HomeMy WebLinkAboutR-87-00311 ' .1-87-68 j 1/5/87 RESOLUTION NO. R 7 - 3 1 ' 1! A RESOLUTION RATIFYING BY A 4/5THS AFFIRMATIVE VOTE OF THE CITY COMMISSION THE ACTION OF THE CITY MANAGER IN HIS WRITTEN FINDING THAT A VALID EMERGENCY NEED EXISTS FOR THE CONSTRUCTION OF THE ORANGE BOWL STADIUM ADDITIONAL PRESS BOX FACILITIES PROJECT AND IN HIS EXECUTING THE ATTACHED AGREEMENT WITH KUNDE, SPRECHEP., YASKIN AND ASSOCIATES, AN ENGINEERING AND ARCHITECTURAL CONSULTING FIRM, TO DEVELOP PLANS AND SPECIFICATIONS AND TO OVERSEE THE CONSTRUCTION OF THE PROPOSED ORANGE BOWL STADIUM ADDITIONAL PRESS BOX FACILTIES PROJECT, WITH FUNDS THEREFOR IN AN AMOUNT NOT TO EXCEED $80,000 ALLOCATED FROM CAPITAL IMPROVEMENT FUNDS. WHEREAS, by Resolution 84-1376, Kunde, Sprecher, Yaskin and Associates, an engineering and architectural consulting firm, where engaged to study the feasibility of constructing a new V.I.P. seating area directly below the fourth level of the Orange Bowl Stadium Press Box; and WHEREAS, said Resolution further authorized said consulting firm to prepare preliminary drawings for a new V.I.P. seating area which were shown to the Commission at the July 25, 1985 Commission meeting; and WHEREAS, completion of the Additional Press Box Facilities needs to be completed before the University of Miami's 1987 season opening football game; and WHEREAS, an agreement was executed with said firm for the preparation of complete plans and specifications; NOW, THEREFORE, BE IT RESOLVED BY THE COMMISSION OF THE CITY OF MIAMI, FLORIDA: Section 1. Ratification is hereby made by a 4/5ths affirmative vote of the City Commission of the action of the City Manager in his written finding that a valid emergency need exists for the construction of the Orange Bowl Stadium Additional Press Box Facilities project and in his executing the attached agreement with Kunde, Sprecher, Yaskin and Associates, an engineering and architectural consulting firm, to develop plans CITY COMMISSION MEETING OF JAN 8 1981 )Mft.87 ow Ll specifications and to oversee the construction of the proposed Orange Bowl Stadium Additional Press Box Facilities project, with funds therefor in an amount not to exceed $80,000 allocated from Capital Improvement Funds. PASSED AND ADOPTED this 8th day of January , 1987. ATTEST': 1G; T;Y =—UL E R K PREPARED AND APPROVED BY: CHIEF DEPUTE( CITY ATTORNEY APPR ED AS, TO FORM AND CORRECTNESS: CITY ATTORNEY Page 2 of 2 '87-31 C CITY OF MIAMI. FLORIDA INTEROFFICE MEMORANDUM 1 TO Honorable Mayor and Members DATE DEC 311986FILE of the City Commission SUBJECT Resolution Ratifying Kunde �1 Agreement for Orange Bowl Press Box Design FROM Cesar H. Odi o REFERENCES City Manager ENCLOSURES A RECOMMENDATION: It is respectfully recommended that the City Commission adopt the attached resolution which would ratify the action of the City Manager in executing an agreement with Kunde, Sprecher, Yaskin and Associates, an engineering and architectural consulting firm, to develop plans and specifications and to oversee the construction of the proposed Orange Bowl Stadium Additional Press Box Facilities project. BACKGROUND: The Department of Parks, Recreation and Public Facilities has been investigating ways to provide additional V.I.P. seating in the Orange Bowl Stadium. By Resolution 84-1376, the engineering and architectural consulting firm of Kunde, Sprecher, Yaskin & Associates was engaged to determine the feasibility of constructing a new V.I.P. seating area directly below the fourth floor of the Orange Bowl Press Box. Kunde and Associates were also authorized to prepare preliminary drawings for a new V.I.P. seating area if they determined the project to be feasible. These drawings were prepared for presentation at the July 25, 1985 Commission meeting. Since completion of the Additional Press Box Facilities needs to be completed before the University of Miami's 1987 season opening football game, an agreement was entered into with Kunde, Sprecher, Yaskin and Associates to prepare plans and specifications for bidding this project and to .oversee its construction. Attachments: Resolution Agreement 31 C i , .11 o(1 - L ill :i ,� r y .� •_i 1. 'J i � l/; « G� QL� ^_ , 1- ',� v i) , of IiLi l.il, < tr,U1)� _ �)i:.1 :(�. 7 Cis"9tlOti QL i.il_ :'l'�.a, Lore.inafter called Ci'1(' uCI`rcl11d KUllde ..1:3•�ltl 6 Asjociates, inc., a L'lorIda f( E)rO LLt r;:7L•itlOil, ti+'c inafter called the '1PRlriC: AL". R E .: I T rI L ;;liL:zLi:S, ...ile Ci't''t.' LS JQ.:iEGUS of securing prof:;�ssioll��l. actual ac::_,;__es ,c, Lies ign a new enclosed sa.at_fiy urC.CA laic upper: _-%r:jss ue:; at tho Miami Orange Bowl Stadium; and .'i:1:iC:PAL nol�s th..a profcassional quali'icac-icns th,-,-sue ::C r'+ .. ;"S; and :.. aZA;;, the :?t21*4Cii>AL is capr,,ble and desirous o:: perforiaina arc] c-ti:2r ..flied tasiSs as right be desired by CI•:i. THEi261^'ORE, till C1''Y 3rid ;-.ae t FZINCIPAL tur I:a"a, ;.bra ioriS hei.