RESOLUTION NO. 8 9 a-1
A RESOLUTION ACCEPTING THE COMPLETED WORK OF
COMMUNITY ASPHALT CORPORATION AT A TOTAL
COST OF $599,029.24 FOR CITY WIDE
RESURFACING PROJECT - WYNDWOOD/OVERTOWN/PARK
WEST B-4499; AND AUTHORIZING A FINAL PAYMENT
OF $62,620.96.
WHEREAS, there exists a contract dated May 16, 1985 between
the City of Miami and Community Asphalt Corporation; and
WHEREAS, the work has been satisfactorily completed and
Community Asphalt Corporation has furnished the required
documents certifying that all bills for labor and materials have
been paid in full in connection with the aforesaid contract; and
WHEREAS, the City Manager and the Department of Public Works
recommend that the completed work be accepted and final payment
made to the contractor;
NOW, THEREFORE, BE IT RESOLVED BY THE COMMISSION OF THE CITY
OF MIAMI, FLORIDA:
Section 1. The completed work performed by Community
Asphalt Corporation for CITY WIDE RESURFACING PROJECT -
WYNDWOOD/OVER TOWN/ PARK WEST at a total cost of $594,029.24, is
hereby approved.
Section 2. The proper officials of the City of Miami are
hereby authorized to pay $62,620.96 to Community Asphalt
Corporation as full and final payment for all work performed and
all materials furnished in connection with CITY WIDE RESURFACING
PROJECT - WYNDWOOD/OVERTOWN/PARK WEST.
r.
�;
j
CITY COMMISSION
MEETING OF
FEB 19 00
RESOLUTION nu. 86 O
REMARKS _
PASSED AND ADOPTED this 13th day of FEBRUARY , 1986.
PREPARED AND APPROVED BY:
TY ATTORNEY
APPROVED AS TO FORM AND CORRECTNESS:
CITY ATTORNEY
{
CITY OF MIAM1, FLORIDA
INTER -OFFICE MEMORANDUM 20
To:
Honorable Mayor and FF4 6 1986 B-4499
Members of the City Commission vv DATE: FILE:
CITY WIDE RESURFACING PROJECT
SUBJECT: WYNDWOOD/OVERTOWN/PARK WEST
Resolution for Final
Payment
FROM: Cesar H. Odio
City Manager
REFERENCES:
(For Commission Meeting
ENCLOSURES: of February 13, 1986)
It is recommended that a resolution be adopted
accepting the completed work and authorizing a
final payment of $62,620.96 to Community
Asphalt Corporation for CITY WIDE RESURFACING
PROJECT - WYNDWOOD/OVERTOWN/PARK WEST.
Community Asphalt Corporation has completed the project that
consisted of the application of new asphaltic concrete
overlay, replacement of broken sidewalk and curb and gutter,
and the construction of handicapped ramps on North 5th, 6th,
10th and 11th Streets between Biscayne Boulevard and N. W.
7th Avenue; and on N. W. 20th and 25th Streets between N.
Miami Avenue and N. W. 2nd Avenue. The original contract
amount was $652,.691, and the completed cost is $599,029.24•
The source of funds is Local Option Gas Tax Funds.
It is now in order for the City Commission to accept the
completed work and authorize final payment, after all
conditions are met.
-iL DW : LEL : vh
solution attached
cc: Alberto Ruder
a
A
FINAL CONSTRUCTION FACT SHEET
JOB NAME City Wide Resurfacing Project -
Wyndwood/Overtown/Park West - B-4499
CONTRACTOR Community Asphalt Corporation
JOB SCOPE New asphaltic concrete overlay, replacement of
broken sidewalk, curb and gutter located in area
bounded by North 5, 6, 10, 11 Streets between
Biscayne Blvd. and N.W. 7 Avenue also N.W. 20-25
Streets between N. Miami Avenue and N.W. 2 Avenue.
REASON Uneven street surfaces and broken sidewalk and curb
FOR WORK and gutter.
SOURCE Local Option Gas Tax Funds
OF FUNDS
PROJECT Bids Received: 12/11/84
HISTORY Contract Awarded: 1/10/85
Preconstruction Meeting: 3/18/85
CONTRACT
TIME
STARTED 6/14/85
CONTRACT
TIME 80 Working days plus 10 days delay from rain
and 9 days delay from utility
adjustments
SCHEDULED
COMPLETION
DATE 11/2/85
ACTUAL
COMPLETION
DATE 11/2/85
BID AMOUNT $652,691.O0
CONTRACT
FINAL COST $599,029.24
CURRENT
ITEM FOR Resolution to accept completed work, and authorize
CONSIDERATION final payment to the contractor.