Sanitary Sewer Extensions Improvement" account.
At the Commission meeting of July 30, 1984 Resolution No. 84-
806 passed, directing the City Clerk to publish a Notice of
Public Hearing on CITY WIDE SANITARY SEWER IMPROVEMENT -
SOUTH WEST 16 STREET - (BID "D") SR-5499 at the completion of
the project.
is now in order
>leted work and
litions are met.
esolution attached
Alberto Ruder
for the City Commission to
authorize final payment,
85-4251
FINAL CONSTRUCTION FACT SHEET
FOR THE CITY MANAGER
JOB NAME City Wide Sanitary Sewer Improvement - S. W. 16
Street (Bid D) - SR-5499-C
CONTRACTOR Joe Reinertson Equipment Co., Inc.
JOB SCOPE Replacement of existing 8"-10" sewer pipe with
extra strength vitrified clay and ductile iron
pipe together with all necessary appurtenances
located in S. W. 16 Street between S. W. 22-27
Avenues.
REASON
FOR WORK In conjunction with highway rebuilding project.
SOURCE
OF FUNDS City Wide Sanitary Sewer Extensions Improvement
PROJECT Bids Received: 6/14/84
HISTORY Contract Awarded: 7/30/84
Preconstruction Meeting: 9/13/84
CONTRACT
TIME
STARTED 10/30/84
CONTRACT
TIME 50 Working days
SCHEDULED
COMPLETION
DATE
1/8/85
ACTUAL
COMPLETION
DATE
12/11/84
BID AMOUNT
$129,275.00
CONTRACT
FINAL COST
$129,211.20
CURRENT
ITEM FOR
Resolution to accept completed work and authorize
CONSIDERATION final payment to the Contractor.
85-425
CITY CF MIAMI. FLORIDA
,N?'ER-OFFIC= ?CIE ICRANZU'I
Ralph G. Ongie March 7, 1985 n-5499
City Clerk
CITY WIDE SANITARY SE4ER
,r1 IMPROVEMENT - SUUTH WEST
16 STREET - (BIU "Dn)
, Request to Publish Notice
for Public Hearing
Donald W. Cather
Director of Public Works `14Z'- `"y (Copy of Res. 84-80b
Please arrange to publish a Notice of Public Hearing
for objections to the acceptance by the City
Commisssion of the completed construction of CITY WIDE
SANITARY SEdER IMPROVEMENT - SUUTH WEST 16 STREET -
(B1D "D")-SR-5499 for the Commission meeting of April
11, 1985.