(?iild 17 tor si;c for. th i.ijree &nj cov(--,n.3i1,:, 0IIv of-t1er. as foi lows : SEC`1'ION I rP. rL A. do P:.1N IPLiL and l C.o Cl`l'Y a::e fully i.warL of t!le SCHEDULE OF WORK requirements as defined under :section Vi. and s,iall t!iercforc proceed with all diligent;_ to ci r_i colt tc,: [;';F:Fi to m::et sack rc:-quir iner,t::. The sh:111 prcc3z:ci vital all applical;le disp4tcil in .soL'.n.a, -.:onoiaicz.l, ofi:ci.ent and professional manner, ..ciudia-j prtp":i:atia,i of i`adding documents for construcr_iori :::3 ry, and shall comply with the prop _lions of : �_ 1 icabia 1 c.c3eral, St.atk� and Local 3. i'ric r?:<lijC:ll'til 3,1 ,: 1 �3�L"i%iLiA Cllt' L'G�e':;SlOn31 s,?rvic,2.; as .: �r_in�lzt :r set ::Sriit ,;!rid lli geld ral acc•-)rdance with the C1'1"�', E ThQ C I TY a Lj rt�es to r-);.; y any i? k L, accept as payment in f u i I Jr ai L -c L: ;? s c technical services re-nde-reLl o 11 1 i Ill - PROFESS IONLL SERVICi-'S rate of 2.8 times Direct in this Agrooment. DE .r NrT!ONS: A. CITY - is hereby dof4n�2d 1:.; r-'--je B. CITY MANAGER - is hereby as tLi-te the CITY. C. PRINCIPAL - is hereby defiria-a as & Associates, Inc . �765 S.w. 18�1-11 Florida 33157. D. PROJECT - is hereby denied as :,,� enclosed seating area under tll� CXiS:zii1(:1 kip" —I: b,- for the Miami Orange Dow! Stadium -Iocl-ILej 3rd Street, Miami, 17jorida. E. PROJEC' MANAGER - is Aerouy as the PROJECT for the CI111Y. F. PROJECT INSPECTOR - is of the PROJECT designai--(-xJ by G. WURK - is hereby ucafjnedl ,s -t-Ij f technical services to Q.t: PRINCIPAL for the PROJECT, cis PROFESSIONAL SERVICES Lereof. H. CONSTRUCTION COST - is !-.ereby d`finecj as the t0k.-Ii construction contract cost of t11,2* but it shall not inclUQ0 ally survcy, i0g,11, administra Lion or, siaiiiic !;crv1i(.-,:-r, It-j(j 1-n'l turn.Lsh,--,d by the (-, I,,e y of .40y C 0 C -11 C, L f urni tur--!. U11-1 I.Li.IC110, 1* L:": I I i 3 11 _- rl'j-' r (-Nu i Pnh!il t Vureli,i:od ljv tj,L� c.-ry. 2 c P E E 1004 "A I FEL - is hereby defined u", th,� C - , . - . , j I agrees to pay and the, i y.rie a t in full fo a I i i i services rendered tpursuant- 1:,:) t. h e WORK as f U r til 0 r d PRUFESSIONAri SERVICES, ho,:euf. J. OIRECT PERSOMNEL EX27-"'14L;i]'S :straight -time portion of wagD:3 F(2je r a 1 1 11C. Ome Ta x ---ho U) 1, i personnel, plus payroll burden %-.hi -:tj i-:, lic j- t_ twenty three percent (2361 , (inc:,.ucijrjc; to Principals, tirck-A! tectE, L n r; L, z-- i: ij.� k'...;3":: Architects, interior Designer, Se -cur i co z L: Planners, Designers, Dr a f t 4 ny Staff.$ S r, c _--, f: L i z Zj Writers and Technicians, (.tc.) , engaged di:�ci:!%, on PROJECT. T h a DIRECT 1.1 ER S 0 !�.' 1,1 U X P E E;'- c: I a r a 0- -A C, the PROJECT for any pka:rsont;el , and/or the PRINCIPAL Is designated special ists exceed forty and ll-o,1103 Payroll burden whliuii i.'-; ;,UL percent (23',-). :3 EC **." I. () 11v I IL PROFESSIONAL SERVICES: A. Thu PRINCIPAL and its 3jpecicilis.:.; in close coordination with A I J. f L City Of Miami Department of RU'-'ZU(sLiCja, r-acilities as well as tii_ Grua: t,11,a 11c F, of Planning, and Fire Rescue zn,.111.3 P (' C" C. 1 r I S Other City Departments shall c-als,) be invc!;ej .r -.;n ZzLi- needed basis. $. The ill close coorclirlar perform the LC I I Oil; Ll(j f o n it services COMpr is ing 1j, K - 3 - u:�SI1"1e for a�i the prof`saiu;i�31 and tcchnicai 3spucr.s thereof: i. Proyran Development and Planning Phase: :During the nrogr.an! Dewclopment and Planniny Prase, upon receipt 0f written authorization frcm the PilOJECT AANAGER, the PRINC12AL shah.: a. Mae with thr? CITY staff IIv01Je.d with the op,3ratiun of the h1i l.►i .).:ancje Bo;il Stadium, an-3 i.3.2nti ry tha 3hcL c and lung tern pruyramunatic need;; aad (j-)a1s, f:utic tionaI rLquir.c:taer,ts, an%. ironc.enta1 co::sidera :ions and th ini cic l cos;: parameter._ fcr vari�-)us fur, -:ions. b. Prograin All a1ysis outlininL1 tho functional relationships within the :;radium and on the site 11 the crnte:xt of the proposed pro-ject i;npact upon the stadium operation. C. Prepare a Program Utilization Pian showing the relative sizes and relationships of the various uses, with pr•==liminary cost estimates, broken down into individual cost estimates for each item or group of items which form a part of the d. The Program Devalopment and Planning Phase shall be completed when the CITY approves and accepts the Program Development- and Planning Documents. 2. Design Development Phase: During the Design Development Phase, upon receipt of written authorization from the PROJECT !MANAGER, the Plilt4::113AL s isi1: PL_pare Design Development Documents consisting of plan, o_�ctions, elevations, interior iayouts ane; other dI:awinys, as we 11 as outline ' dpec i i _cat ions, a11 i:, order to f ix and - 4 - -lil r r �: thu n -iltire a tila Si,7,0 and C1 CtQIr CL 1.:wjzC,r in it-.*, -to Location, kinds Llities, `' jtl:uLI ctUr(2s, L_ mechani(;ai ant? D!L-c t f ical systems, and site ii, t.: n t C). Ud i planLiny, p i: v 4. n Lj , site amenities, i__ re(luirc-d- Co,;"- L broken do, -.In into Major goriezi and e!WJECT elemolits. C. Lpon revi,2w all(] ai-ceratiO,71 as may be requiri-d, .3 u baiJ z tilt: CITY Desiyn Developmeriz-Decum-c S s ii i z: (-,d Iler o J Ll '19 with cl time 3cild ull for Construction dnd a final Cost Estimate. T, I 1 1, 4 C i 0 A L "11 a y be r_--qu i red to -1 -),L c :; e I I t i t o r I S :0 the M i aro i City is Z i Oil nq Board anal/or Planning Ativ �. so ry 30;1 --.-d cite Do -sign Development Documents, including the Construction Cost estimate and the Pro j ec t Design Development Plan. T.'l ..? PRINCIPAL shall revise the Design. Development Documents and other materials as 61ructed by the CITY Commission or A, e aZorementioned Boards. The Design Dr-vAopment Phase snall bo ccrtipluted wL-.eLi the CITY aL)proves i..-nd accepts the Design Development Dccurrt:nts. 3. '_.,.)nstru,_i:ion Documents Phase: P-Lif in(j U10 Cons"-* Y:ict ion Documents Phase, upon Ipt of wrizter iuthorizar-ion from the L IOJEC,: *:ANAGiR, the PRINCIPAL shall, based on the opproved 11. P r t: p a r o. all _­.-.-ustiuction conLiLact. ,pads L: 11 .1 fic-at ions as wc.