HomeMy WebLinkAboutR-85-1220j L85-1161 V 4 RESOLUTION NO. A RESOLUTION ACCEPTING THE COMPLETED WORK OF FRE CONSTRUCTION CO., INC. AT A TOTAL COST OF $737,814.51 FOR ALLAPATTAH INDUSTRIAL AREA HIGHWAY IMPROVEMENT - PHASE I BIDS "A, B, C"; ASSESSING $5,000.00 AS LIQUIDATED DAMAGES FOR 10 DAYS OVERRUN OF CONTRACT TIME; AND AUTHORIZING A FINAL PAYMENT OF $84,699.16. WHEREAS, there exists a contract dated December 8, 1983 between the City of Miami and FRE Construction Co., Inc.; and WHEREAS, the work, has been satisfactorily completed, and FRE Construction Co., Inc., has furnished the required documents certifying that all bills for labor and materials have been paid in full in connection with the aforesaid contract; and WHEREAS, liquidated damages for overrun of contract time of 10 days should be deducted from the final payment due the contractor and the surety; and WHEREAS, the,City Manager and the Department of Public Works recommend that the completed work be accepted and final payment made to the contractor; and WHEREAS, after a duly advertised public hearing held on December 19, 1985, to hear objections by persons interested in or affected by City Commission acceptance of the completed construction of ALLAPATTTAH INDUSTRIAL AREA HIGHWAY IMPROVEMENT - PHASE I BIDS "A, B, C", no objections were sustained; NOW, THEREFORE, BE IT RESOLVED BY THE COMMISSION OF THE CITY OF MIAMI, FLORIDA: Section 1. The completed work performed by FRE Construction Co., Inc. for ALLAPATTAH INDUSTRIAL AREA HIGHWAY IMPROVEMENT - PHASE I BIDS "A, B, C", at a total cost of $737,814.51, is hereby approved. CITY COMMISSION MEETING OF DEC 19 1985 ION ao.8r—i ' V � R 6 Section 2. That liquidated damages in the amount of $5,000.00 for 10 days overrun of contract time shall be deducted from the balance due the contractor and the surety. Section 3. The proper officials of the City of Miami are hereby authorized to pay $84,699.16 to FRE Construction Co., Inc. as full and final payment for all work performed and all materials furnished in connection with ALLAPATTAH y INDUSTRIAL AREA HIGHWAY IMPROVEMENT - PHASE I BIDS "A, B, i C". PASSED AND ADOPTED this 19th day of December , 1985. XA IER L. SUARE , MAYOR ATTEST: RA-TTY HIRAI, CITY CLERK PREPARED AND APPROVED BY: a 7 ROBERT F. CLARK , CHIEF DEPUTY CITY ATTORNEY APPROVED S TO FORM AND CORRECTIJESS: LUCIA A. OUGHERTY CITY ATTORNEY - 2 - 8"'12zo 1 i 'i j CItY OF MIAMI, FLORIDA INTER -OFFICE MEMORANDUM 59 -TO Honorable Mayor and DATE: DEC 12 985 PILEt B-4485 Members of the City Commission SUBJEC; ALLAPATTAH INDUSTRIAL AREA HIGHWAY IMPROVEMENT - PHASE I BIDS "A, B, C" FROM REFERENCES: Resolution for Final Payment Cesar H. Odio ENCLOSURES: (For Commission Meeting City Manager of December 19, 1985) It is recommended that a resolution be adopted accepting the completed work performed by FRE Construction Co., Inc. at a total cost of $737,814.51; assessing $5,000.00 as liquidated damages for overrun of contract time; and authorizing a final payment of $84,699.16, for ALLAPATTAH INDUSTRIAL AREA HIGHWAY IMPROVEMENT - PHASE I BIDS "A, B, C". P n ERE Construction Co., Inc. has completed the project consisting of constructing 1.5 miles of streets, including; clearing and grading, asphaltic paving, concrete curbs and/or gutters, concrete sidewalk, storm sewers, sanitary sewer modifications, and landscaping. The project is located between N.W. 21 St. to N.W. 21 Terrace between N.W. 17 - 27 Avenues. Poor organization and supervision by the contractor contributed considerably to his inability to maintain good production. This poor progress caused the contractor to overrun the contract time by 10 calendar days. The contract provides for the assessment of liquidated damages for failure to complete the work on time at the rate of $500 per calendar day. This was a unit price contract in the amount of $737,314.51 less $5,000.00 as liquidated damages for 10 days overrun of contract. It is now in order for the City Commission to accept the completed work and authorize final payment, after all conditions are met. DWC:LEL:az Alta Yeti �5. -1220 I CITY OF MIAMI. FLORIDA INTER -OFFICE MEMORANDUM TO Matty Hirai DATE December 3, 1985 FILE: City Clerk sUDJECT Re -scheduling of Notices for Public Hearings FROM Donald W. C at he r REFERENCES Director of Public Works ,'-�` �• f ENCLOSURES. This is to request a re -scheduling of the time and date of the notices for Public Hearings previously scheduled for December 12, 1985 at 3:30 p.m. on the following projects. a. Kirkland Sanitary Sewer Improvements j b. Citywide Sanitary Sewer Improvements - f Allapattah Phase II c. Allapattah Industrial Area Highway Improvement Phase I Bids "A, B, C". The corrective date and time of the Public Hearings is December 19, at 11:30 a.m. Would you please make the necessary arrangements to inform the general public. Additionally make arrangements to issue a notice for Public Hearing on December 19, 1985 to hear objections to an increase in contract amount for Curtis Park Elderly Meals Facility. Attached is a suggested text for the advertisement. AB:az cc: Alberto Ruder rHls co, l :7as� S 3 �v3 4 — — C;TY OF MIAMI, FLORIDA INTER -OFFICE MEMORANDUM TO, Matty Hirai DATE November 19, 1985 VILE B-4485 City Clerk SUBJECT ALLAPATTAH IHNDUSTRIAL AREA HIGHWAY IMPROVEMENT - PHASE I(Bids A, B, C) Request to Publish Notice FROM REFERENCES for Public Hearing Donald W. Cather Dir eater of APu Works ENCLOSURES Please arrange to publish a Notice of Public Hearing for objections to the acceptance by the City Commission of the completed construction of ALLAPATTAH INDUSTRIAL AREA HIGHWAY IMPROVEMENT - PHASE I H-4485 for the Commission meeting of December 12, 1985. The Resolution that will authorize the City Clerk to advertise for public hearing is scheduled to be considered at the Commission meeting of November 26, 1985. 4. EMP:az cc: Alberto Ruder r,I , 8" -1220