HomeMy WebLinkAboutR-87-0391.3JOIN
5
RESOLUTION NO. 87-391.3
A RESOLUTION ACCEPTING THE COMPLETED WORK
OF EBSARY FOUNDATION COMPANY AT A TOTAL
COST OF $85,251.00 FOR DINNER KEY MARINA -
PILE REPLACEMENT C.I.P. PROJECT NO. 414005
AND AUTHORIZING A FINAL PAYMENT OF
$8,525.10
WHEREAS, there exists a contract dated September 24, 1986,
between the City of Miami and Ebsary Foundation Company; and
WHEREAS, the work has been satisfactorily completed by
Ebsary Foundation Company and it has furnished the required
documents certifying that all bills for labor and materials
have been paid in full in connection with the aforesaid
contract; and
WHEREAS, the City Manager and the Department of Public
Works recommend that the completed work be accepted and final
payment made to the contractor;
NOW, THEREFORE, BE IT RESOLVED BY THE COMMISSION OF THE
CITY OF MIAMI, FLORIDA:
Section 1. The completed work performed by Ebsary
Foundation Company for DINNER KEY MARINA - PILE REPLACEMENT
C.I.P. Project No. 414005 at a total cost of $85,251.00 is
hereby approved.
Section 2. The proper officials of the City of Miami are
hereby authorized to pay $8,525.10 to Ebsary Foundation Company
as full and final payment for all work performed and all
materials furnished in connection with DINNER KEY MARINA - PILE
REPLACEMENT C.I.P. Project No. 414005.
PASSED AND ADOPTED this 30th day of April , 1987.
ATTEST:
PREPARED AND APPROVED BY:
CHIEF DEPUTY CITY ATTORNEY
APPROVED00"ASITO FORM AND CORRECTNESS:
CITY ATTORNEY
- 2 -
CITY OF MIAMI, FLORIDA
- INTER -OFFICE MEMORANDUM
To. Honorable Mayor and Members DATE:
of the City Commission
SUBJECT:
FROM RVERENCEG:
Cesar H. Odio PO City Manager ENCLOSURES,
RECOMMENDATION:
APR 3 01987 FILE: B-3202
DINNER KEY MARINA - PILE
REPLACEMENT - CIP Project No
414005 - Resolution for Fina
Payment
It is respectfully recommended that the City Commission adopt the
attached resolution accepting the completed work performed by
Ebsary Foundation Company at a total cost of $85,251.00 for DINNER
KEY MARINA - PILE REPLACEMENT C.I.P. Project No. 414005 and
authorizing a final payment of :8,525.10.
BACKGROUND:
The Department of Public Works has determined that it is now in
order for the Commission to accept the completed work and
authorize final payment, after all conditions are met for Dinner
Key Marina - Pile Replacement C.I.P. Project No. 414005.
Ebsary Foundation Company has completed the project consisting of
removing and replacing certain deteriorated wood piles at the
commercial dock, removing two existing wood piers and various
piles at the boat ramp area, driving new piles and constructing
three new piers at the boat ramp area, installing mooring piles
along the bulkhead, and replacing the deteriorated support
structure of two navigation lights at the Coconut Grove Channel.
The total payment to the contractor will be less than the original
contract amount of $87,760.00 because not all of the proposal
items were used.
Attachments:
Proposed Resolution
17Fn,1
0
FINAL CONSTRUCTION FACT SHEET
JOB NAME Dinner Key Marina - Pile Replacement - B-3202-C
CONTRACTOR Ebsery Foundation, Co.
JOB SCOPE Replacing certain mooring piles at the Dinner Key
commercial dock area, constructing several piers at a
boat ramp, and making several miscellaneous pile
Installations.
REASON Replacing deteriorated wood piles and wood piers.
FOR
SOURCE Dinner Key Marina Renovation/Expansion
OF FUNDS
PROJECT Bids Received: 9/9/86
HISTORY Contract Awarded: 9/11/86
Preconstruction Meeting: 10/2/86
CONTRACT
TIME
STARTED 12/15/86
CONTRACT
TIME 50 Working Days
SCHEDULED
COMPLETION
DATE 2/25/87
ACTUAL
COMPLETION
DATE 2/12/87
BID AMOUNT $87,760.00
CONTRACT
FINAL COST $859251.00
CURRENT
ITEM FOR Resolution to accept completed work, and authorize
CONSIDERATION final payment to the contractor.