HomeMy WebLinkAboutR-87-0792k S
J=87-165
8/24/87
RESOLUTION NO. 87-792
A RESOLUTION ACCEPTING THE COMPLETED WORK
OF M. VILA A ASSOCIATES, INC. AT A TOTAL
COST OF $32,391.20 FOR WYNDWOOD SANITARY
SEWER REPLACEMENT PROJECT (2ND BIDDING)
C.I.P. PROJECT NO. 351178 AND AUTHORIZING
A FINAL PAYMENT OF $30384.92,
WHEREAS, there exists a contract dated January 28, 1987
between the City of Miami and M. Vila & Associates, Inc.; and
WHEREAS, the work has been satisfactorily completed by M.
Vila & Associates, Inc. and they have furnished the required
documents certifying that all bills for labor and materials
have been paid in full in connection with the aforesaid
contract; and
WHEREAS, the City Manager and the Department of Public
Works recommend that the completed work be accepted and final
payment made to the contractor.
NOW, THEREFORE, BE IT RESOLVED BY THE COMMISSION OF THE
CITY OF MIAMI, FLORIDA:
Section 1. The completed work performed by M. Vila &
Associates, Inc. for WYNDWOOD SANITARY SEWER REPLACEMENT
PROJECT (2ND BIDDING) C.I.P. Project No. 351178 at a total cost
of $32,391.20 is hereby approved.
Section 2. The proper officials of the City of Miami are
hereby authorized to pay $3,384.92 to M. Vila & Associates,
Inc. as full and final payment for all work performed and all
materials furnished in connection with WYNDWOOD SANITARY SEWER
REPLACEMENT PROJECT (2ND BIDDING) C.I.P. Project No. 351178.
CITY COMMISSION
MEETING OF
SEP 88 1961
)N No. 87-- i
REMARKS:
..��...I�I. I III I �••.++III.1..l��M+�.Ib
t
PASSED AND ADOPTED this g,th_ d8Y of ,..._September _.. r.6 1987.
PREPARED AND APPROVED BY:
7%' , &aor
CHIEF DEPUTY
CITY ATTORNEY
APPROVED/AS/10 FORM AND CORRECTNESS:
vAn • -vvm
TY ATTORNEY
- 2 -
87 ! 92
N
citT OP MIAMI. tLON16A
INTC44PPICC MI MOOAN DUM
to. Honorable Mayor and Members bntE
of the City Commission
9UBAct
PROM
Cesar H. Odio 6y AtrOWNCES:
City Manager
MCLosukE5.
RECOMMENDATION:
AUG W 11987 P,Lt B_-4623
WYNDWOOD SANITARY SEWER
REPLACEMENT PROJECT (2ND DID).
CIP Project No. 351178 -
Resolution for Final Payment
It is respectfully recommended that the City Commission adopt the
attached resolution accepting the completed work performed by M.
Vila & Associates, Inc. at a total cost of $321
391620 for WYNDWOOD
SANITARY SEWER REPLACEMENT PROJECT (2ND BIDDING) C.I.P. Project
No. 351178 and authorizing a final payment of $3,384.92.
BACKGROUND:
The Department of Public Works has determined that it is now in
order for the Commission to accept the completed work and
authorize final payment, after all conditions are met for Wyndwood
Sanitary Sewer Replacement Project (2nd Bidding) C.I.P. Project
No. 351178.
M. Vila & Associates, Inc. has completed the project consisting of
constructing 520 linear feet of 8" clay pipe sanitary sewer and
370 feet of cast iron lateral pipe on N.W. 28 Street between N.W.
1 Avenue and Miami Avenue and on N.W. 1 Avenue between 27 & 29
Streets in conjunction with a highway rebuilding project.
i
1 The total payment to the contractor will be less than the original
contract amount of $41,932.50 because not all of the proposal
items were used.
Attachments:
Proposed Resolution
87-'792
' ilk
JOB NAME
CONTRACTOR
JOB SCOPE
REASON
FOR WORK
SOURCE
OF FUNDS
PROJECT
HISTORY
CONTRACT
TIME
STARTED
CONTRACT
TIME
SCHEDULED
COMPLETION
DATE
ACTUAL
COMPLETION
DATE
BID AMOUNT
FINAL. CONSTRUCTION FACT SHEET
Wyndwood Sanitary Sewer ReplaceMent Project (2nd
Bidding) - 8.5523
M. Vila 6 Associates, Inc.
Construct 520' of 8" clay pipe sanitary sewer, 370' of
6" cast iron lateral pipe, 3 manholes and all necessary
appurtenances located in N.W. 28 Street between N.W. 1
Avenue and Miami Avenue and N.W. 1 Avenue between N.W.
27-20 Streets.
In con3unction with highway rebuilding
Citywide Sanitary Sewers Extension Improvements
Bids Received: 12/16/86
Contract Awarded: 1/8/87
2/2/87
45 Working days
4/6/87
2/25/87
$ 41,932.50
CONTRACT
FINAL COST S 32,391.20
CURRENT
ITEM FOR Resolution to accept completed work and authorize
CONSIDERATION final payment to the contractor.
Z
8 7-'792