HomeMy WebLinkAboutR-88-0309J-88-328
3/10/88
RESOLUTION NO. 404- 30:r
A REFnLUTIny ACCFPTINr, THE COMPLETE[) WORK
OF DOUGLAS N. HIGGINS, INC. AT A TnTAL
COST OF !122,5?d.50 FOR WINONA SANITARY
SEWER PROJECT PHASE I C.I.P. PROJECT NO.
351169 AND AUTHORIZING A FINAL PAYMENT OF
S?2,246.15.
WHEREAS, there exists a contract dated October 1, 1QP5
between the City of Miami, Florida and Douglas N. Higgins, Inc.
for WINONA SANITARY SEWER PROJECT PHASE I C.I.P. Project No.
351169; and
WHEREAS, the work has been satisfactorily completed and
Douglas N. Higgins, Inc. has furnished the required documents
certifying that all bills for labor and materials have been
paid in full in connection with the aforesaid contract; and
WHEREAS, the City Manager and the Director of the
Department of Public Works recommend that the completed work be
accepted and final payment made to the contractor;
NOW, THEREFORE, BE IT RESOLVED BY THE COMMISSION OF THE
CITY OF MIAMI, FLORIDA:
Section 1. The completed work performed by Douglas N.
Higgins, Inc. for WINONA SANITARY SEWER PROJECT PHASE I C.I.P.
Project No. 351169 is hereby accepted at a total cost of
$122,534.50.
Section 2. The proper officials of the City of Miami are
hereby authorized to pay Douglas N. Higgins, Inc. a balance of
$22,246.15 as full and final payment for all work performed and
all materials furnished in connection with WINONA SANITARY
SEWER PROJECT PHASE I C.I.P. Project No. 151169.
CITY COMMISSION
MEETING OF
APR 14 1988 n
RESOLUTION No. S-309
►71
PASSED AND ADOPTED Ws Ift Aey of April , ma.
ATTEST -
PREPARED AND APPROVED BY:
�;Z' /.I.
CHIEF DEPUTY CITY ATTORNEY
APPROVED"AS TO FORM AND CORRECTNESS:
GHERTY
CITY ATTORNEY
6c .4dzik�
P 2iG DEPARTMENT
FINANCE7JEPARTMENT
Ad
FRANK R. MAY, ACTING UlUffrUR
DEPARTMENT OF MANAGE AND BUDGET
• 2 -
98-010S
CITY OF MIAM1, FLORIDA 43
INT[R4FFICt MtMORANDNM
tO Honorable Mayor and Members DATE
of the City Commission
SUBJECT WINONA SANITARY SEWER PROJECT
PH I CIP Project No. 351169
Resolution for Final Payment
.Vom REFERENCE!
Cesar H. Odfo a
City Manager
ENc�osuREs
RECOMMENDATION:
It is respectfully recommended that the City Commission adopt the
attached resolution accepting the completed work performed by
Douglas N. Higgins, Inc. at a total cost of $122,534.50 for WINONA
SANITARY SEWER PROJECT PHASE I C.I.P. Project No. 351169 and
authorizing a final payment of $22,246.15.
BACKGROUND:
The Department of Public Works has determined that it is now in
order for the Commission to accept the completed work and
authorize final payment, after all conditions are met for Winona
Sanitary Sewer Project Phase I C.I.P. Project No. 351lb9.
Douglas N. Higgins, Inc. has completed the project consisting of
constructing a new sanitary sewage system including approx. 435
linear feet of 18" - 24" sewer pipe, and 4 manholes together with
all necessary appurtenances. The project is located on West
Flagler Street at W. 58 Ct. A 66 Avenues.
The total payment to the contractor will be $3,680.50 less than
the original contract amount of $126,215.00 because not all of the
Cash Allowance for Special Items was used.
Attachments:
Proposed Resolution
Y3-/
FINAL CONSTRUCTION FACT SHEET
JOB NAME Winona Sanitary Sewer Project - Phase I - 8-5520
CONTRACTOR Douglas N. Higgins, Inc.
JOB SCOPE Construct 20" and 24" D.I.P. sanitary sewer including
all necessary appurtenances, across W. Flagler Street at
N.M. S8 Court and N.W. 66 Avenue.
REASON In conjunction with Dade County rebuilding West Flagler
FOR WORK Street.
r
SOURCE Winona Sanitary Sewers
OF. FUNDS
PROJECT Bids Received: 7/2/85
HISTORY Contract Awarded: 7/18/B5
Preconstruction Meeting: A/8/85
CONTRACT
TIME.
STARTED 10/25/85
CONTRACT
TIME 50 Working days + 7 days delay from rain
and 16 days to remobilize labor and
equipr,�ent due to stop work order
issued over holidays
SCHEDULED
COMPLETION
DATE 2/11/86
ACTUAL
COMPLETION
DATE 2/11/A6
BID AMOUNT t 126,215.00
CONTRACT
FINAL COST $ 122,534.50
CURRENT
ITEM FOR Resolution to accept completed work and authorize
CONSIDERATION final payment to the contractor.
2