RESOLUTION NO.
A RESOLUTION RATIFYING THE ACTIONS OF THE
CITY MANAGER WHICH RESCINDED A CONTRACT
BETWEEN THE CITY OF MIAMI AND AL MARTIN ;
INDUSTRIES, INC., AND EXECUTED A CONTRACT
BETWEEN THE CITY OF MIAMI AND MET
CONSTRUCTION, INC. FOR THE ORANGE BOWL '
RECEPTION ROOM; RESCINDING RESOLUTION NO.
86-510, ADOPTED JUNE 26,1986, WHICH
AWARDED A CONTRACT TO AL MARTIN
INDUSTRIES, INC.; AND AWARDING A CONTRACT
TO MET CONSTRUCTION, INC., FOR THE ORANGE
BOWL RECEPTION ROOM.
WHEREAS, sealed bids were received June 23, 1986, for
ORANGE BOWL RECEPTION ROOM; and
WHEREAS, after determination of the low bidder, a contract
was awarded to Al Martin Industries, Inc., in the amount of
$397,000.00 for construction of said project, by Resolution No.
86-510, dated June 26, 1986; and
WHEREAS, subsequent to the award of a contract, Al Martin
Industries, Inc. has indicated its inability to supply the
insurance coverage and performance bond necessary to
successfully execute the contract documents in compliance with '
City requirements; and
WHEREAS, Al Martin Industries, Inc. has formally requested
that the City release said firm of any and all obligations to
�4
execute a contract for the project in question; and
WHEREAS, the City of Miami has a commitment with the Miami
Hurricanes to provide the Reception Room facilities at the
Orange Bowl Stadium for no later than the starting game of their
regular season on September 13, 1986; and
WHEREAS, MET Construction, Inc., the second lowest bidder,
is already on the site working on another Orange Bowl project
and has agreed to undertake construction;
NOW, THEREFORE, BE IT RESOLVED BY THE COMMISSION OF THE
CITY OF MIAMI, FLORIDA:
Section 1. Resolution 86-510 adopted June 26, 1986, which
authorized the City Manager to execute a contract with Al Martin
Industries, Inc., in the proposed amount of $397,000.00 for
ORANGE BOWL RECEPTION ROOM, is hereby rescinded.
Section 2. The June 26, 1986, bid of MET Construction,
Inc., in the proposed amount of $439,000.00, for the project
entitled ORANGE BOWL RECEPTION ROOM, for the base bid of the
proposal, based on lump sum prices, is hereby accepted at the
price stated therein.
Section 3. The amount of $439,000. 00 is hereby allocated
from T.D.C. Resort Tax Revenues to cover the cost of said
contract.
Section 4. The actions of the City Manager which rescinded
the contract with Al Martin Industries, Inc., and executed a
contract with MET Construction, Inc., for the ORANGE BOWL
RECEPTION ROOM, are hereby ratified.
PASSED AND ADOPTED this lith day Of SEP
1986.
5;VEZ
M A Y-0
ATT V CT -
MATTY' HIRAI-, CITY CLEffK_
PREPARED AND APPROVED BY:
ROBERT F. CLKRK
CHIEF DEPUTY CITY ATTORNEY
APPROVE
ulw&"A"iOwww� CITY ATTORNEY
FORM AND CORRECTNESS:
t
CITY or MIAEMI, monIVA
INTMOF ICP MKMOINIAP+IPUM
TO: Honorable Mayor and Members
of the City Commission
F,oM:Cesar H. Odi o
City Manager �1
®ATE: S P 3 19FA MLM:
SUBJECT: Orange Bowl Reception Room
Resolution Rescinding
Contract
REFERENCES: (For Commission Meeting
ENCLOSURES:of September 11, 1986)
It is recommended that a resolution be
adopted ratifying the actions of the City
Manager to rescind the contract awarded to Al
Martin Industries, Inc., for the project
named ORANGE BOWL RECEPTION ROOM, and to
award a contract to M.E.T. Construction,
Inc., the second lowest bidder.
Bids were received June 23, 1986 for ORANGE BOWL RECEPTION ROOM. As
reflected in the tabulation of bids, the $397,000.00 bid of Al
Martin Industries, Inc., was the lowest responsible bid for the
total bid of the proposal, and a contract was awarded to said firm
on June 26, 1986.
New Florida statutes regarding insurance coverage and premiums have
made it extremely difficult for some contractors to obtain the
necessary insurance, as required to adequately protect the City's
interests. After several meetings and correspondence to resolve
problems with personnel from various City departments directly
involved in the processing of the contract , the contractor notified I
the Department of Public Works that his firm cannot provide neither
the necessary coverage for this project nor a performance bond. The
contractor requested to be released from any contract obligation.
The project in question is of an emergency nature; both the Miami
Dolphins and the Miami Hurricanes were promised the use of this
facility for the start of their regular seasons. The Dolphins have
already started their exhibition games; the Hurricanes need the
facility for September 13, 1986. In an effort to avoid further
Honorable Mayor and Members
of the City Commission
delays, and to have the room ready on time for the Hurricanes game,
a contract was awarded and executed with the second low bidder,
M.E.T. Construction, Inc., pending City Commission approval. This
contractor was already oc site working
izationanother
City
project
was
at
the Orange Bowl stadium; any
eliminated.
The attached resolution ratifies the actions of the City Manager
which rescinded RANGEtheBOWLard of a RECEPTION oROOM.t
to Al and awarded Martin Industries,
s contractto
Inc., for for 0
M.E.T. Construction, Inc., for the same project.
^y.
OWC:EMP:emp
a
,. A4, ,.... PH P., _._.. USTair I64n ry4, ... ®6i i' onA1 6;, T'! i\ Uf'?RT9'l S
GENERAL CONTRACTORS k. " �; 14006 N.W. 19th Avenue
Miami - Miami. Fior14A 33054
CO - CO 313" _ (305) t -t24-8 or
State License Insure! ° 6N-0692
. August 5, 198
6
City of Miami
l
Public Works Department
275 N.W. tad SL• reet
Miami, ^ loriia 33128
Dear Mr. Long:
Due to unforeseen circumstances resulting from internal
complexities, an administrative edict issued by the Board of
Directors, at the request of the Stockholders, was announced
by the Chairman of the Board Monday, August 44, 1986.
"In lieu of a rising situation within the
administration, the corporate officers, with much regret,
choose to forfeit/relinquish all rights and duties
pertaining to the City of Miami project orange Bowl
Reception Room,' said the Chairman of the Board for Al
Martin Industries, Inc.
There are several ramifications involved, which left.