-Il as DLhe- contr.�A and oiuJiny JOCLI.-IlallLj i 11C 1 Lid i 171(j L11;2 Pro«osal Zlld /.look 3 p e c i. j Provisions, and spLcifically including - 5 - ( en—..r,A Cursa:i "t io s (as pro'vid(L l by ~hu CITY) , f c) _ Pi:U,l[::CT. Tl'! •so durum n i:.; Stl�l i l !DZ, in cot) with all applicable s ciLC' ani C-II laws ana codes, and sha11 include such i t0-r"S a :he working 3rawing:i and i ric•ltlons, auequatzAy settinq forth i[I i3t'•ca:.i, dL,cr•iN.:'_ons of the construction tt7 be lon alid aloo the riater i.alS, w0-i:man:illlp l inistles an6 (3quipinent re(luirkid for a 1 'Z:L1 0Ccura.l, landscaor r::hi tecc•.ir_ii, and uginoe.rin(j wG1:,:, service-connecte;: egaipment, f:ixtu):c;? .:nd equ-iomr:nt :?1:tached c.o th,- -1cil.lt. ala::trically, .liuChanicc' 11; or str':cturaily) site development, and t-!I r, Z;a1 provisions of the C�r_struction Con::I:a Ct Documents. b. Prepare Interior Layout I=lana indicac ng the location of fixtures and furnishings to be bi(3 .na purchased set)arately from the PROJECT construction contract. These plans sho.ild be actor„pani;=d by a Cost Estimate. •1'rc: construction contract plans and specifications, and any other written rQport or wr i t t-_n 3o-current shall conform with codes, L`yuiatiOtis, etc., governing the PROJECT. (i. "Ohe PR1hCIPAL sh:ll continue to advise the CITY of .iny adjustmcnts to previous Cost Eutimate :rhic*a may be indicated by changes in scope, 7v.3i jn, requir rrents, market conditions or o;:tic!ry ise. r'urnisil the CITY with Filial Cost Estimates based aeon the completed working Drawinys, 3pcciiicatiunr. z.alld Diddirig Do-_ument:.s, broken Ws Ui)',i:l !ni.,) iil,JU� i:�C�.tJU:!�:; :i1,J ►�:.t 1t:ri:;S. 1iie t�i;i���i�AL's t�c)t Esc�_n.)t,s �►��1?. b�_ �.:cnstru�ci �c i)inir)n cf a sl;o►;:,iI)iu xport ar.6 the CI:' .511Eli r(AY on :t: as ,) r`;1.3on0 apE)roxi,,.ation of Lids) uo Le rec.. '.ved . L. Sic the t 11:u Conscruction Contract 21an:, an(; i f iCLi i ion 1 Leal: tll:.` Sea I of a F .lor idi- �iuiaCt iL:y pro.Fesoional carchitc:ct, onginee:: i)L '_angst -ape architect as apprcpriata aced tn_,t: tilt' namas of the professionals responsible for major oortions of each s parate specialty cE the WORK appear on the ConstrLiction Contract PlanS, 5oecificacions and Bid Documents. ��. 3ec:ause of the CITY'S concern for energy conservation, i,: shall :.)e fully andersrood that the PRINCIPAL shall pay particular arcention -co the desi ns of all energy systems required for tine Pi20J ,-'T with emphasis towards conserving an--Igy. Particular attcriticn shall be focuseu On the different uses of the PP.OJS(-'T all: 'Che difi..ient dein.uod.,, for air conditioni,l3 and liyi;ting, etc., wichin structures. h. S.ibm;.t ehe (--.,,npiate Construction Contract Pian.3, Sp,::cificati.ons and Bid Documents -,) the I'iY for .4-etaiL-d ruview and approval. i . Conuucc Chit: n4cessary Dry -Run cnec►;_ of dire construction cuntract puns and specifications it, connection wi zil securing their construction ro1_.c_.. approvals so that the necessary c:cnstruction por:nit.s may be obtained ircm all nicanLaI du -41orities having jurisdiction ;v r the P1..UJ2'-'T, after the CITY has approved - 7 - Y +') c:; it r:ICr lOn l;OntY,l t [ 1 ?17;i anl� i I:y said <?1)C1711CC LDpr(_'F.)L C of the Dr•,, -Run PrOct2n ,. i nG C:1'lY dots nGL' Yel : ;V3 Cl:e Pi:iP';CIPAL Oz r:ny r�spo.l:-iuilitit�s, i)�.rcicul.rlj. -1rl:;L . `ll l�i!. _ i1C cowi11a::',1' Scat` G CGn:i` ;: U�:lUn ::UnC_..iCt 1 ins a!,,J shz,_.t C 1C`ttions I�•� Ot:';�?i r_'1�t''•.3 iiiL tS )L tI1 c0:1:3t:1: oi1 C, I: u'.0 1nC:1u ing Lho 3 u2.1 r� urouuc' blc fo _":.T: as may he �t'`c i L i. ;] b-2 :1c l: I `i' Y , The Con:itructio:l DOCLlilent Phase shall be cons itler_d coTplec.e on the date that t-ne PRO.3ECT is advertised for i3 ;. Lidding Phase: -During the Bidding Phase, upon. receipt of written authorization from the PROJECT MANAGER, the RINCIUAL srlJll: Prepar` any addenda, with accompanying drawings. or ot;.er material as required, ant subinit 104 o.igin1. of aach Of the P1t0;1E-07 MAN..GLtt Lor c:pprova! a:a? :iu:inission to the Departs(-nt of Public: Yorks woo shall currci3,l copy kor .a"-c.; ::,at of .:�?ntr�act �Jt;c::►iznt� prep,r.:d. o. :,ss'�r,•.hso ,�:zd i.arr:i:;il tl:v"'- FRU•J�C'1' t'ti,'.Ji.CL;.; :�it�: &I to for i)aal ici ty r-;ce p.ar z in the lare-bid conference wi ffzil t`ic I,ITY. d R'asl:!ond to inqu'_ries from Prosp•active Bidders. :.ssist till CITi in the evaluation of bids. Sid:iing Phase anall o'o considered completed or, CITY exocutas a Coi�strut:tion Contract for ti:e .. 8 - 0 6" ;Jays ail':r �• 2ins ruction 1'r? ,I?: I T1je 4(i!]strucl.iun -3ha!1 Col,irre Ice with Lhe (ward 1 i of the Construction Contract. Dur_irg the Constraction Pn��:��., upon receipt of written :rllo.:i2:3Lion om tIIt- vROJECT MA:1IGu tile RINCIPAL sh,::1i: a. s` t,� mectings and male periodic visits to the Site to rt_r;;ai7 famil-iar with the progres a:Ia quality of the work, to determine that the aori; ir3 a_oceeainq in ac(:ordance with the Contract Docux%2nt s and ;urmit observations to tine CI-Z in writing 4✓it:ir; five (5) working lids after each visit. i i; • Work wi th ti,c Pl: UJ,:CT MANAC'a►:d,�'or til,:? dosi,;r;ated rupruscut:ative, the i, OJLC: fro;.1 the D6oartment of hut• lic Works and the Contractor.. C. 1ssi.it tiie- CITY -in cousiar-rin(j and (---valuating any suggosr- Lon:, or propiosala submitted b; tno -onlracL-or for ta,_ CITY's approval. ?. st ti:c: Cl""_n Inii t_rs r`lating to he i inter;-)r.tac.on of Contract Documents. ee C'urn:slh anv additional details or information ✓:'iLr. r :quirt CL At tale job s: to for proper c:xecutioh of the 1 ORK. i :..7Jl:fit '::,e CITY and r,-,aka written recommendations to thlz' '1'1•I oh matt-:.".s pertaining to til'� I.JIIt.'c:.LUL' s �)r�>>u:3Ci1 Changue, i:, materials and aquipmcnt. and (:n r:.1atters reli:ting to extra %✓orE; ordor:; arnl supplemental ayrE:ctr:�rlts. • �.,,1 �, . • ,.. i_t✓ >hop drawiny�.