A RESOLUTION ACCEPTING THE COMPLETED WORK
OF 14URTON ROOFING CORP. AT A TOTAL COST
OF $20,833.50 FOR COCONUT GROVE
EXHIBITION CENTER - MEZZANINE ROOF
REPLACEMENT; AND AUTHORIZING A FINAL
PAYMENT OF $3,307.35
WHEREAS, there exists a contract dated April 4, 1985
between the City of Miami and Murton Roofing Corporation;
and
WHEREAS, the work has been satisfactorily completed,
and Murton Roofing Corporation has furnished the required
documents certifying that all bills for labor and materials
have been paid in full in connection with the aforesaid
contract; and
WHEREAS, the City Manager and the Department of Public
Works recommend that the completed work be accepted and
final payment made to the contractor;
NOW, THEREFORE, BE IT RESOLVED BY THE COMMISSION OF THE
CITY OF MIAMI, FLORIDA:
Section 1. The completed work performed by Murton
Roofing Corporation, for COCONUT GROVE EXHIBITION CENTER -
MEZZANINE ROOF REPLACEMENT, at a total cost of $20,833.50,
is hereby approved.
Section 2. The proper officials of the City of Miami
are hereby authorized to pay $3,307.35 to Murton Roofing
Corporation as full and final payment for all work performed
and all materials furnished in connection with COCONUT GROVE
EXHIBITION CENTER MEZZANINE ROOF REPLACEMENT.
C177f CODBUSSION
MEETING OF
JAN1988
AM -- A
6$.
lJ
PASSED AND ADOPTED this 9th day of JANUARY ,
1980-
ATTEST:
A,TYH I RA-Il .4 �-I T Y G L L R K
PREPARED AND APPROVED BY:
ROBERT F. -LLA
CHIEF DEPUTY CITY ATTORNEY
APPROVES TU FORM AND CORRECTNESS:
L V V I n n• v v v v
CITY ATTORNEY
- 2 -
.
L.
SIT
M A Y0 R
A a
i
CITY OF MIAMI. FLORIDA
INTER -OFFICE MEMORANDUM
Honorable Mayor and DATE! JAN ` x 1986 KYLE. B-2887
TO. Members of the City
Commission COCONUT GROVE EXHIBITION
SUBJECT CENTER MEZZANINE - ROOF
A REPLACEMENT
Resolution for Final
1 Payment
FROM: REFERENCES:
Cesar H. Odio
City Manager ENCLOSURES: (For Commission Meeting
of January 9, 1986)
It is recommended that a resolution be adopted
accepting the completed work and authorizing a
final payment of $3,307.35 to Murton Roofing
Corporation for COCONUT GROVE EXHIBITION CENTER
MEZZANINE ROOF REPLACEMENT.
Murton Roofing Corporation has completed the project that
consisted of removing and reroofing approximately 7000 square
feet of flat roof over the mezzanine, including: insulation,
four -ply roofing, drip strips, cant, flashing, and drains.
The work is located on the easterly side of the exhibition
center at 3360 Pan American Drive at Dinner Key.
The
original contract amount was for $22,850.00, and the
completed amount is $20,833.50. The source of funds is
"Coconut Grove Exhibition Center - Additional Work" account.
acce
the
It is now iorkorder and for authorize zethe e t fi nal Commis payment sion � aftert al 1
completed w
conditions are met.
tEL:az
ution attached
cc: Alberto Ruder
4 4
FINAL CONSTRUCTION FACT SHEET
JOB NAME Coconut Grove Exhibition Center Mezzanine - Roof
Replacement - B-2887
CONTRACTOR Murton Roofing Corp. (Not) -Minority)
JOB SCOPE Remove and reroof 7000 sq. ft. of the flat roof
over the mezzanine including insulation, four ply
roofing, drip strips, cant, flashing and drains,
located at 3360 Pan American Drive, Dinner Key.
REASON Leaking roof.
FOR WORK
SOURCE Coconut Grove Exhibition Center - Additional Work
OF FUNDS
PROJECT Bids Received: 1/22/85
HISTORY Contract Awarded: 2/14/85
Preconstruction Meeting: 4/11/85
CONTRACT
TIME
STARTED 4/30/85
CONTRACT
TIME 15 Working days
SCHEDULED
COMPLETION
DATE 5/20/85
ACTUAL
COMPLETION
DATE 5/3/85
BID AMOUNT $22,850.00
CONTRACT
FINAL COST $20,833.50
CURRENT
ITEM FOR Resolution to accept completed work, and authorize
CONSIDERATION final payment to the contractor.