HomeMy WebLinkAboutR-86-0669J'-86-752
RESOLUTION NO.
A RESOLUTION ACCEPTING THE COMPLETED WORK
OF MIRI CONSTRUCTION, INC. AT A TOTAL COST
OF $107,877.12 FOR SILVER BLUFF STORM
SEWER PROJECT - BID "C"; AND AUTHORIZING A
FINAL PAYMENT OF $100380.46.
WHEREAS, there exists a contract dated October 1, 1985
between the City of Miami and Miri Construction, Inc.; and
WHEREAS, the work has been satisfactorily completed by
Miri Construction, Inc. and they have furnished the required
k
documents certifying that all bills for labor and materials.
'^s
have been paid in full in connection with the aforesaid
contract; and
U
WHEREAS, the City Manager and the Department of Public
h
Works recommend that the completed work be accepted and final
payment made to the contractor;
NOW, THEREFORE, BE IT RESOLVED BY THE COMMISSION OF THE.
CITY OF MIAMI, FLORIDA:
Section 1. The completed work performed by Miri
Construction, Inc. for SILVER BLUFF STORM SEWER PROJECT - BID
}
"C" at a total cost of $107,877.12 is hereby approved.
Section 2. The proper officials of the City of Miami are
hereby authorized to pay $10,380.46 to Miri Construction, Inc.
as full and final payment for all work performed and all
materials furnished in connection with SILVER BLUFF STORM SEWER
PROJECT - BID "C".
CUT
3145C MG IN
SEP
PASSED AND ADOPTED this 11 day of SEPTEMmR 1986.
CITY OF MIdAMI, FW1110fA
INTIER-OFFICE MEMOnPeNOUM
TO; Honorable Mayor and Members °"TR: SEP 3 1986 B-5512C
of the City Commission
FROM:
Cesar N. Odio WM
SUBJECT: SILVER BLUFF STORM SEWER
REFERENCES:
PROJECT (BID "C")
Resolution for Final Payment
City Manager ENCLOSURES: (For Commission Meeting
of September 11, 1986)
It is recommended that a resolution be
adopted accepting the completed work and
authorizing a final payment of $10,380.46 to
Miri Construction, Inc. for SILVER BLUFF
STORM SEWER PROJECT - BID "C"
Miri Construction, Inc. has completed the Silver Bluff Storm
Sewer Project - Bid "C". The work consisted of constructing
370 feet of three-foot wide covered ditch, 820 feet of french
drain, and six manholes, together with all necessary
appurtenances in an area bounded by S.W. 23rd Terrace and
26th Street between S.W. 22nd and 27th Avenues. The work was
completed on time.
It is now in. order for the City Commission to accept the
completed work and authorize final payment, after all
conditions are met.;
DWC: mh
F
Res ution attached
x
cc: Alberto Ruder
FINAL CONSTRUCTION F4CT SNI[T
.�.....� �.—� .,,,......q.. ..ems
OB NANB Silver Bluff Storm Sever Project (Did "C") • 0-SS12
CONTRACTOR Miri Construction, Inc.
JOB SCOPE Construct 3709 of 3" wide covered ditch 8201 of French
drain and 6 manholes together with all necessary
appurtenances in area bounded by S.N. 23 Terrace to S.Y.
25 Street between S.N. 22-27 Avenues.
REASON Eliminate drainage problems.
FOR WORK
SOURCE Silver Bluff Storm Sewers
OF.. F Fes=
PROJECT Bids Received: 7/16/85
HIS Contract Awarded: T/18/85
Preconstruction Meeting: 4/MV85
CONTRACT
TIME
STARTED 3/3/86
CONTRACT
TIME 50 Working days plus i days delay from rain.
SCHEDULED
COMPLETION
DATE 5/ 15/86
ACTUAL
COMPLETION
DATE 5/9/86
BID AMOUNT $112,531.75
CONTRACT
FINAL COST $107,877.12
CURRENT
ITEM FOR Resolution to accept completed rant and authwile
CONSIDERATION final payment to the contractor.