A RESOLUTION ACCEPTING THE COMPLETED WORK
OF P.N.M. CORPORATION AT A TOTAL COST OF
$28,090.00 FOR WEST DUNBAR SANITARY SEWER
REPLACEMENT PROJECT C.I.P. PROJECT NO.
351178 AND AUTHORIZING A FINAL PAYMENT OF
$10,099.00
WHEREAS, there exists a contract dated September 10, 1986
between the City of Miami and P.N.M. Corporation; and
WHEREAS, the work has been satisfactorily completed by
P.N.M. Corporation and they have furnished the required
documents certifying that all bills for labor and materials
have been paid in full in connection with the aforesaid
contract; and
WHEREAS, the City Manager and the Department of Public
Works recommend that the completed work be accepted and final
payment made to the contractor;
NOW, THEREFORE, BE IT RESOLVED BY THE COMMISSION OF THE
CITY OF MIAMI, FLORIDA:
Section 1. The completed work performed by P.N.M.
Corporation for WEST DUNBAR SANITARY SEWER REPLACEMENT PROJECT
C.I.P. Project No. 351178 at a total cost of $28,090.00 is
hereby approved.
Section 2. The proper officials of the City of Miami are
hereby authorized to pay $10,099.00 to P.N.M. Corporation as
full and final payment for all work performed and all materials
furnished in connection with WEST DUNBAR SANITARY SEWER
REPLACEMENT PROJECT C.I.P. Project No. 351178.
CITY COMMISSION
MEETING OF
JUL 9 1987
8"d RESOLUTION No.
REMARKS;
r
PASSED AND ADOPTED this 9th day of July , 1987.
ATTEST:
MATTY HIRAI, CITY CLERK
PREPARED AND APPROVED BY:
.41
CHIEF DEPUTY CITY ATTORNEY
APPROVO /AS TO FORM AND CORRECTNESS:
L.VV Pn !1• VVv
CITY ATTORNE
- 2 -
r'. 2
s-
5
GITV OF MIAMI. FLORIbA
INTE*-OFFICE MEMORANDUM
to. Honorable Mayor and Members
of the City Commission
bAtE: J U N 3 0 1997 MLc: B- 5 5 3 2
SUDACT:
FROM: Cesar H. O d i o REFERENCES:
C i ty Manager ENCLOSURES:
RECOMMENDATION:
WEST DUNBAR SANITARY SEWER
REPLACEMENT PROJECT - CIP
Project No. 351178 - Resolu-
tion for Final Payment
It is respectfully recommended that the City Commission adopt the
attached resolution accepting the completed work performed by
P.N.M. Corporation at a total cost of $28,090.00 for WEST DUNBAR
SANITARY SEWER REPLACEMENT PROJECT C.I.P. Project No. 351178 and
authorizing a final payment of $10,099.00.
BACKGROUND:
The Department of Public Works has determined that it is now in
order for the Commission to accept the completed work and
authorize final payment, after all conditions are met for West
Dunbar Sanitary Sewer Replacement Project C.I.P. Project No.
351178.
P.N.M. Corporation has completed the project consisting of
constructing 280 linear feet of 8" clay pipe sewer and 25 feet of
lateral pipe on N.W. 18 Terrace between N.W. 7 and 8 Avenues in
conjunction with a highway rebuilding project.
The total payment to the contractor will be less than the original
contract amount of $29,152.25 because not all of the proposal
items were used.
Attachments:
Proposed Resolution
25 1
87--64'y
�L"•'K \a1 �i•+�-:�.i`iu1 � �.��iy.._ - .s'�C.•�i�i3�BRc-��+��� - - _
y
FINAL CONSTRUCTION FACT SHEET
JOB NAME
West Dunbar Sanitary Sewer Replacement Project - B-5532
CONTRACTOR
P.N.M. Corporation
JOB SCOPE
Construct 280 feet of clay pipe sewer and 25 feet of
lateral pipe in N.N. 18 Terrace between N.W. 7-8
Avenues.
REASON
In conjunction with highway rebuilding project.
FOR WORK
SOURCE
Citywide Sanitary Sewer Extension Improvements
OF FUNDS
PROJECT
Bids Received: 9/18/86
HISTORY
Contract Awarded: 10/7/86
Preconstruction Meeting: 10/9/86
CONTRACT
TIME
STARTED
11/7/86
CONTRACT
TIME
20 Working Days
SCHEDULED
COMPLETION
DATE
12/9/86
ACTUAL
COMPLETION
DATE
10/28/86 (Contractor began work before receiving fully
executed contract so as not to delay road
k
construction).
1 BID AMOUNT
$29,152.25
CONTRACT
FINAL COST
$28.090.00