�, 3araples and - 9 - t 1 1: SuDn! A SS;'Drs by tile Contractor design (r(.;-.i 1:o rmi rice, r,.- t. -a i n a ct-.�-py of all duly ti1c. "Y re i. ROViOW tu'::t 'JELL rQ(:'U CI the t-"on-C,:act n t S Cr C' i at, ,CC!, .-I 116 i tooss a i i t� S r s .75 -I-, a y 1; .2 r q u 11 r o d i.V b,.: ti'lt'OSUU bj tl%c Conurac t -.n6 prov id� "Lie CITI- with w:,& 'Cten i:eocrts of all sach '-es-,:s . Re c te i V e S Z!.',l F, i es w'k, I i c h EI r e required to b e r a r 11 i -; hed 1) y .he CoDtractor' r e. (-- o r (I data r ic e i v ed and -i t sourcc. , examine said s a m p 1. e a nozify i:1-,e CITY of approval or re-!*c'1-iun anG J wa-intain custod,,, of approved samples. Assist t*ie CITY in the preparation of bids for fixz,irus . and furnishings and other related equipment for the PROJECT. Upon receipt of tause aids, assist the CITY in their e,,,all uation and ai-i;ike r c--,::-:aP.,nendat ions related to the arrival any' ins ta 1 la -% i oil of said fixtures ard turai s1iings. 1. Aft,-r SLbStc111Li,1 I ccnp.Letion of tile pizoiLCT, inak,a a list of itc-ma for correction bell -ore final int-yec t i oi, and check each i tr�m as it is curt ect'.-(A! . Upon rL-qut-.!st L)y the P110JECT 14ANAGER attend and r-aj)ort co the 'CITY on all required confeconces ii,21d zii Liio job --i'L-e. n. The . PiZINCIPAL :mall car..y out tile EzspollsibilitiQs under the terms of t1lis Ag t: o (-.Li c- il t hu,.ov-*_r, the CITY shall have the I! p0a SeS U V 0 t and use any C CG.nj)1,2Ct3(J PO::t?on Of thu no*il.lCll:3tallillCC t':l .t ' I:L time iG1: G:nj t %:' -,I-, Z. re Pl.UJ7Elk.",i' Gr nUcll portions lluj liJi hu.,o- e::plred, but :iliC:l ta;cing session and us; sha11 not bc� deemed as .ice ;)za1nc L1 of any wor'i not cl')iiC)ll"-'.tc.d and It in nc) the Pi2ILi�-1PM, o,= Iny of �;ic r.,sI?onsibi1i t s url,ler the t e r w s of ti-Ii:� Aytn-; . o. ,331:St 61e CITY in matters relatiny to the Co,itr.actor's schadule arld apprcval of roquests for pro<;ress payment. p. : u:: my the course of the WORK, ensure that all guarantees, certificates, operation and x..aini_cnance manuais, keying schedules, spare carts �.nu ot.-ier items that ha•!'. been spc:CifieJ in the Contract Documents, have been sui:mit;:ed and reviewed. Deliver all such items to the CI'ii prior to the date of beneficial. occupancy. _ FurrliLl Lo the CIT'i within 60 d<,yz after compl;_tion of the Construction Phase of 41 i]e PROJECT, the original reproducible: drawings of t,10 COnstrUCtio1l C ontraet O1<lns, revised to inClud•i all chanjes or modifications to the Ui j i I] made during the Construction 'Phase as r%2c:o,_.ic:(l by '%hc. Gclic- al Contractor ail the record -3eL Oi: arawings. At the c:oanpletion of construction of the �,'•.UJL:C'i, t:�e PRINCIPAL, shall deliver to the CITY .JrtttE:l1 C:(artiti(--atlofl tilat to tho best Of the PAL Is tho PROD ECT has been _unstrLICLI-4d ail aC :.r_'d, n c e w to CITY approved coil SCrUl:tioil plan Is _I,1d :iJC:C:111Cc. tlono. and 0ITY - _1 4 06 E-2 I"1 e4it% 1. naso shall be completed cYner. Z:iIZ 0e,ILt:CIP 1 11a3 ua:liver.ed tale a1,:jresaid zartifi�_,atlon, including "racord Drawings", to .:h,2 C IIVY; .ind she C:ic;• Ccrtmission has accepted saki UJL•'CT, but in no cane l ..�.r. the.3Q days after -'aI v(--i Y b;•the PU:.,-'I?AL. DL! nc. the P TNICIPAL shall act Z15 uw;; Yc.)t:asc•ritjtive to the CiTY in al.l iiatte-K!, ,.•�rtca_ninq -co tn'o 'i`na CI'i'Y's review and a;.proval c;i t_he work s•hall E. 1 aee C1:. y t0 0�:er,?11 cmplis i)C:' J1 _h t'10 I r_Cjuiro;iion'_s of t.h R�)j,C:'1' ?nd 4iaenevGr C?rrf rcvC.l Uy t:te C:ITY't or like t° rin is user! in :7ree�:.nt, .:he ohraseozogy shall in no :gay rel_eve the P!�!iCi?AL frc,n rirt'% duti s or. responsibiliti.-s under the ti1.31z o: t;)is Ayreement and frcai using the best _.rof�Ssi0na1 architectural, engineering, landscape ar:ilit•_ctura1 and any other necessary services and i:ra-tices. �. :he PRINCIPAL and its :>pecialist-s shall,' throughout the course o.: this PRO:iECT, particularly in the initial design s auyc, WOZ.c, ilicMy with tha CI`rY and include its ..:put in :.h,.overall do o ign process. 1t:5 Specialists shall be prepciced witia co att(3nd, and part: cipate in, ? 0r y, W:i h the CITY, var. i0us public meetings as '19pta;priat,3 during it'ic. course of the PROJECT. Prior to the PRINCIPAL shall confer with the: PROJECT MANAGER ::nd relat,�J start to review and approve all i:C'jC u:A� :it.s Z)1l :;Cr)l't,"j r0 the pL'})lll These me etin�]a shall 1. ►r.e hlau:ting ku'visiory bcarc,, tae Goniny Board and - 12 - U: e�04 (I 0,Q; TI i ',', ,10 11 LOt lt" a 1.,:. L: C C) p c s )f cite pojcz rc Lrz3 L-.c t i U n .i-r-ae t lig z• N' Z: 1 in the pj.ep��ration of Plans A ,;c)- c i f i a ,L , and all other- other- documents pertaining Co ,-,*e co,�jply with all F o d e r a I , State and local cod s, ordinances a,id r,.q u 1 a t i c, ns partainintj to tale L 111: o u cj In o u t L; il L! c a u r s (? of e c: i c.-L r C lie C I r Y (" f any .-Ad 3 U:; tli(�•ll t L)itviou.3 1 c -s in ary s z 1�cj-1 z L3 u chai jL A. y Spkt Of v.'