HomeMy WebLinkAboutM-87-0602Bid No. 86-87-098
ADVERTISEMENT FOR BIDS
Sealed bids for construction of FAIRLAWN SOUTH SANITARY SEWER IMPROVEMENT -
SR-5515-C (centerline sewer) will be received by the City Manager and the City
Commision of the City of Miami, Florida at 11:00 a.m. on the 29th day of June,
1987, in the City Clerk's Office, first floor of the Miami City Hall, 3500 Pan
American Drive, Dinner Key, Miami, Florida, 33133, at which time they will be
publicly opened and read.
Construction will include:
28,500 + linear feet of 8-inch to 20-inch vitrified clay, and cast or
ductile iron pipe sewer with the deepest cut being 16 ± feet;
16,300 + linear feet of 6-inch extra heavy cast iron soil pipe laterlas;
111 + manholes from 4 to 16 feet in depth;.
Sidewalk and pavement replacement in construction area.
The engineer's estimate for this project is between $1,500,000 to $2,000,000.
City requirements permit bidders to furnish performance and bid bonds in
accordance with Resolution No. 86-983. For clarification of technical issues
as presented in the construction documents and specifications please contact
James J. Kay, P. E., Sewer Design Engineer, at (305) 579-6865.
All bids shall be submitted in accordance with the Instructions to Bidders and
Specifications. Plans and specifications may be obtained from the office of
the Director of Public Works, 275 N.W. 2 Street, 4th Floor, Miami, Florida,
33128, on or after May 28, 1987. There will be a $20 deposit required for
each set. Deposits will be refunded only upon return of plans and
specifications to the Department of Public Works, unmarked and in good
condition within two (2) weeks after opening of the bids.
Prospective bidders are alerted to the provisions of Ordinance No. 10062
regarding allocation of contracts to minority vendors. The City will expect
prospective bidders to submit an Affirmative Action Plan, as defined in said
Ordinance, and as required in the Instruction to Bidders.
The City of Miami has adopted Ordinance No. 10032, which implements the "First
Source Hiring Agreement." The object of this ordinance is to provide
employment opportunities to City of Miami residents on contracts resulting in
the creation of new permanent jobs. Contractors may be eligible for wage
reimbursement under this program. For further information contact the
Department of Public Works, City of Miami, at (305)579-6856.
Proposal includes the time of performance, and specifications contain
provisions for liquidated damages for failure to complete the work on time.
The City Commission reserves the right to waive any informality in any bid,
and the Citv Manager may reject any or all bids, and readvertise (8-5515, Req.
3679).
Cesar H. Odio
City Manager
30-1
M0-1 �0r
87-602
LICITACION NO. 86-87-098
AVISO DE LICITACION
Propuestas selladas para FAIRLAWN SOUTH SANITARY SEWER IIMPROVEMERr - SR-5515-C
(centerline sewer), seran recibidas por el Administrador y la Comision de la
Ciudad de Miami, Florida, a mas tardar a las 11:00 a.m. el dia 25 de junio de
1987, en la Caoara de la Comision, primer piso, Ayuntamiento de Miami, 3500
Pan American Drive, Dinner Key, Miami, Florida, 33133, a cuya Nora y en cuyo
lugar seran publicamente abiertas y leidas.
Este proyecto comprende la construction de aproximadamente 28,500 pies
lineales de tuberia de arcilla vitrificada y de hierro ductil de 8 a 20
pulgaaas de diametro a una profundidad maxima de 16 pies; aproximadamente
16,300 pies lineales de tuber. a lateral de hierro fundido extra fuerte de 6
p,.lgadas de diametro; 111 registros (manholes) a profundidades de 4 a 16 pies;
reemplazo de aceras y pavi+-nento. El estimaao ae construction esta entre
$1,500,000 y $2,000,000. Regulations municipales permitiran a los
licitadores presentar bonos de cumplimiento y de licitacion de acuerdo a la
Resoluci6n No. 86-983.
Para pregvntas tecnicas acerca de los plans y especificaciones llame a James
J. Kay, P.E., Ingeniero de Disefto de Alcantarillados, al (305)579-6865.
Today las licitaciones seran sometidas de acuerdo con las Instructions a los
Licitadores y las Especificaciones. Los juegos de planos y especificaciones
podtIn obtenerse en la oficina del Director de Obras Publicas, 275 N.W. 2
Street Oto Piso), Miami, Florida, a partir del 28 de mayo de 1987. Se
requerira un deposito de $20 por calla juego. Estos depositos se reembolsaran
unicamente si los planos y las especificaciones son devueltos sin marcas y en
buen estado, aentro de un plazo de dos (2) semanas siguientes a la apertura de
las licitaciones, al Departamento de Obras Publicas.
Se avisa a los interesados de las provisions de la Ordenanza No. 10062, la
cual se reftere a la otorgacion de contratos a minorias. La Ciudad requerira
de los interesados un Plan de Accion Afinnativa, segun definido en 'dicha
Ordenanza, y segue sea requerido en las Instructions a los Licitadores.
La Ciudad de Miami ha adoptado la Ordenwma No. 10032, la coal implements el
"First Source Hiring Agreement". Esta ordenanza tiene por objeto proveer
oportunidades para enpleo a residentes de la Ciudad de Miami en contratos que
resulten en la creaci6n de nuevas plazas de trabajo. Los contratistas podran
ser elegibles para reenbolsos de gastos de salarios bajo este programa. Para
mayor informacion dirijase al Depto. de Obras Publicas, al. (305)579-6856.
Las propuestas incluyen el tiempo de ejecucion, y las especificaciones
contienen provisos para dahos liquidados incurridos por falta de completar el
proyeeto a tiempo. La Comision de la Ciudad se reserva el derecho a descartar
cualquier informalidad en cualquier licitacion, y el Administrador de la
Ciudad puede rechazar cualquiera o todas las propuestas, y reanunciar (8-5515,
Req. 3679) .
Matty Hirai
Secretaria Municipal
87-602
ESTIMATE OF COST
OF
LOCAL IMPROVEMENT AND INCIDENTAL EXPENSES
FAIRLAWN SOUTH SANITARY SEWER IMPROVEMENT SR-5515 C (centerline sewer)
ORDERED BY RESOLUTION NO. 86-679 ADOPTED SEPTEMB 1986-'
ESTIMATED CONSTRUCTION COST OF IMPROVEMENT ............ ..�........ S.I-r-8-H 000
ESTIMATED INCID ;.ITAL EXPENSES:
Surveys; Inspection and Supervision��
of work; Preparation of Plans;
Specifications and Estimates, etc.. S259,000.
Printing; Publishing of notices
and proceedings; Preparation of
Bonds; Legal services; Abstracts;
etc., and other necessary and
proper expenses .................... S 37,000
TOTAL ESTIMATED INCIDENTAL EXPENSES ................ S 296,000
TOTAL INDIRECT EXPENSE ............................. $ 10,730
TOTAL ESTIMATED CONSTRUCTION COST AND INCIDENTAL AND
INDIRECT EXPENSES ........................................ $2,156,730
DISTRIBUTION:
Estimated
cost to
be
paid by City of Miami ...............
$1,024,680
Estimated
cost of
all
items to be assessed ...............
$1,132,050
Estimated
cost of
683
Average Lats.......................
S 409,800
Estimated
cost of
53,500
L. ft. of Frontage ..............
$ 722,250
Estimated
assessment
per front foot: ........................ S 13.50
Estimated
assessment
per average centerline lateral.........
$ 600
3�-
87-602