HomeMy WebLinkAboutR-87-0240J-87-212
2/20/87
RESOLUTION NO. 87-240
A RESOLUTION ACCEPTING THE COMPLETED WORK
OF MIRI CONSTRUCTION, INC. AT A TOTAL COST
OF $58,784.50 FOR CITY WIDE SANITARY SEWER
REPLACEMENT - DESIGN PLAZA AND AUTHORIZING
A FINAL PAYMENT OF $5,836.150
WHEREAS, there exists a contract dated August 19, 1986
between the City of Miami and Miri Construction, Inc.; and
WHEREAS, the work has been satisfactorily completed by
Miri Construction, Inc. and they have furnished the required
documents certifying that all bills for labor and materials
have been paid in full in connection with the aforesaid
contract; and
WHEREAS, the City Manager and the Department of Public
Works recommend that the completed work be accepted and final
payment made to the contractor;
NOW, THEREFORE, BE IT RESOLVED BY THE COMMISSION OF THE
CITY OF MIAMI, FLORIDA:
Section 1. The completed work performed by Miri
Construction, Inc. for CITY WIDE SANITARY SEWER REPLACEMENT -
DESIGN PLAZA at a total cost of $58,784.50 is hereby approved.
Section 2. The proper officials of the City of Miami are
hereby authorized to pay $5,836.15 to Miri Construction, Inc.
as full and final payment for all work performed and all
materials furnished in connection with CITY WIDE SANITARY SEWER
REPLACEMENT - DESIGN PLAZA,
CITY COMMISSION
MEETING OF
MAR 13 1987
PASSED AND ADOPTED this 13th day of
ATTEST:
ALta-c"—
PREPARED AND APPROVED BY:
CHIEF DEPUTY CITY ATTORNEY
APPROVE
CITY ATTORNEY
CORRECTNESS:
- 2 -
I � %
March , 1987.
8'7-24Q
is
CITY OF MIAMI, FLORIDA
INTER -OFFICE MEMORANDUM
TO. Honorable Mayor and Members DATE: MAR 5 1907 FILE:
B-5524
of the City Co mission
SUBJECT CITY WIDE SANITARY SEWER
1 1 REPLACEMENT - DESIGN PLAZA
Resolution for Final Payment
FROM, REFERENCES:
Cesar H. Odio
C i ty Manager ENCLOSURES:
RECOMMENDATION:
It is respectfully recommended that the City Commission adopt the
attached resolution accepting the completed work performed by Miri
Construction, Inc. at a total cost of $58,784.50 for CITY WIDE
SANITARY SEWER REPLACEMENT - DESIGN PLAZA and authorizing a final
payment of $5,836.15.
BACKGROUND:
The Department of Public Works has determined that it is now in
order for the Commission to accept the completed work and
authorize final payment, after all conditions are met for City
Wide Sanitary Sewer Replacement - Design Plaza.
Miri Construction, Inc. has completed the project consisting of
677 feet of 8" mainline sewer, 208 feet of 6" clay laterals and
one manhole on M.E. 40 Street between N. Miami Avenue and N.E. 2
Avenue.
The total payment to the contractor will be less than the original
contract amount of $69,877.50 because not all of the bid item
quantities and the $5,000 Cash Allowance for special items were
used.
Attachments:
Proposed Resolution
15-1
87--24C
FINAL CONSTRUCTION FACT SHEET
JOB NAME Citywide Sanitary Sewer Replacement - Design Plaza -
B-5524
CONTRACTOR Miri Construction, Inc.
JOB SCOPE Replace 677 feet of 8" clay pipe sewer, 208 feet of 6"
clay pipe laterals, and 1 manhole located in N.E. 40
Street between N. Miami Avenue and N.E. 2 Avenue.
REASON In conjunction with highway improvement
FOR WORK
SOURCE Citywide Sanitary Sewer Extension Improvements-FY "86"
OF FUNDS
PROJECT Bids Received: 5/15/86
HISTORY Contract Awarded: 6/12/86
Preconstruction Meeting: 7/14/86
CONTRACT
TIME
STARTED
9/23/86
CONTRACT
TIME
20 Working Days
SCHEDULED
COMPLETION
DATE
10/21/86
ACTUAL
COMPLETION
DATE
9/30/86
BID AMOUNT
$69,877.50
CONTRACT
FINAL COST
$58,784.50
CURRENT
ITEM FOR Resolution to accept completed work, and authorize
CONSIDERATION final payment to the contractor.
I S-: I
8'7-24C