A RESOLUTION ACCEPTINC THE COMPLETED WORK
OF MAN CON, INC. AT A TOTAL COST OF
$532,246.41 FOR OVERTOWN/PARK WEST
SANITARY SEWER REPLACEMENT C.I.P. PROJECT
NO, 35I280 AND AI!THORIZING A FINAL PAYMENT
OF S54,820.66.
WHEREAS, there exists a contract dated October 29, 1987
between the City of Miami, Florida and Man Con, Inc. for
OVERTOWN/PARK WEST SANITARY SEWER REPLACEMENT C.I.P. Project
No. 351280; and
WHEREAS, the work has been satisfactorily completed and
Man Con, Inc. has furnished the required documents certifying
that all bills for labor and materials have been paid in full
in connection with the aforesaid contract; and
WHEREAS, the City Manager and the Director of the
Department of Public Works recommend that the completed work be
accepted and final payment made to the contractor;
NOW, THEREFORE, BE IT RESOLVED BY THE COMMISSION OF THE
CITY OF MIAMI, FLORIDA:
Section 1. The completed work performed by Man Con, Inc.
for OVERTOWN/PARK WEST SANITARY SEWER REPLACEMENT C.I.P.
Project No. 351280 is hereby accepted at a total cost of
$532,246.41.
Section 2. The proper officials of the City of Miami are
hereby authorized to pay Man Con, Inc. a balance of $54,820.66
as full and final payment for all work performed and all
materials furnished in connection with OVERTOWN/PARK WEST
SANITARY SEWER REPLACEMENT C.I.P. Project No. 351280.
CITY COMMISSION
MEETING OF
JUN 9 1986
RESOLUTION No. 88---S 12
RFMARKS: 1
A
PASSED AN8 WPM 'th# g 91-h— day 6f r, , Juhe..._._.., � f 1988.
ATTEST*
PREPARED AND APPROVED BY:
CHIEF DEPUTY CITY ATTORNEY
APPROVED AS TO FORM AND CORRECTNESS:
ms
JL1\V V 1\i uv.�..� v �\i
PLA EPARTMENT ,
FINA CE DEPARTMENT
- 2 -
s
MAYOR
88-51.2
CITY OF MIAMI, FLORIDA
1Nfi€WOIrPicr MEMORANbUM
to� Honorable Mayor and Members bAtE:
of the City Commission
SUBJECT
FROM REFERENCES:
Cesar H. O d i o ENcLCsuRE9:
City Manager
RECOMMENDATION:
35
MAY
3 11988
FILE: B-5533
OVERTOWN/PARK WEST SANITARY
SEWER REPLACEMENT PROJECT
C.I.P. Project No. 351280
Resolution for Final Payment
It is respectfully recommended that the City Commission adopt the
attached resolution accepting the completed work performed by Man
Con, Inc. at a total cost of $532,246.41 for OVERTOWN/PARK WEST
SANITARY SEWER REPLACEMENT PROJECT C.I.P. Project No. 351280 and
authorizing a final payment of $54,820.66.
BACKGROUND:
The Department of Public Works has determined that it is now in
order for the Commission to accept the completed work and
authorize final payment, after all conditions are met for
Overtown/Park West Sanitary Sewer Replacement Project C.I.P.
Project No. 351280,
Man Con, Inc. has completed the project consisting of the
replacement of portions of an existing sanitary sewage system
using 8"-24" ESVC and DIP with all necessary appurtenances in an
area bounded by North Miami Avenue, N.W. 3 Avenue, N.W. 5-10
Streets.
The total payment to the contractor will be $58,721.59 less than
the original contract amount of S590,968.00 because not all of the
Cash Allowance for Special Items was used.
Attachments:
Proposed Resolution
35-1
88-512
PENAL CONMUCTION PACT SHEET
J08 NAME Overtown/Park West Sanitary Sewer Replacement 8=99�3
CONTRACTOR Man Con, Inc.
J68 SCOPE
Replacement of portions of an existing sanitary sewage
system using 8"44" ESVC and DIP with all necessary
appurtenances in an area bounded by North Miami Avenue,
N.W. 3 Avenue, N.W. 5-10 Streets.
REASON
Replacement of deteriorated sewer mains in conjunction
FOR WORK
with highway rebuilding.
SOURCE
Capital Improvements Ord. 10187, Project 351280
OF FUNDS
PROJECT
Bids Received: 7/21/87
HISTORY
Contract Awarded: 9/8/87
Preconstruction Meeting: 9/29/87
CONTRACT
TIME
STARTED
11/13/87
CONTRACT
TIME
100 Working days
SCHEDULED
COMPLETION
DATE
4/6/88
ACTUAL
COMPLETION
DATE
1/19/88
BID AMOUNT
b 590,968.00
CONTRACT
FINAL COST
$ 5323246.41
CURRENT
ITEM .FOR
Resolution to accept completed work and authorize
CONSIDERATION
final payment to the contractor.
813-510.