HomeMy WebLinkAboutR-87-0127J-87-111
I/ 26/87
RESOLUTION NO. 87-1 1"i
A RESOLUTION ACCEPTING THE COMPLETED WORK
OF LANZO CONSTRUCTION COMPANY AT A TOTAL
COST OF $716,972.67 FOR WAGNER CREEK
RENOVATION; AND AUTHORIZING A FINAL
PAYMENT OF $18,753.07.
WHEREAS, there exists a contract dated October 1, 1985
between the City of Miami and Lanzo Construction Company; and
WHEREAS, the work has been satisfactorily completed by
Lanzo Construction Company and they have furnished the required
documents certifying that all bills for labor and materials
have been paid in full in connection with the aforesaid
contract; and
WHEREAS, the City Manager and the Department of Public
Works recommend that the completed work be accepted and final
payment made to the contractor;
i
NOW, THEREFORE, BE IT RESOLVED BY THE COMMISSION OF THE
I CITY OF MIAMI, FLORIDA:
Section 1. The completed work performed by Lanzo
i
i Construction Company for WAGNER CREEK RENOVATION at a total
cost of $716,972.67 is hereby approved.
Section 2. The proper officials of the City of Miami are
hereby authorized to pay $18,753.07 to Lanzo Construction
Company as full and final payment for all work performed and
all materials furnished in connection with WAGNER CREEK
y RENOVATION.
I
CITY COMMISSION
MEETING OF
FEB 12 1987
RESOLUTION No. 87L.•1Z•
lltEMARI(Si _
/�
F
PASSED AND ADOPTED this 12th day of February , 1987.
ATTEAT :
ATYHlRAln,.t.*G�I-TYCLERK
PREPARED AND APPROVED BY:
v
CHIEF DEPUTY CITY ATTORNEY
APPROVED AS TO FORM AND CORRECTNESS:
'L V VA n 1'1 • u V V N
CITY ATTORNEY
BUDGETARY REVIEW AND --'APPROVAL:
1'1 I111 V 11r%11% J • J V 1\ ,
MANAGEMENT & ET
FINANCIAL REVIEW AND APPROVAL:
�/,V. .
FINANC'r DEPARTMENT
- 2 -
8'7--127,1-
E
CITY OF MIAMI. FLORIDA
9* 19
INTER -OFFICE MEMORANDUM
TO. Honorable -Mayor and Members °ATE`
of the City Commission
sueJECT:
:1
FROM REFERENCES:
Cesar.H. Odio
City Manager ENCLOSURES:
RECOMMENDATION:
FEB 41987 FILE: B-5508
WAGNER CREEK RENOVATION
Resolution for Final Payment
It is respectfully recommended that the City Commission adopt the
attached resolution accepting the completed work performed by
Lanz•o Construction Company at a total cost of $716,972.67 for
WAGNER CREEK RENOVATION, and authorizing a final payment of
$18,753.07.
BACKGROUND:
The Department of Public Works has determined that it is now in
order for the Commission to accept the completed work and
authorize final payment, after all conditions are met for Wagner
Creek Renovation.
Lanzo Construction Company has completed the project consisting of
the construction of 1775 linear feet of 8' x 4' concrete box
culvert, and a 34' x 10' special manhole structure along with all
necessary appurtenances. The work is located in Wagner Creek
easement west of N.W. 15th Avenue between N.W. 20th and 23rd
,Streets.
The total payment to the contractor will be less than the original
contract amount of $787,320.00 because not all of the bid item
quantities and the $60,000 Cash Allowance for special items was
used.
Attachments:
Proposed Resolution
87:427
FINAL CONSTRUCTION FACT SHEET
JOB NAME Wagner Creek Renovation - B-5508
CONTRACTOR Lanzo Construction Co.
JOB SCOPE Construct 1775 linear feet of 8'x4' concrete box
culvert, a 34'x1O' special manhole structure along with
all necessary appurtenances. The work is located in
Wagner Creek easement west of N.W. 15 Avenue between
N.W. 20-23 Street.
REASON
FOR WORK
SOURCE
OF FUNDS
PROJECT
HISTORY
CONTRACT
TIME
STARTED
CONTRACT
TIME
SCHEDULED
COMPLETION
DATE
ACTUAL
COMPLETION
DATE
BID AMOUNT
CONTRACT
FINAL COST
Removal of open channel section of Wagner Creek.
Wagner Creek Renovation - Phase II
Bids Received: 6/6/85
Contract Awarded: 7/18/85
Preconstruction Meeting: 8/22/85
3/17/86
90 Working days
7/22/86
6/6/86
$787,320.00
$716,972.67
CURRENT
ITEM FOR Resolution to accept completed work, and authorize
CONSIDERATION final payment to the contractor.