-Ia ?'7ZOJECT. P11f, t') �)ro,,14UCID a j: zn,- L L:c- zhe obii9ati0". ct Lhzi P-1'NC"- W- -. I' c h ma e cons r-ruc t::a v� i tL 1 .1',, t 111 n t -n thereof approveci '.�v or rt;�viL-, - C 1T Y. Approval by the CITY of t:io P r cj r,:: r..i L and Plan n i n a and oi: U e: 3 A Dc- v e1 o ome n t documents i nc 1 ud e s approval r; f the construction Cost Estimates unles-other-wise advised, submitted tilerewith. -ost for any of the phases are greater uudgatod amount. the CITY may require the 's related to tha t PIL'i 1 NC 1 L LO re.'v iSe the documen.- L;o-zc1i'lu phaso as neces:.;ary ill order to bring the 1 P A L. i� r u %, i :,.! d Cost Es t imci te w i -c 111i n tne CITYs Frc Ct BUCAJvC- The wont undertaken by the PRINCIPAL in purposes of meetincr the re-,j,jjl,,g L,,.:) dcjcumunts for L. - P�Uj,.--ct Budcluz- S.L14111 be considere-3 as part of the V St. rV iC'.?S al: 110 ijCjU ;Jolla 3aSiV P1.0fLISSional to the CITY. be rQZ-ponsible for designing the nevi z,::;. i;-icj ., rr--a :.:i a manner i:ha t iiall support and nce the ut-iliz,4Liozi of Lnu Qcdn,3L- 1;.,)w.L as defined by %-- A. IT Y - 13 - U, E i"N ::E11T..014 1V -'V 1,' 3 A -'D 5P0N" 12A iL i'C .:S � (ui•nij0 t11with she _')i10wln'� r j _10"1 l.t:io,iatiOrl i,:3,ri i sting (.'iTY r,:Ccrds :.i.C. (. I T Y Ile �i': : Gall. �7; GV.1C,� in��:C.n3l'lOn Lt.y�r�lnca iL 3 )_ iY saali furnish a Cei:ti i(.?d Land Ll;u::vey of .:he :site i i ✓ my , as alapl icable, gradc:.s and lines )f streets, al;.eys, i:ava-!rI:nzs c:nd adjoining property; riciiz of way, r, strict' - ions, 0as"iments, utiliL-!es, trees, �►:croa��i:�nents, zoning, deed rests icti ons, boundaries and con _ours of the site; locatior.:;, dimensions and data from existing rocords on file in the Department of :,ualic Works of the: CI`1'Y pertaining to existing Orange i1owl, :)thar improve.nont_s; and information concerning available sarvice utility lines both public and 1. ivate, if re,.,uired. C. I L t h a PRUJE*--'T MAN'AGER and/or the PROJECT :NSPECTOR o-vserves or nas been notified in wr'.L1:1G of any fault- or J0f:: ` in t11e P::U.i::V iL nuncutif c rm ance l/:':�I c.lL Contract Docurients, prompt noticE tllircof shall oe ui,,•=r1 _o the PRINCIPAL. �1. The CITY shall do ali reproduc'"-ion and binding of the :.i(J6ing anc: constLar.t.icn sate of the dra .-wings and specifications, a;'- lean all existing and applicable C!TY aezial photogriphs to the PRINCIPAL. 1, C I T lail ai)pc: nt a PROJECT MANAGER to act as i .30n but- en c:i`1'Y anti PRINCIPAL, and the PRINCIPAL will rOt scarf wore llcr incur any expenses for an't Phase sp;:ciL-al conditions or change orders without authorization from the CIM"s MIANAGER CO (IL sa . Woching contained har_in - 14 - 4 0 �. i�Lll':f�, G.. [1' L'�1sooil:i-ibi1it1 GJ :)_ 1'.i� U L•i1l�Lr l.'l1J /�ai •.�,=.1,i �=11 �. f;ITY shali i.l.1:ili3 1'C:: test —in", iiL:c,,;-,SSal'y 1r �ilC� PROJECT, il":i:li1�];.11'.' CUti? UOtiC1C�:i, tGSC E�i1:.5, (.'..°.1, ctlenli._•31, soil, a:la mill and Y. ;acts; ..:lei ti r_• :`lalc�d :services of a soils ::7:.2i cal Ur C1:.l :'G l3Ul ia(ltS Wt1Gn dce.ned by isle PRIINCIP�'L; al:f1 bile PRINkCIPAL sLiail b:� 1_i :i,2,j upon til_ acc::racy, complet.-moss anc, i G:77 ?L""Gili:C rhero f. �i. 'ihe �-i,fY r-igllt to ieta"_il till: L;ervice..s of a Prof"aajiOnal QL"::ntlt:y Sur'leyor to p),:epare Detail=d Construction CO'3t Ezuimat'.3S b,lsed upon zhc. Des cjn �_V'1�LJ;AI?nt DO(-UITlee11L'S and the Construction Do^,umcnts. , ices, 1llfJi:lii•3t1CCi, Slll'VC--yB and reports rCCjlllraU -hall be furnished atile- C I T Y I s expense anti >+he c R oNCIPAL snail be enci tled to rely upon the accuracy c111d Complateness that: _Cf . I. if the CITY oi.)sf3r'.'Ls or otherviise beccRlVs aware of any fault or de-: t:ct in ci,e YROJGCT for nonconformance :ait-h `he Caiitzaci: Do'.:aatL!nts ivro,iipt, written notico tnar�'Cf G:lal1 be given by cn(: CITY to i:he PRINCIPAL. .1. `il,E� ;.,i i'Y sij ill _urrli.-;il royulre: infor►:iation and shall Jp_(iValS Icna dur.ision, as (::{pedit1Uusly a:-, for rh(_ ora•,rly progress of the PRINCIPAL'S .lad of tau Si.CT1ON V .: •t'' .ai'i l:iii r!a :i}sIZ'J_I.LJi .)r fro .::3sir;n11 uad cuch;,ic�l services for the rroyram d Plano ng, oesign Development., 3idding, •__La Doc;:.n,--nc and Construction Phases of the PROJECT, as _il SLCT1ON' 111, the CITY agrees co pay, and tiro 15 - 4 0 L I I - t cot L it i s 3 r -j cu.,; a (2 L �S 2 . 8 --L) i 1:-C L: PE.- i(.ime I Ex us 'A3 P. i 13 J 5 IF, E X P il p III] T,'Cn,l c ?:v 1, Cc.-, 4 13 i: t i orl Sna I I o,` CCIAP,lI--I3U as fol i O-V,S I Cil ki,jch 4 0 11 0 L: jr, c:, n t r o )o r y i .he 3 i: I-.l services 1 L :,I tL. 0 4: t i!r,0.3 V, L) i z_- L ve 1 0 3 r o iJul.I s 4'. 1 a I: r 1; tl'_ V L, r a e 4 0 0 0 Pr ion a I ?rcll i C,--lct .?24 00 Pi:ofessional -Enjitieer $24.00 ucsiCntrS $16.50 e C h n i an $14.00 Siz:nioi: Oraf tcr $12.50 r a A-: r- z, r $10.CIU :3,� z) ;.)o c u.ii jo ed foi certain work z: (:: 1,I t ej C Z L, 1: E .3 11C t 0 v I.? 1: 0 U, b.. 1: C? ka.12 rill" a rjr; n e e-, j. ng t: -v i c r-, s -J,-' 1, i Lor-aL; ,i e 1., J. ci us a tit hLIr i. -"ed y t .or of t 10 k:i , I Z' Q C r C, L i PuDl ic Fac i ties DepzAA: tinent shall Lot (.-;xcocd an,J 1,1:.:y include: :,';c j? -�a I I z Li L Or ITL k? Ilt reproduciton, e a t,-, I of ut I t i n and purchase of s t e ---- ia I 'lc-Ct;!sslr7 'or Lhe L-ficient performancC of r 0 v 1 (1, -:!jj t: such I;,.; t r umen t s r e.nzj i n the tho CITY upon work Completion. T h e. c. e on a LjjrC!ct cost basis - 16 - IM% ?00% tra%7oi, i): r, cluir{_+i, transit oi:tation and s:ao5 stence3 outside Dade 4i:.11 be reimbursed bused L)L'LOY lNJCOVc l CL. i:ll(_ : -PY. aC11ED1,7LE VI C:)t th,a l:sst:nc.2 and furLiiior +. i.0 ' the ILUkK pC•�!