RESOLUTION NO. "`� $ 8
A RESOLUTION AUTHORIZING AN INCREASE, IN AN
AMOUNT NOT TO EXCEED $5,300.00, IN THE
CONTRACT BETWEEN THE CITY OF MIAMI, FLORIDA,
AND LEWIS GREEN CONSTRUCTION, INC., DATED
OCTOBER 16, 1991, FROM $89,700.00 TO
$95,000.00, FOR THE SCATTERED SITE HOUSING -
COCONUT GROVE PHASE I (THIRD BIDDING)
B-3241-A, CAPITAL IMPROVEMENT PROJECT NO.
321034; AUTHORIZING AN INCREASE, IN AN AMOUNT
NOT TO EXCEED $540.00, IN THE CONTRACT
BETWEEN THE CITY OF MIAMI, FLORIDA, AND LEWIS
GREEN CONSTRUCTION, INC., DATED OCTOBER 23,
1991, FROM $94,460.00 TO $95,000.00, FOR THE
SCATTERED SITE HOUSING -MODEL CITY PHASE IV,
B-3242-A, CAPITAL IMPROVEMENT PROJECT NO.
321034; AUTHORIZING AN INCREASE, IN AN AMOUNT
NOT TO EXCEED $3,000.00, IN THE CONTRACT
BETWEEN THE CITY OF MIAMI, FLORIDA, AND LEWIS
GREEN CONSTRUCTION, INC., DATED FEBRUARY 12,
1992, FROM $92,000.00 TO $95,000.00, FOR THE
SCATTERED SITE HOUSING HOME OWNERSHIP
DEVELOPMENT PROGRAM-WYNWOOD, PHASE II,
B-3245, CAPITAL IMPROVEMENT PROJECT NO.
321034; AUTHORIZING SAID FUNDS TO BE PROVIDED
FROM CAPITAL IMPROVEMENT ORDINANCE NO. 10938
FUNDS ALREADY APPROPRIATED TO SAID PROJECT;
FURTHER RATIFYING THE CITY MANAGER'S WRITTEN
FINDING, BY AN AFFIRMATIVE VOTE OF 4/5THS OF
THE MEMBERS OF THE CITY COMMISSION, THAT THE
HEREIN INCREASES RESULTED FROM EMERGENCY
CIRCUMSTANCES.
WHEREAS, there exists a contract dated October 16, 1991,
between the City of Miami, Florida, and Lewis Green Construction,
Inc., for Scattered Site Housing, Coconut Grove Phase I (Third
Bidding), B-3241-A, Capital. Improvement Project No. 321034; and
CM comnssion
wEi'mTG OF
{ Resolution No.
'�' �i
x
WHEREAS, there exists a contract dated October 23, 1991,
between the City of Miami, Florida and Lewis Green Construction,
i
Inc., for Scattered Site Housing, Model City, Phase IV, B-3242-A,
Capital Improvement Project No. 321034; and
WHEREAS, there exists a contract dated February 12, 1992,
between the City of Miami, Florida and Lewis Green Construction,
Inc. for Scattered Site Housing,
S ousi g, Homeownership Development
Program, Wynwood Phase II, B-3248, Capital Improvement Project
No. 321034; and
WHEREAS, increases, in an amount not to exceed the combined
total of $8,840, for all three of the aforesaid contracts are
required to cover the cost of necessary extra work involving
unforeseen theft, vandalism and other security problems;
replacement of deteriorated sidewalk, curb and gutters not
included in the original contracts; revisions to window
specifications to satisfy building code requirements; clearing 1
and hauling illegally dumped debris from the project sites;
S
revisions to the architect's original plans for electrical
service to the sites; and an increase in building material costs
since the acceptance of bids by the City Commission; and 3
WHEREAS, the Director of Public Works, the Director of the i
Development & Housing Conservation Department, and the City J
Manager recommend the increases in said contracts to cover the
additional costs; and
WHEREAS, the City Manager has made a written finding that a
valid emergency existed for the work to continue to protect the
health, safety and welfare of the citizens of the City; and
-2- 93- 548
WHEREAS, funs to cover the contract increases are available
from monies already appropriated to the said projects;
NOW, THEREFORE, BE IT RESOLVED BY THE COMMISSION OF THE CITY
OF MIAMI, FLORIDA:
Section 1. After a properly advertised Public Hearing,
the findings of the City Manager set forth in the Preamble to
this Resolution are hereby ratified by an affirmative vote of
4/5ths of the City Commission, and are hereby incorporated by
reference thereto and adopted as if fully set forth in this
Section.
