A RESOLUTION ACCEPTING THE COMPLETED WORK
OF LANZO CONSTRUCTION CO. AT A TOTAL COST
OF $2349006.07 FOR CITYWIDE SANITARY SEWER
EXTENSIONS IMPROVEMENT - N.W. 47 AVENUE
C.I.P. PROJECT NO. 351178 AND AUTHORIZING
A FINAL PAYMENT OF $36,802.66
WHEREAS, there exists a contract dated MAY 6, 1986 between
the City of Miami and Lanzo Construction Co.; and
WHEREAS, the work has been satisfactorily completed by
Lanzo Construction Co. and they have furnished the required
documents certifying that all bills for labor and materials
have been paid in full in connection with the aforesaid
contract; and
WHEREAS, the City Manager and the Department of Public
Works recommend that the completed work be accepted and final
payment made to the contractor;
NOW, THEREFORE, BE IT RESOLVED BY THE COMMISSION OF THE
CITY OF MIAMI, FLORIDA:
Section 1. The completed work performed by Lanzo
Construction Co. for CITYWIDE SANITARY SEWER EXTENSIONS
IMPROVEMENT - N.W. 47 AVENUE C.I.P. Project No. 351178 at a
total cost of $234,006.07 is hereby approved.
Section 2. The proper officials of the City of Miami are
hereby authorized to pay $36,802.66 to Lanzo Construction Co.
as full and final payment for all work performed and all
materials furnished in connection with CITYWIDE SANITARY SEWER
EXTENSIONS IMPROVEMENT - N.W. 47 AVENUE C.I.P. Project No.
351178.
CITY COMMISSION
MEETING OF
JUN 1111987
:SOLUTION No. 8 I1�
' tom-
PASSED AND ADOPTED this 11th day of June , 1987.
ATTESTwr (//4 r CLERK
-
PREPARED AND APPROVED BY:
CHIEF DEPUTY CITY ATTORNEY
APPROVEJrO TO FORM AND CORRECTNESS:
vv aT f1• VVV�i
ITY1ATTORNEY
.1.
- 2 -
45
Coif OF MIAMI, PLOOVIbA
INTER -OFFICE MtMORANCCUM
TO: Honorable Mayor and Members OATE:
of the City Commission
susjEc•r:
FROM: REFERENCE!:
9tLIy
ar H. Odio Manager ENCLOSURES:
RECOMMENDATION:
JUN 0 31987 MR, B-5521
CITYWIDE SANITARY SEWER EXT.
IMP. -NW 47 AVENUE CIP Project
No. 351178 - Resolution for
Final Payment
It is respectfully recommended that the City Commission adopt the
attached resolution accepting the completed work performed by
Lanzo Construction Co. at a total cost of $2341,006.07 for CITYWIDE
SANITARY SEWER EXTENSIONS IMPROVEMENT - N.W. 47 AVENUE CIP Project
No. 351178 and authorizing a final payment of $36,802.66.
BACKGROUND:
The Department of Public Works has determined that it is now in
order for the Commission to accept the completed work and
authorize final payment, after all conditions are met for Citywide
Sanitary Sewer Extensions Improvement - N.W. 47 Avenue C.I.P.
Project No. 351178.
' Lanzo Construction Co. has completed the project consisting of
constructing a new sanitary sewage system using 8"-16" clay and
ductile iron pipe together with all necessary appurtenances
located in N.W. 47 Avenue between West Flagler Street and N.W. 7
Street.
The total payment to the contractor will be less than the original
contract amount of $265,191.00 because only $221,954.65 of the
proposal items were used and only $12,051.42 of the $20,000 Cash
Allowance for Special Items was used.
Attachments:
Proposed Resolution
ra
<.x
`s.
z.�
JY r.
i
rw
FINAL CONSTRUCTION FACT SHEET
JOB NAME City Wide Sanitary Sewer Extensions Improvement - N.W.
41 Avenue - B-5521
CONTRACTOR Lanzo Construction Co.
JOB SCOPE Construct new sanitary sewage system using 8"-16" clay
and ductile iron pipe together with all necessary
appurtenances in N.W. 47 Avenue between West Flagier
Street and N.N. 7 Street.
REASON In conjunction with highway rebuilding project.
FOR WORK
SOURCE Citywide Sanitary Sewer Extensions Improvement •
OF FUNDS
PROJECT Bids Received: 1/9/86
HISTORY Contract Awarded: 2/13/86
Preconstruction Meeting: 3/27/86
CONTRACT
TIME
STARTED 7/7/86
CONTRACT
TIME 90 Working Days
SCHEDULED
COMPLETION
DATE 11/12/86
ACTUAL
COMPLETION
DATE 9/18/86
BID AMOUNT $265,191.00
CONTRACT
FINAL COST $234,006.07
CURRENT
ITEM FOR Resolution to accept completed work, and authorize final
CONSIDERATION payment to the contractor.