� [�i j', ;1Il lll�:+tnt.ij' .:N� C?I)iy a:,on ..it1c1 .:uii"c'r:...an:: ...Itil, :,I;eC,fC aut-i1U1".....itloil L.v,;' tll.' wf Ir g !'he CI`rY sh-LI :�ndecvor to to ra'. ie�i �a�i �;a��::oval c-+: tine various L),l ,s+�s c 3 2 tic J a 1 J Q ,. r e C: C 1,J t O .f .. a b:T11 .3 s l O I i o . � ). G .... _r.. i.oc•a u:10 _�grc.ci bj bo�.. p..3rtic.s tiiat CiIU Alollo:, irj• acj,.�6ulo Silaii be St.-ictly follow(.3 Ly the PRIN^IPAL alid tilt �.i:Y. P agr2m 3+.l.cbm+_nt and Planninq Phase: ine PItItiCIPAL shall complete the Pirogram Deve.lop.aent a:ld ?i,:nl)iay Phase within 15 calendar days after receipt Df written author i za t:on from the PROJECT t•ihWAGE . to '),egin ►:OI;i, on this Phase. 3. J•_sign Jev;.?.onment Phase: "r Pt21,'i, ti "'IPAL shill co;aaletc the Desiya �weloptnant wit,11.1 60 cal._r,d,_r vays aite:. receipt of-,jr4.tt'E'n :auriz..Lio,: ..fo;n Lii._ l:o be-c:_n t;CItK o:; T,le PARINC1 PAL shall complate the Construction, l:hus<_ within oQ calendar days after receipt of. ;;rit_en itutilui i_,at:cn i:o:n til• PROJECT ;iANAGEP% to using :•rc.rr on tnis Ph,t---e. PilJ:�: iClu i3,dLIin Pha:_o is .!Xpucteu to require 30 calendar •.1'J,ys, 1L onay .1 311IrAle hid is Usec . - 17 - ,:I'uc zII-I .I coi,:,cr-nue 41th the ..1v,1l:v 1 he cci,r:1eted :•;hen �onji�ion v� �_en rnet: i:.'. Plt! 1 s ti_'livG're�; �:O �Ii3 t;i1'�' [:ilttE'n J'CIPAL L'ti CiL . 'i�1n Lilat i_he i?ROJCCT ha:: been constr[:c:i ed L':1 L11a CI`P', d1:r'J'l L'•iCt I��CG17r3[1tG, 111C1 ]C�'_rl�� 1! 1 '.'�'provt:Li chanq'-, or-lul:3. i,_ :- J C ? ' �• •` 1 L 1 J 1.:3 Jali%e�re� to the CITY "rCc'0rci :L" i:e.gUl ..CC Ur,CjeL ,SZC'I'' G�i Ag ro..'men1:. iry C.0AlMiG3ion has accepted the FROJLC'r Lo1J Resolution. i;lc? L[1 j:.11 Ol tilo CollstL 11Ct1UG P11c3:iG: Slla.l). Le C`ituL11S11( d U�'.y1. acc.:,:rec, a: i:;1+= compI 'ion of thu Design 1Devolepatent ev ::zc tiic PI;IidCipiL is un,ble to mot''t tl-le auov3 L:ci :1 , or c(:):np.1ote tIx? above services because,or d e 1 a S r,o:.; :�c:ts or Gc:J or untimely review and approv"I by the cvern;',Ie ltai autilorit:i..s i;a:.iny j[:r.isu::�t;on Duet: such del'1''s �r�� not �dt1Sr_d t)l� t'i( ��t�I:d:'hL, the Sli :li 11: a reasocia�ole exte. sion O.i- LiMe fur COMr,10i;1Gfi UL be .:1L'. r, 5pc;nSlbi'_1Ly of the PRINCIPAL -_o �?ro.r::,t:ly i11 wriCing whonever a dolay i:1 approval a, ,: _ ;r.• :..li. e:ic�l agunc is ar[ticiparced or experienced, a, to the C!'71 ,ii a! 1 i.:cts anu d::tails related to the delay. sllcl'T_Q(•i VII Lo'1'liOR' ZLJ THE BY "ITY: rsn..;ii furnish space planning and i•,torior s_•; : �3c)rVie--e w:-I_ci: arQ ncrinally u par of his JOCl:ljerlZ:a dfid sp,3cifications , as pait Uf Ilia 4 �^ :ii!:Lin tao c.tt!:)ul.lted FEU, l s )8 _ )MN /'"IN ti,c right t:o ,UCi:oriL� tile PRINCIPAL a6dit:LC,:I>1 ;c.1:- ic,.s, .i fou.rd a c-,iss.iry b7 P?rL-vie In wiliCII C,:!---e tI.l' i[<1jd': Li.'r�fa a[?c.�/VY thej)a%LrJ CII�Jlrylh�lt�l! Jyl�cjai..sts J11a11 lie i)ai� at t. u i Ji:c )� -.cS �:1(nE.'F) l)1:::�r.:l: ...C(lil1C"11 salz-1:y' ::j,?Vli:il;S fCL _• _ dI], �). mil:_ o',1:VJ.r fi:Cjul i file _fTY A�)_.iJ_liln�j '.-Jrl .ii_II aI,tiIU! i.,aL1(;11 v i1C. i'..... a:,.L:'Ali 11)pi1 p-41, til'. IP!!!i a - d r-tJL .-.J illLC?C:t L)er!iollnuI LXPerlSQS as def111'�.i In .:11iS o..inent, cor these services rendered: 1. ilci prevlou iy approved proCjraulI drawings and,, or specificarions to accomplisrl changes, by the CITY, unl%?ss such changes are required to brine the c--)11:3tr'lcticn cost_:; within the budget as required in SLC`PIO:J :if or to ineet buidling or uIt- iler code !-6LlUireirle11ts. 0r,2pia1:F-- uocumutlts if requested by the CITY for altarn_ce aids rand change orders. r,yirl f•�r t.l'_ t1�,Rt: to pros -Bed Should cilc: :ont;:,accJ_ d31a'alt due t, (jclinque::cl or insol•:enc: ,. )/aJl;.ly .i.'.:71C 19rrd i:O:iLraCI adminis:--iat:C!ih a .a �).)3e.:vat1UU ci __ustrucLion si.ould tu a 1 :st.rlction ti,i,. ....:doJI i:ha contl'.:ct Cliil.iL.'.UCt loll u ri7-4u!ro. ..iore tliul: ss1X a:dltiou -- I tlt'-IAly !'.lt•:OViIII S C!UC to no f:.u1t Of tha PP. 1INC 1PAL. 1'cllstru.otion Contract time shall include any tir.ie -.. ior,a recum.-.i,. lnuod by -thy: PRINCIPAL and approv'a,: Di t11:: CIT'- unless :)oth parties agree that tha cause �i til._ LICc ..y t:.;:, tucu-'.1v beyond the control or Of t;le PRINCIPAL;. i,h .,1� �v•_nL rh at delays not caused by the PRINCIPF,L - 19 - 0 L] i %I}�:t :•lUit: i11 ill Pilaf:es CUf thPro cct, ,X 1';;ili:,; tn? "oils ,:ruct:_;;n Phase, Ua dezl:ayed moro than i}c:V` _'1e oILUn L =1 t0 i'+.-jjci.�rt= c..ntlL),�r►.iatlion i:j.,_-.06 0l7 .;ctua: OXI;enses i any 11 : ',1:iti ll:.l': i. : n l.lc;alroLi b'•i ta,? !t INCI r:d: d'ui: 1tv_j tilt' Jri C.1'3 hC�J u":T .•1dS :;'levee: . ::.1: i.l `a i.. 11115 _;lEt G .0 `..O-ti:rnllne t:li'j �L s,a;i":L _'2" t0 CCi;iof ='l+' WO"IK of t.hij SY:• 6e in 41riz: ng to th'te Pe;1CiC:iPAL• aild the P:2i!:C:Ii�.�i, t:u11 aai1i _or sei:vicus iE:ilc��_''L�CI In cacti cutiipl'--teU hi1F::it' priUt to t:errninacion in acc;�druaiice wiLil Section V - COMPENSATION provided hUW:r Ve:: that the PRINCIPAL is not in :iaf tu{t under the ter,is of this Agreement. If, however, the termination of this Agreement, occurs during an imcomplete P. iiSE, -:hen the PRINCIPAL shall be paid at the razea of 2.8 ti:^es ui rect Pc:rsoilnel Expenses for those services tendered inzcmplote Phase provided, that the PRINCIPAL is not :1 dt?flUa.L under" the: L_irit.