HomeMy WebLinkAboutR-85-0633RESOLUTION No. 8 "`6 3
A RESOLUTION AGCEPTING THE COMPLETED WORK
PERFORMED BY MARTIN CHANEY EQUIPMENT
RENTALS$ INC., AND UNITED STATES FIDELITY
AND GUARANTY COMPANY AS SURETY, AT A
TOTAL COST OF $294779-763.51 FOR AUBURN
SANITARY SEWER IMPROVEMENT IN AUBURN
SANITARY SEWER IMPROVEMENT DISTRICT - SR-
5475a-C (CENTERLINE SEWERS); ASSESSING
$6,000.00 AS LIQUIDATED DAMAGES FOR 12
DAYS OVERRUN OF CONTRACT TIME; AND
AUTHORIZING A FINAL PAYMENT OF $569850.95
TO BE MADE JOINTLY TO MARTIN CHANEY
EQUIPMENT RENTALS, INC. AND UNITED STATES
FIDELITY AND GUARANTY COMPANY, THE
SURETY.
WHEREAS, there exists a contract dated October 100 1981
between the City of Miami and Martin Chaney Equipment
Rentals, Inc.; and
WHEREAS, the work, has been satisfactorily completed,
and Martin Chaney Equipment Rentals, Inc. and United States
Fidelity and Guaranty Company, the surety, have furnished
the required documents certifying that all bills for labor
and materials have been paid in full in connection with the
aforesaid contract; and
WHEREAS, liquidated damages for overrun of contract
time of 12 days should be deducted from the final payment
due the contractor and the surety; and
WHEREAS, the City Manager and the Department of Public
Works recommend that the completed work be accepted and
final payment made to the contractor and the surety; and
WHEREAS, after a duly advertised public hearing held on
June 13, 1985, to hear objections by persons interested in
or affected by City Commission acceptance of the completed
construction of AUBURN SANITARY SEWER.IMPROVEMENT in AUBURN
SANITARY SEWER IMPROVEMENT DISTRICT - 3RC-5475-C (Centerline
aeweri) no objections were sustained;
If C01011SSION
MEETING OF
JUN 113 1985
RESOLUTiwi uu. 85763
REM4RKS
I'
d NQW, THtREPORE 1 BE IT RESOLVED BY THE COMMI8810N OF t
=1 OF MIAMI, FLORIDA
` Section 1 . The completed wf 'Work perormed by Martifl
Chaney Equipment Rentals, Inc. and United Sates Fidelity and
C
Guaranty Company, the surety, for AUBURN SANITARY SEWER
IMPROVEMENT in AUBURN SANITARY SEWER IMPROVEMENT DISTRICT
SR-5475-C (Centerline sewers) is hereby approved and
accepted at a total cost of $2,477.763.51.
Section 2. That liquidated damages in the amount of
$6,OOD.00 for 12 days overrun of contract time shall be
deducted from the balance due the contractor and the surety.
Section 3. The proper officials of the City of Miami
fi are hereby authorized to pay jointly to Martin Chaney
Equipment Rentals, Inc. and United States Fidelity and
r,
Guaranty Company, the surety, after ail adjustments are
x made, a balance of $56,850.95 as full and final payment for
all work performed and all materials furnished in connection
z
with AUBURN SANITARY SEWER IMPROVEMENT in AUBURN SANITARY
SEWER IMPROVEMENT DISTRICT - SR-5475-C (centerline sewers).
PASSED AND ADOPTED this 13th day of June ,
y 1985.
f,
Maurice A. Ferre
M A Y 0 R
ATTEST:
7RA H G. ONGIE, CITY C K
PREPARED AND APPROVED BY:
-' ROBERT F. CLARK
DEPUTY CITY ATTORNEY
APPROV O FORM AND CORREOTNESB:
L. O. A DOU HERTY
CITY ATTORNEY
85-633
01" Oft MIAMI, r`LONIOA
68
INTER-OltFICC MCMOPtAt DUM
' `� B-5475-C
Honorable Mayor and Members , I+,.
I�AtE: RtLi:
M. of the City Commission
AUBURN SANITARY SEWER
guerEct:
IMPROVEMENT -
Resolution Assessing Liquidated
Sergio Pereir Damages and Authorizing Final
Front: City Manager impEiFENe & Payment
(For Commission Meeting of
ENcLbsupEs: June 13, 19 8 5)
The Department of Public Works recommends
the adoption of a resolution accepting
the completed work performed by Martin
Chaney Equipment Rentals, Inc. and United
States Fidelity and Guaranty Company, the
surety, at a total cost of $2,477,763.51;
assessing $6,000.00 as liquidated damages
for overrun of contract time; and
authorizing a final payment of
$56,850.95, for AUBURN SANITARY SEWER
IMPROVEMENT in AUBURN SANITARY SEWER
IMPROVEMENT DISTRICT - SR-5475-C
(Centerline sewers).
Martin Chaney Equipment Rentals, Inc. and United States
Fidelity and Guaranty Company have completed the project
consisting of constructing a new sewage system including 811-
24" sewer pipe, 6" house laterals together with all necessary
appurtenances in the area bounded by West Flagler Street,
N.W. 7 Street, N.W. 27-37 Avenues.
}°
The contractor began work on the project and brought it to a
state of beneficial use in early 1983, but, was financially
unable to finish the work. Essentially, only surface
restorations remained to be completed at that time. The
surety at first resisted taking over and completing the
project, preferring that we prepare plans and specifications
and let out a contract for the work. They finally agreed to
finish the work, and have just recently done so. It is
recommended that liquidated damages in the amount of $6,000
be assessed. This represents the 12 calendar days, at $500
per day, between the expiration of the contractor's
construction time and the taking of beneficial use of the
h
improvements by the City. The total construction cost for
the project will therefore be $2,477,745.51 less $6,000 for
liquidated damages.
85-633
it
d.
3
k
Honorable Mayor and McMbers
t: of the City Commission
t. It is now in order for the Commission to accept the completed
work and authorize final payment, after all conditions are
met.
az
ReG�olution attached
'` cc: Alberto Ruder
PINAL CONSTBUMC� FACTS� T
FOR R
THE CITY MANAGE
JOB NAMS Auburn Sanitary Sewer Improvement SR-5475C (Centerline Sewer)
CONTRACTOR Martin Chaney Equipment Rentals, Inc. and
United States Fidelity & Guaranty Company, the surety
JOB SCOPE Construct a new sewage system including 8"-24" sewer
pipe, 6" ho'use laterals, together with all necessary
appurtenances in the area bounded by West Flagler
Street, N. W. 7 Street, N. W. 27-37 Avenues.
REASON
FOR WORK Provide sanitary sewers to previously unsewered area
SOURCE
OF FUNDS Sanitary Sewer G. 0. Bond Fund
PROJECT Bids Received: 9/10/81
HISTORY Contract Awarded: 10/7/81
Preconstruction Meeting: 11/4/81
CONTRACT
TIME
STARTED 12/28/81
CONTRACT
TIME 220 Working days plus 35 days delay from rain.
SCHEDULED
COMPLETION
DATE 12/30/82
ACTUAL
COMPLETION
DATE 1/11/83 (12 Calendar day overrun of contract time at
$500.00 per calendar day = $6,000.00)
BID AMOUNT $2,731,825.50
CONTRACT
FINAL COST $2,477,763.51 (Less $6,000 liquidated damages)
CURRENT Resolution to accept completed work, assess
ITEM FOR $6,000.00 liquidated damages, and authorize
CONSIDERATION final payment to the surety, United States
Fidelity and Guarantee Company.