HomeMy WebLinkAboutR-87-0533J-87-529
RESOLUTION N0. 87--53k'3:
A RESOLUTION ACCEPTING THE COMPLETED WORK
OF CAMPANELLA CORPORATION AT A TOTAL COST
OF $64,336.15 FOR BICENTENNIAL PARK WATER
a SEWER SERVICE - 1986 C.I.P. PROJECT NO.
413003; AUTHORIZING AN INCREASE IN
DECEMBER 239 1986 CONTRACT WITH
CAMPANELLA CORPORATION FOR SAID WORK IN
THE NET AMOUNT OF $2,381.15 AND
AUTHORIZING A FINAL PAYMENT OF $6,811.15.
WHEREAS, there exists a contract dated December 23,
1986 between the City of Miami, Florida and Campanella
Corporation for BICENTENNIAL PARK WATER b SEWER SERVICE - 1986
C.I.P. Project No. 413003; and
WHEREAS, the work has been satisfactorily completed,
and Campanella Corporation has furnished the required documents
certifying that all bills for labor and materials have been paid
in full in connection with the aforesaid contract; and
WHEREAS, the removal of unforeseen reinforced concrete
obstructions caused an increase in construction cost that will
require a final increase in the contract amount of $2,381.15; and
WHEREAS, sufficient funds for the increased cost are
available from funds allocated to the project; and
WHEREAS,. the City Manager and the Director of the
Department of Public Works recommend the increase of $2,381.i5 to
cover the increase in the contract;
NOW, THEREFORE, BE IT RESOLVED BY THE COMMISSION OF THE
CITY OF MIAMI, FLORIDA:
Section 1. The amount of the December 23, 1986 contract
with Campanella Corporation for BICENTENNIAL PARK WATER b SEWER
SERVICE - 1986 C.I.P. Project No. 413003 is hereby increased in
the net amount of $2,381.15 with monies therefor to be provided
from funds allocated to the project.
Section 2. The completed work performed by Campanella
Corporation for BICENTENNIAL PARK WATER b SEWER SERVICE - 1986
C.I.P. Project No. 413003 is hereby accepted at a total cost of
$649336.15.
CITY COMMISSION
MEETING OF
JUN 111198T
ESQLUTION No. E #t�j a -
I®
PASSED AND ADOPTED this 11„t day of tine 1987•
PREPARED AND APPROVED BY:
ZC
R BERT F. CLARK
CHIEF DEPUTY CITY ATTORNEY
APPROV
CITY ATTORNEY
BUDGETARY REVIEW AND APPROVAL:
It" 0
MAN HARt!;tk--DIRECTOR
MANAGEMENT b GET
FINANCIAL REVIEW AND APPROVAL:
CARLOS ESTA R R
FINANCE DEPARTME T
PLANNING REVIEW AND APPROVAL:
u Rvv�saav�.&, v
ING DEPARTMENT
NESS:
- 2 -
11
CItY OF MIAMI, FLORIDA
INTER -OFFICE MSMCRANOUM
R is
to; Honorable Mayor and DATE: JUN 0 31987 riLE: B-5536
Members of the City Commission
SUBJECT: BICENTENNIAL PARK WATER & SEWER
1 SERVICE - 1986 C.I.P. Project
No. 413003 - Resolution for
F"°M'
REFERENCE Increase in Contract & Final
Cesar H. Odio Acceptance
City Manager ENCLOSURES:
RECOMMENDATION:
It is respectfully recommended that the City Commission
adopt the attached resolution accepting the completed work
performed by Campanella Corporation at a total cost of
$64,336.15 for BICENTENNIAL PARK WATER b SEWER SERVICE -
1986 C.I.P. Project No. 413003; authorizing an increase in
the contract in the amount of $2,381.15 and authorizing a
final payment of $6,811.15.
BACKGROUND:
The Department of Public Works has determined that it is now
in order for the Commission to accept the completed work and
authorize final payment, after all conditions are met for
the Bicentennial Park Water & Sewer Service - 1986 C.I.P.
Project No. 413003.
Campanella Corporation has completed the project consisting
of the installation of 596 feet of 8" PVC sanitary sewer
main, 52 feet of 6" PVC lateral pipe, two manholes, 227 feet
of 4" Ductile iron pipe water main and 121 feet of 2 1/2"
galvanized steel water main including all necessary
appurtenances at the SE corner of the park. This work was
required to service the ships that are to dock on the south
side of the Park or Old Slip No. 3.
The total payments to the contractor will be greater than
the original contract amount by $2,381.15 because unforeseen
reinforced concrete obstructions were encountered and had to
be removed. The cost of this extra work exceeded the
$15,000 Cash Allowance. This was a lump sum contract in the
amount of $61,955 but because of the $2,381.15 increase, the
final construction cost for the project is $64,336.15.
Attachments:
Proposed Resolution
87-53:1
/,S- /
FINAL CONSTRUCTION FACT SHEET
JOB NAME Bicentennial Park Water and Sewer Service-1986 - B-5536
CONTRACTOR Campanella Corporation
JOB SCOPE Construct 596' of 8" PVC sanitary sewer, 52' of 6" PVC
lateral, 2 manholes, 227' of 4" DIP, watermain, and 121'
of 2 1/2" galvanized steel water main including all
necessary appurtenances located at Slip 3.
REASON Provide water and sanitary sewer service for visiting
FOR WORK ships.
SOURCE Miamarina - Miamarina/Watson Island Major Maintenance
OF FUNDS
PROJECT Bids Received: 10/7/86
HISTORY Contract Awarded: 10/7/86
Preconstruction Meeting: 11/13/86
CONTRACT
TIME
STARTED 12/31/86
CONTRACT
TIME 40 Working Days
SCHEDULED
COMPLETION
DATE 2/26/87
ACTUAL
COMPLETION
DATE 1/16/87
BID AMOUNT $61,955.00
CONTRACT
FINAL COST $64,336.15 (Includes $2,381.15 overrun in Contract
amount)
CURRENT
ITEM FOR Resolution to accept completed work, increase contract
CONSIDERATION $2,381.15, and authorize final payment to the
contractor.