RESOLUTION NO. 8 6 - 8 9
A RESOLUTION ACCEPTING THE COMPLETED WORK
OF MET CONSTRUCTION, INC,. AT A TOTAL COST
OF $116,587.00 FOR DINNER KEY MARINA -
ELECTRICAL IMPROVEMENTS; AND AUTHORI7_ING A
FINAL PAYMENT OF $18,129.60.
WHEREAS, there exists a contract dated July 18, 1985
between the City of Miami and MET Construction, Inc.; and
WHEREAS, the work, has been satisfactorily completed by
MET Construction, Inc. and they have furnished the required
documents certifying that all bills for labor and materials
have been paid in full in connection with the aforesaid
contract; and
WHEREAS, the City Manager and the Department of Public
Works recommend that the completed work be accepted and final
payment made to the contractor;
NOW, THEREFORE, BE IT RESOLVED BY THE COMMISSION OF THE
CITY OF MIAMI, FLORIDA:
Section 1. The completed work performed by MET
Construction, Inc. for DINNER. KEY MARINA - ELECTRICAL
IMPROVEMENTS at a total cost of $116,587.00 is hereby
approved.
Section 2. The proper officials of the City of Miami are
hereby authorized to pay $18,129.60 to MET Construction, Inc.
as full and final payment for all work performed and all
materials furnished in connection with DINNER KEY MARINA -
ELECTRICAL IMPROVEMENTS.
CITY COMMISSION
MEETING OF
FEB 13 f
ilia. 8R -
V.
PASSED AND ADOPTED this 13th day of FEBRUARY , 1986.
ATTES .
MATTY HIRAI, CITY CLERK
PREPARED AND APPROVED BY:
y
CHIEF DEPU ITY ATTORNEY
APPROVED AS TO FORM AND CORRECTNESS:
�p
A 04a
EMIA A. E
CITY ATTORNEY
- 2 -
lJ A E Z
MAYOR
JBG 0 fl 0
.it
CITY OF MIAMI, FLORIDA
INTER -OFFICE MEMORANDUM
V.
19
TO, Honorable Mayor and Members DATE: FEB 6 1986 FILE:,g-3202-A
of the City Commission
SUBJECT: DINNER KEY MARIPlA -
ELECTRICAL IMPROVEMENTS
Resolution for Final
FROM: REFERENCES, Payment
Cesar H. Odi o
City Manager kP ENCLOSURES: (For Commission Meeting
of February 13, 1986)
It is recommended that a resolution be
adopted accepting the completed work and
authorizing a final payment of $18,129.60 to
MET Construction, Inc. for DINNER KEY
MARINA - ELECTRICAL IMPROVEMENTS.
MET Construction, Inc. has completed the Dinner Key Marina -
Electrical Improvements project. The work consisted of
constructing a bank of eight - 4" ducts to extend Florida
Power and Light Company's primary electric service to two
proposed transformer areas near the existing marina bulkhead,
also the construction of a switching vault and a
communications room, all located in the Dinner Key Marina
parking lot area. The original contract amount was for
$116,587.00, and the completed amount is $116,587.00. It was
completed on time.
It is now in order
completed work and
conditions are met.
solution attached
Alberto Ruder
for the City Commission to accept the
authorize final payment, after all
'I
FINAL CONSTRUCTION FACT SHEET
JOB NAME
Dinner Key Marina - Electrical Improvements B3202-A
CONTRACTOR
MET Construction, Inc.
JOB SCOPE
Construct a bank of 8 - 4" ducts to extend FP&L primary
electric service to two proposed transformer areas near
the existing bulkhead, also construct a switching vault
and a communications room located in the Dinner Key
Marina parking areas.
REASON
Provide primary electric service for future marina
FOR WORK
development and 3 phase electric service to the
Dockmaster's Office
SOURCE
Dinner Key Marina - Renovation/Expansion
OF FUNDS
PROJECT
Bids Received: 5/21/85
HISTORY
Contract Awarded: 6/13/85
Preconstruction Meeting: 6/24/85
CONTRACT
TIME
STARTED
i
8/5/85
CONTRACT
TIME
60 Working days plus 7 days delay from rain
1 day delay from hurricane warning
36 days delay by Public Works for
extra work and scheduling of
contractors work, not required in
contract specs., so as to minimize
inconvenience to J.P.s restaurant
marina patrons, and exhibition
center events.
SCHEDULED
COMPLETION
DATE
1/3/86
ACTUAL
' COMPLETION
DATE
1/3/86
BID AMOUNT
$116,587.00
i
CONTRACT
FINAL COST
$116,587.00
CURRENT
ITEM FOR
Resolution to accept completed work, and authorize
CONSIDERATION
final payment to the contractor.