A RESOLUTION AUTHORIZING AN INCREASE
IN THE CONTRACT AMOUNT OF $30t000 IN
THE CONTRACT BETWEEN THE CITY OF
MIAMI, FLORIDA AND MET CONSTRUCTION,
INC. , DATED MAY 16, 1986 FOR ORANGE
BOWL - JOIST REPLACEMENT - 1986,
SAID FUNDS TO BE PROVIDED FROM
"ORANGE BOWL STADIUM GENERAL
OPERATING BUDGET"; FURTHER RATIFYING
THE CITY MANAGER'S WRITTEN FINDING
THAT THE HEREIN INCREASE RESULTED
FROM EMERGENCY CIRCUMSTANCES BY AN
AFFIRMATIVE VOTE OF TWO-THIRDS OF
THE MEMBERS OF THE CITY COMMISSION,
AND ADOPTING THE FINDINGS AND
CONCLUSIONS SET FORTH IN THE
PREAMBLE OF THIS RESOLUTION
WHEREAS, there exists a contract dated May 16, 1986, between
the City of Miami, Florida and MET Construction, Inc., for the r
construction of Orange Bowl - Joist Replacement - 1986; and
WHEREAS, an increase in contract of $30,000 is required to
cover the cost of additional structural repairs that had to be
made prior to the use of the stadium for the first Dolphin
Exhibition Game on August 23, 1986; and
WHEREAS, the City Manager has made a written finding that a
valid emergency existed for the work to be done; and
WHEREAS, the Directors of the Departments of Public Works
and Parks and Recreation recommend the increase in contract to
cover the additional costs, and
WHEREAS, funds to cover the increase are available from
money already allocated to the project; and
WHEREAS, MET Construction, Inc., has completed all of the
work covered by the original contract amount and has only that
work covered by the aforementioned increase in contract to
complete; and
%010
�Jyli_ •
SEP 11 1966
"`° 723
WHEREAS, the Director of Public Works recommends that the
retainage on the project be reduced from 10% to 1%;
NOW, THEREFORE, BE IT RESOLVED BY THE COMMISSION OF THE CITY
OF MIAMI, FLORIDA:
Section I. After a properly advertised public hearing, the
finding of the City Manager set forth in the preamble to this
resolution is hereby ratified by an affirmative vote of two—
thirds of the City Commission, and adopted as if fully set forth
in this section.
Section 2. The contract between the City of Miami, Florida
and MET Construction, Inc. for the construction of Orange Bowl —
Joist Replacement — 1986 dated May 16, 1986 is hereby increased
by $30,0009 with funds for the increase to be provided from
monies already allocated to the project.
To. Honorable Mayor and °ATs'SEP 3 1906 T -29O?
Members of the City Commission "�°
ORANGE BOWL --� JOIST
sus�ccn REPLACEMENT
Resolution for
Increase in Contract
FROM: R[F[R6Ncts: and Reduced Retainage
Cesar H. Odio Resolution (For
City Manager ENCLOSURES: Commission - Meeting
of September 11, 1986)
It is recommended that a resolution be adopted
authorizing an increase in contract amount of
$30,000 and reducing the retainage from 10% to
1% in the contract between the City of Miami,
Florida and MET Construction, Inc. for the
construction of Orange Bowl - Joist
Replacement - 1986; said funds to be provided
from "Orange Bowl Stadium General Operating
Budget"; further ratifying the City Manager's
written finding that the herein increase
resulted from emergency circumstances by an
affirmative vote of two-thirds of the members
of the City Commission and adopting the
finding and conclusions set forth in the
preamble of this resolution.
During the construction of the project more deteriorated deck
slabs were encountered than anticipated and most of the $50,000
cash allowance for the project was used to replace the
deteriorated slabs. During the late stages of the construction,
Joist seats at the expansion joint between the old original steel
standard deck and the concrete additions at all four quadrants of
the stadium were found to be badly deteriorated and in need of
immediate replacement and/or repair. The Public Works Director
directed the contractor to proceed with the work in order not to
have a dangerous situation exist for the first Dolphin Exhibition
Game scheduled for August 16th.
The Director of the Department of Parks and Recreation will
request at the September 11, 1986 Commission Meeting an increase
in appropriation to the Orange Bowl Stadium General Operating
Budget to cover the increase in contract.
DWC:LEL:vh
Resolution Attached
cc: Alberto Ruder
SUBJECT, ORANGE BOWL - JOIST
REPLACEMENT - 1986
Emergency Need for
Cesar H. Odio Increase in
FROM: City Manager REFERENCES: Contract Amount
(For Commission
ENCLOSURES: Meeting 9--11-86)
Based on information supplied to me by the Director of the
Department of Public Works and the Director of Parks and
Recreation I have found that there exists an emergency need for
an increase in contract amount of $309000 in the contract between
the City of Miami and MET Construction, Inc. for the construction
of Orange Bowl - Joist Replacement - 1986.
The reasons for the emergency need are as follows:
* More deteriorated deck slab than anticipated had to be
replaced in connection with the replacement of
deteriorated joist.
* Several deteriorated structural members were uncovered
during the construction that required correction before
the stadium was used for the first Dolphin Exhibition
Matty HiraiR 1 1986 B-2907
TO. City Clerk DATE: FILE:
Authorization to
su.JECT: Advertise for Public
Hearing - Increase
in Contract Amount
Cesar H. Odio for Orange Bowl -
FROM: City Manager REFERENCES: Joist Replacement
1986
ENCLOSURES:
Tcvt for Aduertjsement _,..
This is your authorization to advertise for a Public Hearing to
be held atil:30 R.M. on September 119 1986, to hear objections to
an increase in contract amount for Orange Bowl - Joist
Replacement - 1986. Suggested text for the advertisement is
attached.
DWC:LEL:vh
CITY OF MIAMI, FLORIDA
NOTICE OF PUBLIC HEARING
A public hearing will be held by the Commission of the City
of Miami, Florida on Thursday, September 11, 1986, at 1.1:30 A.M.
in the City Commission Chambers at City Hall, 3500 Pan American
Drive, Miami, Florida, for the purpose of considering the
ratification by the City Commission of the waiver of the
requirement of obtaining sealed competitive bids for increases in
the contract cost for the following designated public works or
improvements:
ORANGE BOWL e JOIST REPLACEMENT - 1986
An increase of $30,000 in the contract with
MET Construction, Inc., to cover the cost
^-P +Ho oAAifinnsal atruetural renair work.