HomeMy WebLinkAboutR-88-06210 0
J-88-663
6/16/88
RESOLUTION NO.
A RESOLUTION ACCEPTING THE COMPLETED WORK
OF ROSE ENGINEERING, CONTRACTORS AT A TOTAL
COST OF $437,724.85 FOR LOCAL DRAINAGE
PROJECT E-56 C.I.P. PROJECT NO. 352232 AND
AUTHORIZING A FINAL PAYMENT OF $21,886.24.
WHEREAS, there exists a contract dated October 3, 1986
between the City of Miami and Rose Engineering Contractors;
and
WHEREAS, the work has been satisfactorily completed by
Rose Engineering Contractors and they have furnished the
required documents certifying that all bills for labor and
materials have been paid in full in connection with the
aforesaid contract; and
WHEREAS, the City Manager and the Director of the
Department of Public Works recommend that the completed work be
accepted and final payment made to the contractor;
NOW, THEREFORE, BE IT RESOLVED BY THE COMMISSION OF THE
CITY OF MIAMI, FLORIDA:
Section 1. The completed work performed by Rose
Engineering Contractors for LOCAL DRAINAGE PROJECT E-56 C.I.P.
Project No. 3522.32 at a total cost of $437,724.85 is hereby
approved.
Section 2. The proper officials of the City of Miami are
hereby authorized to pay $21,886.24 to Rose Engineering
Contractors as full and final payment for all work performed
and all materials furnished in connection with LOCAL DRAINAGE
PROJECT E-56 C.I.P. Project No. 352232.
CITY COMMISSION
MEETING OF
t
JUL 144 198o
RESOLUTION No. 138-621
0
0
PASSED AND ADOPTED this 14th day of July , 1988.
ATTES
i
i�
PREPARED AND APPROVED BY:
,e&4u,e-&Leelc
CHIEF DEPUTY CITY ATTORNEY
APPROVED AS TO FORM AND CORRECTNESS:
1
CIT ATTORN
APPROVED EXPENDITURE:
42
-v
FINA CE DEPARTMENT
BUDGETARY REVIEW:
MANAGEMENT WND BUDGET DEPARTMENT
CAPITAL PROJECT:
DIREClUT
ING DEPARTMENT
/111
- 2 -
47
CITY OF MIAM1. FLORIDA
INTER -OFFICE MEMORANDUM
�O
i U L �9a�
Honorable Mayor and Members
DATE FILE B-5523
of the City Commission
SUBJECT LOCAL DRAT-NAGE PROJECT E-56
-CIP Project No. 352232 -
Resolution for Final Payment
FROM
REFERENCES
GO Cesar H. O d i o I lip
ENCLOSURES
City Manager �t
RECOMMENDATION:
It is respectfully recommended that the City Commission adopt the
attached resolution accepting
the completed work performed by Rose
Engineering Contractors at a
total cost of $437,724.0-5 for LOCAL
DRAINAGE PROJECT E-56 C.I.P
Project No. 352232 and authorizing a
final payment of 521,886.24.
BACKGROUND:
The Department of Public Works has determined that it is now in
order for the Commission
to accept the completed work and
authorize final payment, after
all conditions are met for Local
Drainage Project E-56 C.I.P.
Project No. 352232.
Rose Engineering Contractors has completed the project consisting
of constructing drainage structures citywide including: 30"-36"
French drain, 2'-3' covered ditch, concrete, aluminum and ductile
iron pipe in various sizes, arch culvert pipe together with all
necessary appurtenances.
The total payment to the contractor will be less than the original
contract amount of $481,605.00 because riot all of the proposal
items were used.
Attachments:
Proposed Resolution
FINAL CONSTRUCTION FACT SHEET
JOB NAME Local Drainage Project E-56 9-5528
CONTRACTOR Rose Engineering Contractors
JOB SCOPE Construct drainage structures at locations citywide
includina: :10"-36" French drains, 2'-3' wide• covered
ditches,' miscellaneous aluminum, concrete and ductile
iron pipe in various sizes, arched culvert pipe along
with all necessary appurtenances.
REASON Eliminate drainage problems
FOR WORK.
SOURCE Local Drainage Projects - 1986
OF FUNDS
PROJECT Bids Received: 8/19/86
HISTORY Contract Awarded: 9/11/86
Preconstruction Meeting: 11/19/86
CONTRACT
TIME
STARTED 1/2/87
CONTRACT
TIME 150 Working days plus 10 days delay from rain
and 68 days delay from extra work
787 days total delay
SCHEDULED
COMPLETION
DATE 11/25/87
ACTUAL
COMPLETION
DATE 11/25/87
BID AMOUNT $ 481,605.00
CONTRACT
FINAL COST S 437,724.PS
CURRENT
ITEM FOR Resolution to accept completed work and authorize
CONSIDERATION final payment to the contractor.