Section 2. The contract between the City of Miami and
Lewis Green Construction, Inc., dated October 16, 1991, for
Scattered Site Housing, Coconut Grove, Phase I (Third Bidding),
B-3241-A, Capital Improvement Project No. 321034, is hereby
increased in an amount not to exceed $5,300.00 from $89,700.00 to
$95,000.00, with funds for the increase to be provided from
monies already appropriated to said project.
Section 3. The contract between the City of Miami and
Lewis Green Construction, Inc., dated October 23, 1991, for
Scattered Site Housing, Model City, Phase IV, B-3242-A, Capital
Improvement Project No. 321034, is hereby increased in an amount
not to exceed $540.00, from $94,460.00 to $95,000.00, with funds
for the increase to be provided from monies already appropriated
to said project.
Section 4. The contract between the City of Miami and
Lewis Green Construction, Inc., dated February 12, 1992, for
Scattered Site Housing, Homeownership Development Program Wynwood
-3- 9 3 - � :!g
Phase II, B-3245, Capital Improvement Project No. 321034, is
hereby increased in an amount not to exceed $3,000.00, from
$92,000.00 to $95,000.00, with funds for the increase to be
provided from monies already appropriated to said project.
Section 5. This Resolution shall become effective
immediately upon its adoption.
PASSED AND ADOPTED this 7th day of September 1993.
XAVIER L. SUAREZ MAYOR
ATT T'
MATEY HIRAI
CITY CLERK
CAPITAL PROJECT REVIEW:
EDUAADO RODIGUtZ
CAPITAL IMPROVEMENT MANAGER
DEPARTMENT OF DEVELOPMENT AND
#OUSING COOS-ERVATION REVIEW:
ERY � HEPBURN
STANT DIRECTOR
PREPARED AND APPROVED BY:
CARMEN L. LEON
ASSISTANT CITY ATTORNEY
CLL:csk:M3808
SUBMITTED BY:
W Cam, Lx,
WALDEMAR E. LEE
DIRECTOR OF PUBLIC WORKS
APPROVED AS TO FORM AND
CORRECTNESS:
. U
A. Q TN 0 S, III
CITY ATT R Y
-4- 93- 548
n
CITY OF MIAMI, FLORIDA 29
INTER -OFFICE MEMORANDUM
To Honorable Mayor and
Members of the City Commission
PATE AUG 2 61993 FILE
SU&IECT Scattered Site Housing --
Coconut Grove Phase I (Third
Bidding), Model City Phase IV
and Wynwood Phase II
FROM REFERENCES Increase In Contracts
Cesar io
City g e r ENCLOSURES
RECOMMENDATION
It is respectfully recommended that the City Commission adopt the
attached Resolution authorizing increases in the contracts
between Lewis Greer, Construction, Inc. and the City of Miami for
Scattered Site Housing --Coconut Grove Phase I (Third Bidding), not
to exceed $5,300; for Scattered Site Housing -Model City Phase IV,
riot to exceed $540; and for Scattered Site Housing Homeownership
Development Program--Wyndwood Phase II not to exceed $3,000; and
further ratifying the City Manager's written finding that the
increases resulted from emergency circumstances.
BACKGROUND
The Department of Public Works, in an effort to serve all
residents of the City of Miami, has determined that it is now
appropriate and in order for the City Commission to ratify the
City Manager's decision to increase three existing contracts
dated October 16, 1991, October 23, 1991, and February 12, 1992,
between the City and Lewis Green Construction, Inc, for
construction of Scattered Site Housing --Coconut Grove Phase I
(Third Bidding), Model City Phase IV and Wynwood Phase II, in the
total amount not to exceed $8,840 for all three contracts for
necessary extra work, and to ratify the City Manager's emergency
finding that allowed the extra work to continue on all three
projects.
The City Commission awarded contracts to Lewis Green
Construction, Inc. for the construction of Scattered Site
Housing -Coconut Grove Phase I (Third Bidding) on July 11, 1991 in
the amount of $89,700; for Scattered Site Housing --Model City
Phase IV on July 11, 1991 in the amount of $94,460; and for
Scattered Site Housing Homeownership Development Program--Wynwood
Phase II on November 14, 1991 in the amount of $92,000.
