HomeMy WebLinkAboutR-86-0185J-86-199
RESOLUTION NO.
A RESOLUTION ACCEPTING THE COMPLETED WORK
OF CUYAHOGA WRECKING CORPORATION AT A
TOTAL COST OF $148,816.64 FOR BAYFRONT
AND
PARK AUDITORIUM - DEMOLITION;
AUTHORIZING A FINAL PAYMENT OF $14,881.66.
WHEREAS, there exists a contract dated March 30, 1985
between the City of Miami and Cuyahoga Wrecking Corporation; and
WHEREAS, the work has been satisfactorily completed and
Cuyahoga Wrecking Corporation has furnished the required
documents certifying that all bills for labor and materials have
been paid in full in connection with the aforesaid contract; and
WHEREAS, the City Manager and the Department of Public Works
recommend that the completed work be accepted and final payment
made to the contractor;
NOW, THEREFORE, BE IT RESOLVED �, fH£ )MMISSION OF THE CITY
OF MIAMI, FLORIDA:
Section 1. The completed work performed by Cuyahoga
Wrecking Corporation for BAYFRONT PARK AUDITORIUM - DEMOLITION at
a total cost of $148,816.64 is hereby approved.
Section 2. The proper officials of the City of Miami are
hereby authorized to pay $14,881.66 to Cuyahoga Wrecking
Corporation as full and final payment for all work performed and
all materials furnished in connection with BAYFRONT PARK
AUDITORIUM - DEMOLITION.
CUT COI+a SSIOH
MBETING OF
MAR 18 I M
PASSED AND ADOPTED this _Latjl_ day of MARCH '
1986.
. t4
X V SUAIEZ
MAYOR
PREPARED AND APPROVED BY:
ROBERT K
CHIEF DEPUTY CITY ATTORNEY
APPROVED TO
FOR` AND CORRECTNESS:
LU%J Lm ' ....-
CITY ATTORNEY
CITY OF MIAMI. FLORIDA
INTER -OFFICE MEMORANDUM
Honorable Mayor and
TO; Members of the City Commission
FRoM: Cesar H. Odio
city Manager
11
MAR 12 PILE: B-3213A
DATE:
BAYFRONT PARK AUDITORIUM -
SUSJECT: DEMOLITION
Resolution for Final
Payment
REFERENCES:
(For Commission Meetin.6
ENCLOSURES: of March 139 1986)
It is recommended that a resolution be adopted
accepting the completed work and authorizing a
final payment of
Corporation 14,8or•66to BAYFRONTuyahoga
PARK
Wreaking
AUDITORIUM - DEMOLITION.
Cuyahoga Wrecking Corporation has completed the project that
consisted of the demolition The originalthe dicontract torium at amount the owas
end of Bayfront Park.
$165,000, and the completed cost is $1489816.64. The source
of funds is Bayfront Park Demolition.
It is now in order for the City Commission to accept the all
completed work and authorize final payment,
conditions are met.
DW L : v h
X/Olution attached
cc: Alberto Ruder
SG- a-
FINAL CONSTRUCTION FACT SHEET
JOB NAME
Bayfront Park Auditorium - Demolition
B-3213-A
CONTRACTOR
Cuyahoga Wrecking Corp.
JOB SCOPE
Demolition and removal of the City's
including removal of some
Bayfront Park
asbestos finishes,
Auditorium,
sidewalks, curbs, and scarifying and
The
removing existing
auditorium is
pavement in certain parking areas.
located at 499 Biscayne Blvd.
REASON
Bayside development.
FOR WORK
SOURCE
Bayfront Auditorium Demolition
OF FUNDS
PROJECT
HISTORY
Bids Received: 4/17/85
Contract Awarded:
preconstructionMeeting: 5/2/85
CONTRACT
TIME
STARTED
5/31/85
CONTRACT
TIME
Not Applicable
ADJUSTED
COMPLETION
DATE
9/24/85 (The City delayed the contractor relative toa
existing pi
decision on whether to remove
not a part of the existing
and pile caps,
project, because they might interfere - with
new piling to be driven a�oorthe ARouse
new parking garage decision was
Company's
piles and caps in
made to leave the existing p
demobilize and
place. The contractor had to
remobilize his work forces and return to the
project and complete the work. The Rouse
delayed in receiving the
Company was not
cleared property or in starting their
construction).
ACTUAL
COMPLETION
DATE
9/24/85
BID AMOUNT
$165,000.00
CONTRACT
FINAL COST
$148,816.64
CURRENT
ITEM FOR
Resolutionto accept completedwork, and authorize