HomeMy WebLinkAboutR-88-10623-88-1003
10/4/88
RESOLUTION NO.
A RESOLUTION ACCEPTING THE COMPLETED WORK
OF P.N.M. CORPORATION AT A TOTAL COST OF
$45,318.93 FOR CITYWIDE SANITARY SEWER
EXTENSION IMPROVEMENT - N.W. 5 AVENUE IN
CITYWIDE SANITARY SEWER EXTENSION
IMPROVEMENT DISTRICT - N.W. 5 AVENUE SR-
5546C (CENTERLINE) C.I.P PROJECT NO.
351274 AND AUTHORIZING A FINAL PAYMENT OF
$5,634.39
WHEREAS, there exists a contract dated February 24,
1988 between the City of Miami, Florida and P.N.M. Corporation
for CITYWIDE SANITARY SEWER EXTENSION IMPROVEMENT - N.W. 5
AVENUE in CITYWIDE SANITARY SEWER EXTENSION IMPROVEMENT
DISTRICT - N.W. 5 AVENUE SR-5546C (CENTERLINE) C.I.P. Project
No. 351274; and
WHEREAS, the work has been satisfactorily completed
and P.N.M. Corporation has furnished the required documents
certifying that all bills for labor and materials have been
paid in full in connection with the aforesaid contract; and
WHEREAS, the City Manager and the Director of the
Department of Public Works recommend that the completed work be
accepted and final payment made to the contractor;
NOW, THEREFORE, BE IT RESOLVED BY THE COMMISSION OF
THE CITY OF MIAMI, FLORIDA:
Section 1. The completed work performed by P.N.M.
Corporation for CITYWIDE SANITARY SEWER EXTENSION IMPROVEMENT -
N.W. 5 AVENUE in CITYWIDE SANITARY SEWER EXTENSION IMPROVEMENT
DISTRICT - N.W. 5 AVENUE SR-5546C (CENTERLINE) C.I.P. Project
No. 351274 is hereby accepted at a total cost of $45,318.93.
CITY COMMISSION
MEETING OF
NOV 3 1988
88-1062
SOLUTION No.
4 0
Section 2. The proper officials of the City of Miami
are hereby authorized to pay P.N.M. Corporation a balance of
$5,634.39 as full and final payment for all work performed and
all materials furnished in connection with CITYWIDE SANITARY
SEWER EXTENSION IMPROVEMENT - N.W. 5 AVENUE in CITYWIDE
SANITARY SEWER EXTENSION IMPROVEMENT DISTRICT SR-5546C
(CENTERLINE) C.I.P Project No. 351274.
PASSED AND ADOPTED this 3rd day of November ,
1988.
ATTEST,
1 PREPARED AND APPROVED BY:
CHIEF DEPUTY CITY ATTORNEY
APPROVED AS TO FORM AND CORRECTNESS:
ANUEZ
CIT ATTORNE
APPR D EXPENDITURE:
CARLZA E. GARCIA, DIRECTOR
FINAN DEPARTMENT
BUDGETARY REV E
MANU
d�
BUD D ARTMENT
CAPITAL PROJECT:
SE PLA G DEPARTMENT
A A
CITY OF MIAMI, FLORIDA
INTER -OFFICE MEMORANDUM
To Honorable Mayor and Members
of the City Commission
FRQM1-, Cesar H. Odio
+& City Manager
RECOMMENDATION:
71
DATE 0 C I 2 4 1968 FILE B- 5 5 4 6
SUBJECT CITYWIDE SAN. SEWER EXT. IMP.
-N.W. 5 AVE. IN CITYWIDE SAN.
SEWER EXT. IMP. DISTRICT- NW
REFERENCES 5 AVE SR-5546C (CENTERLINE)
C.I.P. Project No. 351274
ENCLOSURES: Resolution for Final Payment
It is respectfully recommended that the City Commission adopt the
attached resolution accepting the completed work performed by
P.N.M. Corporation at a total cost of $45,318.93 for CITYWIDE
SANITARY SEWER EXTENSION IMPROVEMENT - N.W. 5 AVENUE in CITYWIDE
SANITARY SEWER EXTENSION IMPROVEMENT DISTRICT - M.W. 5 AVENUE SR-
5546C (CENTERLINE) C.I.P. Project No. 351274 and authorizing a
final payment of $5,634.39.
BACKGROUND:
The Department of Public Works has determined that it is now in
order for the Commission to accept 'the completed work and
authorize final payment, after all conditions are met for CITYWIDE
SANITARY SEWER EXTENSION IMPROVEMENT - N.W. 5TH AVENUE in CITYWIDE
SANITARY SEWER EXTENSION IMPROVEMENT DISTRICT - N.W. 5 AVENUE SR-
5546C (CENTERLINE) C.I.P. Project No. 351274.
P.N.M. Corporation has completed the project consisting of
constructing 585' of 8" extra strength clay pipe, 112' of 6" extra
heavy cast iron house laterals together with all necessary
appurtenances in N.W. 5 Avenue between N.W. 33-35 Streets.
The total payment to the contractor will be $5,368.57 less than
the original contract amount of $50,687.50 because $4,275.00 in
proposal items were not used and $1,O93.57 of the $5,000 Cash
Allowance for Special Items were not used.
Attachments:
Proposed Resolution
FINAL CONSTRUCTION FACT SHEET
JOB NAME CITYWIDE SANITARY SEWER EXTENSION IMPROVEMENT N.W. 5
AVENUE - B-5546
CONTRACTOR P.N.M. Corporation
JOB SCOPE Construct 585' of 8" extra strength clay pipe, 112' of
b" extra heavy cast iron house laterals together with
all necessary appurtenances in N.W. 5 Avenue between
N.W. 33-35 Streets.
REASON Provide sanitary sewers to previously unsewered
FOR WORK properties.
SOURCE 1988 Capital Improvement Ordinance No. 10347
OF FUNDS Project No. 351274
PROJECT Bids Received: 12/10/87
HISTORY Contract Awarded: 1/14/88
Preconstruction Meeting: 3/16/88
CONTRACT
TIME
STARTED 4/22/88
CONTRACT
TIME 30 Working days
SCHEDULED
COMPLETION
DATE
6/3/88
ACTUAL
COMPLETION
DATE
5/12/88
BID AMOUNT
$50,687.50
CONTRACT
FINAL COST
$45,318.93
CURRENT
ITEM FOR
Resolution to accept completed work and authorize
CONSIDERATION final payment to the contractor.
� 2