HomeMy WebLinkAboutItem #52 - Discussion Item28 CIT , OF ' ' r,'., . F._0::',L);.
INTER -OFFICE MEMORA14DUM
TO Honorable Mayor and Members DATE �;�+.'; i ,, �•.
B-2983-
of the Citv Commission
FRo%! ee�
Cesar H. Odio
City Manager
RECOMMENDATION
It is respectfully recommended that
attached Resolution authorizing an
to exceed $25,000, in the contract
Urban Constructors, Inc. for the
Fieldwork Project B-29 83-H; and
Manager's written finding that
emergency circumstances.
BACKGROUND
SUBJECT Curtis Park Redevelopment -
Fieldwork Project
INCREASE IN CONTRACT
REFERENCES
ENCLOSURES
the City Commission adopt the
increase in the contract not
between the City of Miami and
Curtis Park Redevelopment -
further ratifying the City
the increase resulted from
The Department of Public Works and the Department of Parks and
Recreation, in an effort to serve all residents of the City of
Miami, have determined that it is now appropriate and in order
for the City Commission to ratify the City Manager's decision to
increase the existing contract dated December 17, 1991, between
the City and Urban Constructors, Inc. for Curtis Park
Redevelopment -Fieldwork Project (Second Bidding) in an amount not
to exceed $25,000 for necessary extra work, and to ratify the
City Manager's emergency finding that allowed the extra work to
continue.
The City Commission awarded a contract to Urban Constructors,
Inc. for the construction of Curtis Park Redevelopment -Fieldwork
Project (Second Bidding), Project No.331353, on October 3, 1991.
Generally, the project consisted of the construction of track and
field event amenities including miscellaneous park improvements.
As the project progressed, the need for additional work beyond
the original scope of the project became apparent. The
additional work is outlined below:
1. Installation of a temporary chain link fence around the
perimeter of the running track was needed to protect the new
track surface from vandals and other construction activity
until the facility was officially turned over to the City.
-A
- 1 - 92- 413-A
Honorable Mayor and Members
of the City Commission
2. Extra compacted fill material and grading were needed under
the east (home side) bleachers and at the site of the new
restroom facility on the visitors' side.
3. Additional compacted fill material and grading were needed
at the southeast corner of the park to accommodate the
proposed walkway area leading from N. River Drive to the new
sports field.
U. Construction of two concrete walls and footings were added
to the contract to accommodate the F•iblic address control
panels which will be installed by others at a future date.
5. In order to accelerate completion of the project that the
dedication ceremony scheduled by the Ccmmissiocould be
held, the contractor was paid "premium time" labor rates for
overtime and weekend work.
6. The cost of renting a crane was authorized to lift new sod
across the running track for the January 16, 1992 dedication
ceremony. The new track surface was curing concurrent with
the placement of the sod. Heavy vehicles required to
transpo-t the sod could not be driven across the track until
the surface had cured completely.
None of the items described above were included in the original
scope of work. Failure to correct these problems could have
endangered the health, safety and welfare of our citizens. It
was decided that the most cost effective and expeditious manner
to address all of these problems was to allow the contractor
already working on the project, Urban Constructors, Inc., to
accomplish the extra work.
The increase in contract to cove- all of the aforementioned extra
work will not exceed $25,000. Funds for the increase are
available from monies already appropriated to the project in the
City's Capital Improvement Appropriation Ordinance No. 10938,
Project No. 331353•
— 2 —
92- 413•A
.
0
Z
CITY OF KIWI i. FLOAiDA
• INTER -OFFICE MEMORANDUM
r0 File DATE
SUBJECT
:a ;• REcERENCES
Cesar H . Od i o ENCLOSURES
City Manager
April 27, 1992 = _-B-2983-H
EMERGENCY FINDING
Curtis Park Redevelopment -
Fieldwork Project
Increase In Project Scope
Based on information supplied to me by the Director of the
Department of Public Works, I have found that an emergency
existed justifying the authorization for Urban Constructors, Inc.
to undertake additional work at the Curtis Park Redevelopment -
Fieldwork Project beyond the original scope of their contract.
The reasons for the emergency need and subsequent authorization
to perform additional work are as follows:
The City Commission awarded a contract to Urban Constructors,
Inc. for the construction of Curtis Park Redevelopment -Fieldwork
Project (Second Bidding), Project No. 331353, on October 3, 1991.
Generally, the project consisted of the construction of track and
field event amenities including miscellaneous park improvements.
As the project progressed, the need for additional work beyond
the original scope of the project became apparent. The
additional work is outlined below.
1. Installation of a temporary chain link fence around the
perimeter of the running track was needed to protect the new
track surface from vandals and other construction activity
until the facility was officially turned over to the City.
2. Extra' compacted fill material and grading was needed under
the east (home side) bleachers and at the site of the new
restroom facility on the visitors' side.
3. Additional compacted fill material and grading was needed
at the southeast corner of the park to accommodate the
proposed walkway area leading from N. River Drive to the new
sports field.
- 1 -
92- 413.A
3
A
File
4. Construction of two concrete walls and footings were added
to the contract to accommodate the public address control
panels which will be installed by others at a future date.
5. In order to accelerate completion of the project so that the
dedication ceremony scheduled by the Commission could be
held, the contractor was paid "premium time" labor rates for
overtime and weekend work.
6. The cost of renting a crane was authorized to lift new sod
across the running track for the January 16, 1992 dedication
ceremony. The new track surface was curing concurrent with
the placement of the sod. Heavy vehicles required to
transport the sod could not be driven across the track until
the surface had cured completely.
None of the items described above were included in the original
scope of work. Failure to correct or address these problems
could have endangered the health, safety and welfare of our
citizens. It was decided that the most cost effective and
expeditious manner to address all of these problems was to allow
the contractor already working on the project, Urban
Constructors, Inc., to accomplish the extra work.
The increase in contract to cover all of the aforementioned extra
work will not exceed $25,000. Funds for the increase are
available from monies already appropriated to the project in the
City's Capital Improvement Appropriation Ordinance No. 10938,
Project No. 331353.
cc: Eduardo Rodriguez, CIP
— 2 —
92- 413•,2