^, Of :his Agreement. if no case, sh-sil c,ie (mil )ay tl}e P.iINCiPAL a cjreatcx :,.wounr_ ..Ould have 13c,an pz;id hzid Lhe i;`+_n mi"de ti,-: ccmpl et ion of the Phaae. :i rile: e v e i i c of Ler:rllilatloil f,,r any reason, all tioou.n_ats, [Mans, etc., ac set Iort:h in SECTION XI s'hL11 ecorae tale pru,.)crty of the CITY, with tite same provisions of l C ►� a 1'7::L1 In SECTION X1. SEC-TIUN IX ,)(l[.C1PAL r(:[)j;:es Uo have the fallowing r� :. _:acs, _ici:�_r fron his utganization or .is his r"'1 ,l.l,,.lt:ttlt5 Ui 3S OC1:3t:tS :O i)oj-.tor:il i:ihe ;=rviceu indicated: Git:n AIIet. Buff Pat i.lsi;in 3j. :.nd LiQ'_-cric i.L Tr'ii ,i.o Assoc.. 1L(2:; 1210NI X :.�S1OI•i;1L i,F;P0US1B Li':'IL6 Lvi1o`;.:atj L'0I::?5:'1011.11. sc-lr *cc:s d'.:d work L'V tee 1 l = 1 no ~ be cons ijered L?::::: 7 :::;(:ry lceS b-A t;1n i.:t'_ Gt .t r :iha.il :.r _-)',,(.Bred ?aI:t tjf i.t•d;ORK f t'lu ,. R?-tVi:;e :he Construction Dc)t;umeats 1?hase ;ar,6 Construction Mans and specifications to reduce t-he cost of con..:_uction of thc. PROJECT to chc:• find b-%1dgeted or CITY approved amount for the cons,:ructlon of :no PItUJEC'i',, in the amount of t I i o _owest acceptacile yid 'receiver by the CITY fJr tn(? conS,�ructi(►n of the PROJECT is in exces3 of tile fitl�l dmoan� budgeted or approved for the cost of Coils t:ucCIoil contract of tile PRUJI:C71. :,:,Quid �,�, Lrror or arro', s in 41 PRINCIPAL I S :iesig:. ca.;sta di-1:1y 1n 1-;1e construction of the PR)JLC l,, d consequcntl;' result in lelay of file C1-Ty 's beneficial oecul?ancj of tale PROJECT without compensa;:ion of damages from the contractor, the Pi2INCIP:�L agrees to seek no additional compensation ioZ the sw_viees required under this Agreement, during t1;.' poriod oi: said delay. �. -"Y O''-ilt3r revisions suggesttad by the CITY that are lJ:t:ihin t't;(. sc:ope of the WORK as defined in SE LION I1, Subst ctioth P. SECTION xi A u,,j,: um—nl'_s cIt v,'l0L--) Jy the PRI::CIPA1, under cr as ,. 21 _ m lb A 6hail of to tic- Cri,Y by :3 7 1 L:C i on roimt)i a t: ion of thu s � r v i c c s quires U to th is Ag roon,_'nt in,. oh a;'.. I )(.t,_-ome the :-)r opei: ty Of 1: L2 ;7' c .1 in a f: c r. on i ts o e i'y t r v .1 s _.c UC,:?J C U V OM (: he d R I,.; I Pj i L cl S to -flu r.:-'):i t-,U 1 r- Ij r us E Th.-- PRINCIPAF, agrees uliat all 0 n t s in a i n t ..i i n c?u z I n J, (j d 11 ";_1 !*':. t 0 j P U r z u a 11 t tQ this til(:., CITY anI tilt) PRIL1,1CIPAL rela, t ions.-, i:� r i i,.) L"Uoi i o o r. 6. 3 117, FloZi6a '_'tai-lltes. S :u1-'*1._-1: t)y _! and be1w.,cn .he j..)artiQE; .:jI,,jt o n y i I f o rm a t i o n t 1, 11 .�T S Contract documents .s 1— . or any other rnatter whatsoever whicn is 91vell -y Liie CITY to the PR!114',-'IPAL pursuant to this Agreement shall .:ill times remailn the property of the CITY and shall not by t:ie PRINCIPiALE for any other purpose whatsoever itilout the aritten approval of the CITY. It i f u i: the;: unaerstood that no press releases or publicity is to be issued oy the PRINCIPAL without prior to tie CITY and written approval ErOM the CITY. SECTION XI I ...;A OF AGREE 'MENT: iie has not einployad or j_(_!:3r,j,js to s-,- icit r,-_, rjc~cc.ZL' t'. .11S that: ilt: -'IdS '1'.')L Palu )L agreed to Nay any compull.y percentage, orokerage fee, or 0 L L'i t--' r cOl-ir, i:jQrF, tiOns conLingerIt upon c r z-;--i -.:.ward or making of this warr,:Illts that to tiles - best of i1jr, f no Mayor or otht--r officer 7.1: ; S t h U c; ill, i e r e s t e d diro:ictly , or zht r of i t-, of emOIC4,1011ts Of this Aqreem_:--nt - 22 - with 1: n. f C) L) 1: f: r s n z '2 n I Oi LAliS C? 0CITY. This dce_3 nor WDPILY to it J C"I T !f . -PAL i, "e "onflict of Irtter_!sj -t Law , c o f 6,;1 t i C L v N,fill. ij a d,D o u: i r:v , F 1. a r d, ci Luliy COML)ly ill with tlic-, t --:. 1 m s 0 f _aft] aw SECTION, XIII Oi" AGREEIMENT: the entire and i n tey r a ted s n', n t r er) r '_-S 0,- 1 t S INCIPAL and suporsed-es -,tw�aea -lie cury and the PR L prig n e,j o t i a t1' o n s representations 0 r agrOU'LlelltS h.3 r tt r L or. or oral . This Agreement may be amended only e n . 4n s t r um e nts oy 1;oth the CITY and the PRINCIPAL. SECTION XIV 7UOCESOR_S"-"'1;D ASSIGNS: ':,:, PiiiNCIPAL shr-11 ma:W 110 assignments or traiisf,-_i: of or zransfer any part of witilout the written consent oZ IT y ri"Iiis Ayr.::_ ,lent shall be binding upon the parties t r il e 1 ': Z-. executors, legal representatives, T I(; S ""' ..-� - N XV cc:rti that w;i"o ratc!s an ' 1 :NL: I PA L d 0L I er u, J L co i. - s u pp o It n the compensation are accurate, - 33 - $ �a t 2 r .2 t. 0 1: i '!' Y L i c l r a -.4 A j u. n t c. k am Ll 4" %, 0 Jo I I w i: L t nu t-A•j S Ij ? I,- J z ke J. c f- [A t Dl- ng 1: c h c i,.. n r .A1) Ll SECTIGN ;,lvrl 0 7 'J D.LT C 1T y sc ry t C) u d t t 11 o r c. ro r j s of cn;.. L n t . r i ..III' 4 1' 0 G -- C U t 0 I'l 0 f t I I 13 A t ci u L I i J C. 1::-: a 1.: c- r 111 .1 1: IS V ILl Q il. -4; S,tvc t:ht. CIT'.1 L: L'A IL i 1_.• j U0% I L i C; k., I s t- a "a ea , L'.7, t, 1 " I., _3 I t.C, t e rl C;. 1. 1: 11 %!'. 1 C!, i C r Ir :,:b: I i,i cA i's C: i E�:. _ 7) V P I Y L, rl(; th t: '! LI C C, c I n:i 1 i -a b I t v I s u r,, n e in E, il, -.i o u n t r; .L,!);:t),i)ilU k: C, V 2 1: ')(1 :A 1 1 a Y) I 3 Ccr.-i. c ri--:,a Gn in s u 1- a nc e. in e :3 ,a, u -cry 50 -'S I..g j a n ��er C:.� C 0- 1 c Z, c; 11 s -a 0 lis"tod J.n ma-,Iua s :filch m, o s tn a r OZ the PRI.INCIP"L. be s uod b n j n U" 7 Z, and which art~ a,.jo ov.