Generally, the projects consisted of the construction of two,
three --bedroom, two --bathroom, single-family residences in each
project, for a total of six residences, on City owned scattered
housing sites. As the construction progressed, some unexpected
conditions developed for the small --firm contractor which affected
the construction costs. These conditions are outlined below:
07 93 - 548
1. The scattered site locations had unforeseen, security
problems which in many instances required the contractor to
replace and redo phases of the work due to vandalism and
theft.
2. Several locations required sidewalk and curb and gutter
replacement work that was not anticipated by the contractor.
3. Window specifications were revised to satisfy building code
requirements which resulted in extra costs for the houses.
4. Site clearing and haul. -off of illegally dumped debris were
required for some of the locations.
5. Building material. costs escalated and increased for the
contractor since being awarded the contracts.
6. Electric service to the houses had to be revised from that
originally shown on the architect's plans.
7. Several locations required a zoning variance which delayed
the start of construction. This resulted in an additional
building permit review of plans and specifications.
The above items caused delays in the scheduled completion of the
houses. The City was allocated specific surtax mortgage
financing for the prospective home buyers. Work on the subject
houses was underway, and in several cases, prospective buyers
were identified when the contractor requested additional monies
to complete the houses. Further delays in construction would
impact the prospective buyers and place the City at risk of
having Dade County's Documentary Surtax Advisory Board rescinding
mortgage funds. It was decided that the most cost effective and
expeditious manner to address all of the above problems was to
allow Lewis Green Construction, Inc. to proceed with the extra
work and complete the construction of the houses as soon as
possible.
Funds are available for the aforesaid contract increases
totalling $8,840 from monies already appropriated to the project
in the City's Capital Improvement Appropriate Ordinance No.
10938, Project No. 321034.
DCB:au
�a
CITY OF MIAMI, FLORIDA
' INTER -OFFICE MEMORANDUM
B--3241-A
TO : Matty Hirai
DATE July 19, 1993 F"E B -3242 -A
City Clerk
B 3L45
SUBJECT SCATTERED SITE HOUSING -.COCONUT
GROVE PHASE I, MODEL'. CITY PHASE
11
IV, and WYNWOOD PHASE II
FROM:
REFERENCES Increase In Contracts
Waldemar E. Lee
Request to Publish Notice for
Director of Public Works
ENCLOSURES Public Hearing
I
Please make arrangements to
publish a Notice of Public Hearing
for objections to a proposed
increase in the contracts with Lewis
Green Construction, Inc. for construction of Scattered Site
Housing --Coconut Grove Phase
I (Third Bidding), Scattered Site
Housing --Model City Phase
TV, and Scattered Site Housing
Homeownership Development
Program--Wynwood Phase II for the
Commission Meeting of September 9, 1993.
DCB:au
Approved:
urelio Perez--Lugones
Legislative Administrator
cc: City Clerk
Tax & License
Cost Analysis
Contract B-3241--A
Contract B-3242-A
Contract B--3245
3
93- 548
CITY OF MIAMI, FLORIDA
NOTICE TO THE PUBLIC
A public hearing will be held by the Commission of the City
of Miami, Florida, on September
9„ 1993, at a.m. in the
City Commission Chambers at City
Hall, 3500 Pan American Drive,
Miami, Florida, for the purpose
of hearing any objections from
any interested parties affected
by an increase in the contract
between Lewis Green Construction,
Inc. and the City of Miami in
an amourit not to exceed $5,300
for necessary extra work at
Scattered Site Housing -Coconut Grove
Phase I (Third Bidding) B--
3241-A, Project No. 321034; by
an increase in the contract
between Lewis Green Construction,
Inc. and the City of Miami in
an amount not to exceed $540
for necessary extra work at
Scattered Site Housing --Model City
Phase IV 8--3242---A, Project No.
321034; and by an increase in the contract between Lewis Green
Construction, Inc. and the City
of Miami in an amount to to
exceed $3,000 for necessary extra
work at Scattered Site Housing
Homeownership Development Program-Wynwood
Phase II B-3245,
Project No. 321034; and in ratifying the City Manager's finding
that the aforesaid increases
resulted from emergency
circumstances.
All interested persons are
invited to appear and may be
heard concerning these items. Should any person desire to appeal
any decision of the City Commission with respect to any matter
considered at this hearing, that person shall ensure that a
verbatim record of the proceedings is made, including all
testimony and evidence upon which any appeal may be based.
(City Seal) Matty Hirai
City Clerk
Miami, Florida
J3-- 548