RESOLUTION NO. SG-5597
A RESOLUTION ACCEPTING THE COMPLETED WORK
OF RIC-MAN INTERNATIONAL INC. AT A TOTAL
COST OF $714,360.60 FOR EAST LITTLE HAVANA
HIGHWAY IMPROVEMENT - PHASE I - (BID "F")
IN EAST LITTLE HAVANA HIGHWAY IMPROVEMENT
DISTRICT H-4487; AND AUTHORIZING A FINAL
PAYMENT OF $74,975.27.
WHEREAS, there exists a contract dated October 16, 1984
between the City of Miami, Florida and Ric -Man International,
Inc. for EAST LITTLE HAVANA HIGHWAY IMPROVEMENT PHASE I (BID
"F") ; and
WHEREAS, the work, has been satisfactorily completed and
Ric -Man International, Inc. has furnished the required
documents certifying that all bills for labor and materials
have been paid in full in connection with the aforesaid
contract; and
WHEREAS, after a duly advertised public hearing held on
July 10, 1986, to hear objections by persons interested in or
affected by City Commission acceptance of the completed
construction of EAST LITTLE HAVANA HIGHWAY IMPROVEMENT PHASE I
(BID "F") in EAST LITTLE HIGHWAY IMPROVEMENT DISTRICT H-4487,
no objections were sustained; and
WHEREAS, the City Manager and the Director of the
Department of Public Works recommend that the completed work be
accepted and final payment made to the contractor;
NOW, THEREFORE, BE IT RESOLVED BY THE COMMISSION OF THE
CITY OF MIAMI, FLORIDA:
Section 1. The completed work performed by Ric -Man
International, Inc. for EAST LITTLE HAVANA HIGHWAY IMPROVEMENT
PHASE I (BID "F,') in EAST LITTLE HAVANA HIGHWAY IMPROVEMENT
DISTRICT H-4487 is hereby accepted at a total cost of
$714,360.60.
CITY COMMISSION
MEETING OF
JUL 10 1986
iSOWT,CN No.196-'5974'
Section 2. The proper officials of the City of Miami are
hereby authorized to pay Ric -Man International, Inc. a balance
of $74,975.27 as full and final payment for all work performed
and all materials furnished in connection with EAST LITTLE
HAVANA HIGHWAY IMPROVEMENT - PHASE I (BID "F") in EAST LITTLE
HAVANA HIGHWAY IMPROVEMENT DISTRICT H-4487.
PASSED AND ADOPTED this loth day of JULY , 1986.
ATTES
CLERK
PREPARED AND APPROVED BY:
,,ZGLZ�// I, &jj�
CHIEF DEPUTY CITY ATTORNEY
APPROVEDAU TO FORM AND CORRECTNESS:
CITY ATTORNEY
86-597
i
CITY OF MIAMI, FLORIDA
INTEROFFICE MEMORANDUM
67
TO; Honorable Mayor and Members DATE: JUL 11986 FILE: B-4487F
of the City Commission
SUBJECT: EAST LITTLE HAVANA HIGHWAY
IMP. - PH I - (BID "F")
Resolution for Final
FROM: Cesar H. Odio REFERENCES: Payment
City Manager ENCLOSURES: (For
July Comm ssion8Meeting
It is recommended that a resolution be
adopted accepting the completed work
performed by Ric -Man International, Inc. at
a total cost of $714,360.60 for EAST LITTLE
HAVANA HIGHWAY IMPROVEMENT - PHASE I - (BID
"F") and authorizing a final payment of
$749975.27.
Ric -Man International Inc. has completed the project
consisting of constructing approximately 5300 feet of new
storm drainage, including a 12" - 42" concrete pipe,
manholes, and all necessary appurtenances, including repairs
to an existing 481' storm drainage system. The work is
located between S.W. 6 Avenue east to the Miami River between
S. W. 1st and 5th Streets.
The' original contract amount was $742,137.32, and the
completed cost is $714,360.60. The source of funds is "East
Little Havana Street Improvements" account.
At the Commission meeting of July 31, 1984 Resolution No. 84-
909 passed, directing the City Clerk to publish a Notice of
Public Hearing on EAST LITTLE HAVANA HIGHWAY IMPROVEMENT -
PHASE I (BID "F") at the completion of the project.
It is now in order for the City Commission to accept the
completed work and authorize final payment, after all
conditions are met.
�)/eesolution
:RAR:mh
attached
cc: Alberto Ruder
86-597
FINAL CONSTRUCTION FACT SHEET
JOB NAME
East Little Havana Highway Improvement - Phase I (Bid
"F" - B-4487
CONTRACTOR
Ric -Man International. Inc.
JOB SCOPE
Construct 5300± feet of new drainage including 12"-42"
concrete pipe, manholes, and all necessary
appurtenances, and repairs to an existing 48" storm
drain. The work is located between S.W. 6 Avenue east
to the Miami River between S.W. 1-5 Streets.
REASON
In conjunction with highway rebuilding.
FOR WORK
SOURCE
East Little Havana Street Improvements
OF FUNDS
PROJECT
Bids Received: 6/14/84
HISTORY
Contract Awarded: 7/31/84
Preconstruction Meeting: 10/10/84
CONTRACT
TIME
STARTED 11/30/84
CONTRACT
TIME 150 Working days
SCHEDULED
COMPLETION
DATE 7/3/85
ACTUAL
COMPLETION
DATE 5/13/85
BID AMOUNT $742,492.00
CONTRACT
FINAL COST $714,360.60
CURRENT
ITEM FOR Resolution to accept completed work and authorize
CONSIDERATION final payment to the contractor.
86-59'7.
To. Matty Hirai
City Clerk
CITY OF MIAMI. FLORIDA
INTER -OFFICE MEMORANDUM
DATE: June 1 1 , 1986 FILE B-4487F
SUBJECT. EAST LITTLE HAVANA HIGHWAY
• IMPROVEMENT - PHASE I -
(BID "F")
FROM Request to Publish Notice
REFERENCES for Public Hearing
Do ath r ENCLOSURES:
Director of Public Works
Please make arrangements to publish a Notice of Public
Hearing for objections to the acceptance by the City
Commission of the completed construction of EAST LITTLE
HAVANA HIGHWAY IMPROVEMENT - PHASE I (BID "F") - H-4487 for
the Commission Meeting of July 10, 1986.
Resolution No. 84-909 passed at the Commission Meeting of
July 31, 1984 authorizing the City Clerk to advertise for
public hearing.