A RESOLUTION ACCEPTING THE COMPLETED WORK OF
MARKS BROTHERS COMPANY AT A TOTAL COST OF
$11,000.00 FOR STORM SEWER REPAIR -EAST
FLAGLER STREET CIP PROJECT NO. 352251 AND
AUTHORIZING A FINAL PAYMENT OF $2,000.00.
WHEREAS, there exists a contract dated April 12, 1988
between the City of Miami, and Marks Brothers Company; and
WHEREAS, the work has been satisfactorily completed by Marks
Brothers Company and they have furnished the required documents
certifying that all bills for labor and materials have been paid
in full in connection with the aforesaid contract; and
WHEREAS, the City Manager and the Director of the Department
of Public Works recommend that the completed work be accepted and
final payment made to the contractor;
NOW, THEREFORE, BE IT RESOLVED BY THE COMMISSION OF THE CITY
OF MIAMI, FLORIDA:
Section 1. The completed work performed by Marks Brothers
Company for STORM SEWER REPAIR -EAST FLAGLER STREET C.I.P. Project
No. 352251 at a total cost of $11,000.00 is hereby approved.
Section 2. The proper officials of the City of Miami are
hereby authorized to pay $2,000.00 to Marks Brothers Company as
full and final payment for all work performed and all materials
CITY COMMISSION.
MEETING OF
NOY s 1998
MARK&
furnished in connection with STORM SEWER REPAIR -EAST FLAGLER
STREET C.I.P. PROJECT N0. 352251.
PASSED AND ADOPTED this 3rd day of November 1988,
PREPARED AND APPROVED BY:
91X^ lrl
ROBERT F. CLARK
CHIEF DEPUTY CITY ATTORNEY
BUDGETARY REVIEW:
N H AN , DIRIETTM
DEPAR ENT OF BUDGET
10
JECT:
G R R , E
PLANNING DEPARTMEN
APPROVED AS TO FORM AND CORRECTNESS: APPROYBD EXPENDITURE:
AJOG. NDCARLU GARCIA, DIRECTOR
CITY A TO EY FINANCE DEPARTMENT
-2-
FINAL CONSTRUCTION FACT SHEET
JOB NAME STORM SEWER REPAIR - EAST FLAGLER ST. - B-5550
CONTRACTOR Marks Brothers Company
JOB SCOPE Installation of protective concrete slab over existing
concrete box culvert, repair of sanitary sewer lateral.
REASON Emergency repairs to correct an unsafe condition due to
FOR WORK cave in of a box storm sewer.
SOURCE G.O.B. - Local Drainage Projects - FY 88 Account
OF FUNDS
PROJECT Bids Received: 2/22/88 (Emergency Bid)
HISTORY Contract Awarded: 3/10/88
Preconstruction Meeting: None
CONTRACT
TIME
STARTED 2/26/88
CONTRACT
TIME N/A
SCHEDULED
COMPLETION
DATE 3/1/88
ACTUAL
COMPLETION
DATE 3/1/88
BID AMOUNT $11,000.00
CONTRACT
FINAL COST $11,000.00
CURRENT
ITEM FOR Resolution to accept completed work and authorize
CONSIDERATION final payment to the contractor.
CITY OF MIAM1, FLORIDA
INTER -OFFICE MEMORANDUM
TO Honorable Mayor and Members
of the City Commission
FROM
Cesar H. Odio
City Manager
RECOMMENDATION:
17
DATE: G C T 2 4 1988 "LE: B-5 5 50
SUBJECT- STORM SEWER REPAIR - EAST
FLAGLER ST. CIP PROJECT
No. 352251 Resolution for
REFERENCES: Final Payment
ENCLOSURES:
It is respectfully recommended that the City Commission adopt the
attached resolution accepting the completed work performed by
Marks Brothers Company at a total cost of $11,000.00 for STORM
SEWER REPAIR -EAST FLAGLER STREET C.Z.P. Project No. 352251 and
authorizing a final payment of $2,000.00.
BACKGROUND:
The Department of Public Works has determined that it is now in
order for the Commission to accept the completed work and
authorize final payment for STORM SEWER REPAIR -EAST FLAGLER
STREET C.I.P. Project No. 352251.
Marks Brothers Company has completed the project consisting of
removal of existing concrete pavement, repair of existing storm
sewer box culvert, placement of 1211 thick concrete slab on East
Flagler Street.
The total payment to the contractor will be $11,000.00, the
original contract amount.