HomeMy WebLinkAboutR-89-0558J-89-528
5/2/89
RESOLUTION NO. fi49_5 39
A RESOLUTION ACCEPTING THE COMPLETED WORK OF
MIRI CONSTRUCTION, INC. AT A TOTAL COST OF
$1,807,040.90 FOR MANOR HIGHWAY IMPROVEMENT -
PHASE IV CIP PROJECT NO. 341119 AND
AUTHORIZING A FINAL PAYMENT OF $174,763.95
WHEREAS, there exists a contract dated October 29, 1987
between the City of Miami, Florida and Miri Construction, Inc.
for MANOR HIGHWAY IMPROVEMENT - PHASE IV C.I.P. Project No.
341119; and
WHEREAS, the work has been satisfactorily completed by
Miri Construction, Inc. and they have furnished the required
documents certifying that all bills for labor and materials have
been paid in full in connection with the aforesaid contract; and
WHEREAS, the City Manager and the Director of the
Department of Public Works recommend that the completed work be
accepted and final payment made to the contractor;
NOW, THEREFORE, BE IT RESOLVED BY THE COMMISSION OF THE
CITY OF MIAMI, FLORIDA.-
Section 1. The completed work performed by Miri
Construction, Inc. for MANOR HIGHWAY IMPROVEMENT - PHASE IV
C.I.P. Project No. 341119 is hereby accepted at a total cost of
$1,807,040.90.
Section 2. The proper officials of the City of Miami are
hereby authorized to pay Miri Construction, Inc. a balance of
$174,763.95 as full and final payment for all work performed and
all materials furnished in connection with MANOR HIGHWAY
IMPROVEMENT - PHASE IV C.I.P. Project No. 341119.
CITY COMMISSION
MEETING OF
JUN 7
pp1989
NE
c
Section ?. This Resolution shall become effective
immediately upon its adoption pursuant to law.
PASSED AND ADOPTED this 7th day of June ,
1989.
ATTES .
MATTY s
PREPARED AND APPROVED BY:
CHIEF DEPUTY CITY ATTORNEY
APPROVED AS TO FORM AND CORRECTNESS:
FERN NDE
CIT ATTORN Y
CAPITAL BUDGET REVIEW:
C�VF --
ET—
CAPITAL IMPROVEME14T MA14AGER
—2—
I
E
o
34
CITY OF MIAMI. FLORIDA
INTER -OFFICE MEMORANDUM
iO Honorable Mayor and Members °ATE. R FILE 1-4111
of the City Commission MAY 1 ����
SUBJECT : MANOR HIGHWAY IMPROVEMENT -
_ PHASE IV 1=
C.I.P. PROJECT #341119 _
FRO REFERENCES: Resolution for Final Payment
Cesar H. Od a=
City Manage ENCLOSURES: i-
I—
f—
RECOMMENDATION:
It is respectfully recommended that the City Commission adopt the
attached resolution accepting the completed work performed by Miri
Construction, Inc. at a total cost of $1,807,040.90 for' MANOR
HIGHWAY IMPROVEMENT - PHASE IN C.I.P. Project No. 341119 and
authorizing a final payment of $174,763.95.
BACKGROUND: �_
The Department of Public Works has determined that it is now in
order for the Commission to accept the completed work and
authorize final payment, after all conditions are met for Manor
Highway Improvement - Phase IV C.I.P. Project No. 341119.
Miri Construction, Inc. has completed the. project of constructing
3.4 miles of streets including: clearing and grading, new
asphaltic pavement,. concrete curbs and/or gutters, concrete
sidewalk, storm sewers and landscaping in area bounded by N.W. 12-
17 Avenues between N.W. 50-54 Streets.
_ The total payment to the contractor will be $131,679.60 less than
the original contract amount of $1,938,720.50 because not all of
the Cash Allowance for Special Items was used.
Attachments:
Proposed Resolution
' A S
FINAL CONSTRUCTION FACT SHEET
JOB NAME Manor Highway Improvement - Phase IY - B-4519
CONTRACTOR Miri Construction, Inc.
JOB SCOPE Construct 3.4 miles of streets including: clearing and
grading, new asphaltic pavement, concrete curbs and/or
gutters, concrete sidewalk, storm sewers and landscaping
i-n area bounded by N.W. 12-17 Avenues between N.W. 50-54
Streets.
REASON Eliminate drainage problems, streets out of grade and
FOR WORK deteriorated side parkways.
SOURCE Capital Improvement Ordinance, project #341119
OF FUNDS
PROJECT Bids Received: 7/9/87
HISTORY Contract Awarded: 9/8/87
Preconstruction Meeting: 10/28/87
CONTRACT
TIME
STARTED 12/14/87
CONTRACT
TIME 220 Working days plus 15 days delay from rain
SCHEDULED
COMPLETION
DATE
11/16/88
ACTUAL
COMPLETION
DATE
11/11/88
BID AMOUNT
$1,938,720.50
CONTRACT
FINAL COST
$1,807,040.90
CURRENT
ITEM FOR
Resolution to accept completed work and authorize final
CONSIDERATION payment to the contractor.