-- ac c)iairks CO C C �L 10 0 tilt:: 'z k' Mail t i.3-, on oL 17 r i-C r. o i I o t th L. IC 0111 t 0 If C a t o :j shal 1. ea r I L NC I i'AIL lha:-i cij i-i I -J.1 i u ra i1c o is3i f I (---I .:-Loll iIS L C t 0 1' t 0 .4 on t;l;1 L ill day-i w: it :%In I;JCic0 CO t i I.,:! o r o 1 '01 requ I C", i. s t Y a F ILI I J L C i T N, t 1h. !L" H. a L Q Z IJ 1,' U L Q C e t i 011.11, L. UO i: o r. s i il a i J s L 1 1 D U C 11 1 j L; 17 o. i-, n k:. 't L- i J "-s 3 J1 'J ncurriancc- ':111-6 GU -t...On in i:_:lt`lii . OC t ' 0 11 Zfi V 1.3 L ri, - I.. i) e P CT Mli i i A G: E k s I ri-C 1" oil r. G` (..2 " 'LR 0 j EC_ 'A' i'iA LIJ A 10 ER arid "I In P_ PIS i N C 12 A L s; .;Cc ij:­)n Di t I CITY MANAGER A-- -.1 S t M k- 'I t C 3:11. C., t L.-i-ne i)ecausc of- changf:,is .111 1: 1. c v 1 e u y h'2 P 1., :v E%--,"- A G v C r. 1 s� ON 01 C C"i L C. CL o". Li. c t 0 Liz. 2 L !I".C. L c, 1 v 1 [IOU m: � c' o r is 1 1 I'l C 1 DAL S I: ::Fla t S E:,-, I Q. es O.f: C., Il' Y 3 1, cl sa a I no v k�z., t: 0 1 0 v I r v f V r W: s ene r �l 1: 0 r IL r i ),a D 3 t 1 L, ION V I � I L il il 1 02 11 (-',1 1! :4 1 ,3 C C C) i "JI a Wp S 2 L -S at- S C., 1*.,,..:T %'. �, I �V, L Cj .7_ .:o�.. 1 ;'-A in Wr, _1 I ..• :i r[:_ L.1 ,i .-�.L 71. .-1,.l__ 1c . b :wee : to. to Law "L I _ any :r_[:w6 cr :101Li01:_' ._.:C:'_Aina:. do....:iian t , Lh a terms in t:..l._ • '.l .:,=:;r 3r. G any L:? ^.V _s..ona, pareyzapVu, .. ;:nta3nccc, word2 _ _ . .mij .:' p .. AM _.. Lhi. Ayr,:�cm mt at r_C_�?_:: __:i� }LlI15i 1C�...Ol� to i:'_` iwal...G, _1 ug' _ or O'_:1e.'4:15'. L:aun .forcL7aole under chn O'. s of , ..: 1_a :i .: 21wric:.: OK W: r"i to, o 0i'm 1, 01': i ��, 11.•J. i:il'7[7: , �J.. it ,.la :;,,i[!:t:il � , ilJ." :: f:'.. P..r.. 10, .h .' COW.- hi :rl.::c'.: it i"i and i i ul l :_awu in.] t ._ 24 ._ V I i L! L: -i XXV I 1 n v., t 11 I L 1*1 � Ii-6 :1 C., a r L OiC 'j 13 -:v r -ril .;n( no i A c! z IIC --ond i z- ions cc.-itaitiid' hec ei W pun wr n n,.) i c 301 Q 01) c un L. � L and terminate th.-is Agreemcrit, aiJ ail -S PA L auvancQs, Or o c ii c r c om p e n s a t i r): i pi id t o F 1 1 L,, C I r R 1 .4 1 p A r, V., cl l, it) def-'ault of tho 1) r;., v i C.) n 3 i ii,--,Ll , sh'-, 11 be k, r - tit; i th r tu rn --d "o C TY It: G U i: 1 i: c r, t:,,-, President 'I", j t L 0 ( 13 _, A L ) ISSUE. DATE 1A%L—%N1 8/7/86 JW THIS CERTIFICATE W fSam A." No RIGHTS UPON THIS CERTIFICATE EXTEND OR ALTER THE COVERAGE aloflar IEK �. PRO(R10ER Seitlin b Company .y P.O. Box 025220 Miami, Florida 33102-5220 „,sSURED Kunde, Sprecher, Yaskin & Assoc., Inc. 9765 SW 184th Street Miami, Florida 33157 COMPANIES AFFORDING COVERAGE "RY A United States Fidelity E Guaranty Co. COMPANY (Design Professional) LETTER B Connect i cu t t Indemnity COMPANY LETTER C COMPANY D LETTER COMPANY E LETTER THIS IS TO CERTIFY THAT POLICIES OF INSURANCE LISTED BELOW HAVE BEEN ISSUED TO THE INSURED NAMED ABOVE FOR THE POLICY PERIOD INDICATED. Ik NOTWITHSTANDING ANY REQUIREMENT. TERM OR CONDITION OF ANY CONTRACT OR OTHER DOCUMENT WITH RESPECT TO WHICH THIS CERTIFICATE MAY BE ISSUED OR MAY PERTAIN, THE INSURANCE AFFORDED BY THE POLICIES DESCRIBED HEREIN IS SUBJECT TO ALL THE TERMS. EXCLUSIONS, AND CONDI- TIONS OF SUCH POLICIES.*} i CO LTFt TYPE OF INSURANCE POLICY NUMBER POLICY EFFECTIVE GATE iMM/GQ+YY) POLICY EXPIRATION DATE (MWDWYY1 LIABILITY LIMITS IN THOUSANDS ►' EA N AGGREGATE Ali UR OCC,ENCE GENERAL LIABILITY BODILY INJURY � .Fj X COMPREHENSIVE FORM $ $ PROFEFITY DAMAGE $ 11.. � X PREMISE S'OPERATIONS UNDERGROUND SMP 093021380 4/29/86 4/29/87 EXPLOSION d COLLAPSE HAZARD X PROOUCTS/COMPLETED OPERATIONS X CONTRACTUAL III a PO CCOMONED $ 750 $ 750 X INDEPENDENT CONTRACTORS X BROAD FORM PROPERTY DAIIaGE X PERSONAL INJURY PERSONAL INJURY $ ]SO AUTOMOBILE LIABIUTYkAJFfY w X ANY AUTO BAP 058726800 4/29/86 4/29/87 ARPEMN $ MILY ALL OWNED AUTOS (PRIV PASS.) ALL OWNED AUTOS (OTHER RAM AR NTI $ PTHA) PRIHIRED PROPERTY AUTOS NON -OWNED AUTOS DAMAGE $ a Po GARAGE LIABILITYeI e coAAsINE:D $ 750 `• EXCESS LIABILITY 4 X UMBRELLA FORM CEP 084680541 4/29/86 4/29/87 ;� $ 2000 $2000 OTHER THAN UMBRELLA FORM STATUTORY WORKERS' COMPENSATION 45o4797861 4/29/86 4/29/87 $100 (EACH ACCIDENT) AND ' 00 (DISEASE -POLICY LIMIT) 1$100 EMPLOYERS' UABIUTY (OISEASE-EACH EMPLOYEE) OTHER SCRIPTION OF UPERATIONSILOCATIONSIVEHICLE$/SPECIAL ITEMS Job Location: Orange Bowl - Gate 7 B City of Miami 1501 NW 3rd Street Miami, Fl 33125 Attn: Sussey Bermudez SHOULD ANY OF THE ABOVE DESCRIBED POLICIES BE CANCELLED BEFORE THE EX. PIRATION DATE THEREOF. THE ISSUING COMPANY WILL ENDEAVOR TO MALL 3 0 GAYS WRITTEN NOTICE TO THE CERTIFICATE HOLDER NAMED TO THE LEFT. BUT FAILURE TO MAIL SUCH NOTICE SHALL MPOSE NO OBLIGATION OR UABILM OF ANY KIND UPON THE COMPANY. ITS AGENTS OR REPRESENTATIVES. ITHORIZED REPR ESENTATIVE 5e i t 1 i n & Company 'I .:+:.rest George, H . KtLA dg!, C. Exec . V . P . , Sec., Treas., B(-•n -jamin P . iYa i r.+� 1 p d to 3*L1: cc r t.racts :i ..._.._. ,.. ;:� _ � Kf1C3j]j,:,,�.-SPLtF��--`1#-i4-�'F�--F►--'A:� ,_"�'P:f'.�...____. ....._. i i:5 :uly :i'+vf)rCl 0i1 _.:iaent - Vic,:-nresid'ent - ocretarv) ::nc- iLs ar.d z igfl car,t.ractrl and ag :-_everts bind ric z he ..,1-1poratic-'r. zo ocntract:3 and Offic,3 o2 Stadivans. 5;'ALs f TO .'::vl) SCBSCRIF L) 1,o or o me tiac ��nI1RTu '70TARYr P 8' I Ccirn;iseion Expi `s: r a n a e "zo .7i&&nzj ln�., w�L Qu jv zoll .%I �c -Intl ao" dooal:r cs f UrAiso 1w z t..1 Fourth• a: September SAVISALN, WON LZ Ar7cvo:.: 13Y A4v- k 1. A t C A L d September Fo ka r tfi y .,.Ai ... •.,L , I The original frdi'which this microfilm was taken was awfully poor. This is the bestphotographwe' could obtain